Procurement Summary
State: Uttar Pradesh
Summary: Design, Supply, Erection, Testing & Commissioning of 25 Kv, 50 Hz Single Phase Ac Ohe in Connection with the Following Works over Lucknow Division of Northern Railway: (I) Conversion of Barsethi Halt....
Deadline: 08 Jun 2026
Posting Date: 16 May 2026
Other Information
Notice Type: Tender
TOT Ref.No.: 141392206
Document Ref. No.: 154-Dy-CEE-C-LKO-2026-27
Financier: Self Financed
Purchaser Ownership: Public
Document Fees: Refer Document
Tender Value: ₹ 100182281.85
EMD: ₹ 2003700.00
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_details
Login to see detailsTender Details
Design, Supply, Erection, Testing & Commissioning of 25 KV, 50 Hz Single Phase AC OHE in connection with the following works over Lucknow Division of Northern Railway: (i) Conversion of Barsethi Halt into Crossing station. (ii) Conversion of Salkhapur halt into Crossing station. (iii) Provision of New 1x25 KV SSP at Varanasi Station one at Kashi End and One at Lohta End along with associated Modification works in OHE
SUPPLY (Material) 2 Please see Item Breakup for details. 1106664.40 139.69 2652563.90
Contract Type : Works - General
Tender Type : Open
Advertised Value : 100182281.85
Bidding Style : [ Decision at Schedule level ]
Bidding System : Two Packet System
Pre-Bid Required : No
Pre-Bid Query Date Time :
Tendering Section : TENDER
Bidding Unit :
Publishing Date / Time : 15/05/2026 12:03
Period Of Completion : 18 Months
Bidding Start Date : 25/05/2026
Closing Date Time : 08/06/2026 15:00
Validity of Offer ( Days) : 90
Are Joint Venture (JV) firms allowed to bid : Yes
Tender Doc. Cost (Rs.) : 0.00
Earnest Money (Rs.) : 2003700.00