Expired Tender Burkina Faso ICB TOT Ref. 42088402

Supervision and Control of (I) Construction Works Tender - 42088402

Tender notice from Burkina Faso, published on 09 Apr 2020.

Exeutive Summary

The SOCIETE NATIONALE D’ELECTRICITE DU BURKINA has issued a Tender notice for the procurement of a Supervision and Control of (I) Construction Works the 90 Kv Loop in the Burkina Faso. This Tender notice was published on 09 Apr 2020 and is scheduled to close on 15 Apr 2020, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 42088402, while the tender notice number is 001/2020 / PR-RNI and Register on the platform.

Key facts

Summary
Supervision and Control of (I) Construction Works the 90 Kv Loop
TOT Ref. No.
42088402
Document Ref. No.
001/2020 / PR-RNI
Country
Burkina Faso
Notice type
Tender
Competition
ICB
Publication date
09 Apr 2020
Bid deadline
15 Apr 2020
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Tenders are invited for Supervision and Control of (I) Construction Works the 90 Kv Loop from Ouagadougou and (Ii) the 90 Kv Crossing of the Zagtouli- Line Koudougou
purpose of the project is to strengthen the evacuation system of the national interconnected

network (RNI) by closing the 90 kV loop from Ouagadougou and switching the Zagtouli-Koudougou

line to 90 kV. The works consist of: - The construction of a 90 kV double-circuit line with a length of

around 17 km between the existing 90/33/15 kV substation in Kossodo and the 90/33 kV substation

to be built on the site of the future 330/225/90/33 kV substation at Ouaga Est; - The construction of

a double-circuit 90 kV line with a length of approximately 25 km between the 90/33 kV substation to

be built on the site of the future 330/225/90/33 kV substation in Ouaga East and the 132 substation

/ 90/33/15 kV of the Paw of the Goose; - The extensions of the existing 90 kV substations in Kossodo

and the Goose Leg as well as the construction of the 90/33 kV substation in Ouaga East; - The

construction of a 90/33 kV substation in Koudougou and the extension of the 90 kV substation in

Zagtouli; - The construction of a dull single-line 90 kV line extending the Zagtouli-Koudougou line by

about 3 km to the site of the 90/33 kV substation to be built; - Replacement on the existing 90 kV

frame line between Zagtouli and Koudougou of the old guard cable with a fiber optic guard cable;

Without being limiting, the Consultant services include the following activities: - Coordination,

supervision, work management and monitoring of contracts; - Technical control of execution studies;

- Control, testing and acceptance during manufacturing; - Control of the execution of works on the

site; - Control at the end of works; - Assistance during the warranty period; - Preparation of reports.
The minimum score of 70 points is required to be retained on the shortlist. Interested candidates

can obtain additional information on the reference documents at the following address from 8:00

a.m. to 12:00 p.m. and 1:00 p.m. and 4:00 p.m. (GMT): Attention: Raouda OUEDRAOGO Project

Manager for Strengthening the National Interconnected Network avenue du Président Thomas

SANKARA Floor / office number: Mezzanine, BIRGUI building, City: Ouagadougou Postal code: 01 BP

54 Ouagadougou 01 Country: BURKINA FASO Telephone number: 00226 25 48 37 82 Fax number:

00226 25 31 03 40 10 Expressions of interest must be written in French. The expression of interest

files in four (4) copies (1 original and 3 copies) as well as a digital copy will be deposited at the

following address: Société Nationale d`Electricité du Burkina (SONABEL) 55 Avenue de la Nation 3rd

Floor / Office N ° 88 OUAGADOUGOU 01 BP 54 OUAGADOUGOU 01 BURKINA FASO Telephone: +226

25 30 61 00 Fax: +226 25 31 03 40 No later than: Date: 04/15/2020 Time: 09:00 GMT Supervision of

work of the PR-RNI Notice of Expression of Interest February 2020 Criteria Notes 1. Nature of the

candidate`s activities and relationship with the field of services 5 points 2. The number of years of

experience 10 points 10 years 10 points 3.
[Disclaimer: The above text is machine translated. For accurate information kindly refer the original document.]

Documents

Tender Notice
Login to view

Similar tenders

Burkina Faso Public Procurement Intelligence

Frequently asked questions

The bid deadline for Supervision and Control of (I) Construction Works the 90 Kv Loop was 15 Apr 2020. Bidding is closed.

This tender has been issued by SOCIETE NATIONALE D’ELECTRICITE DU BURKINA in Burkina Faso.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 71520000 - Construction supervision services.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 42088402. The purchaser document reference is 001/2020 / PR-RNI.

See the Similar Tenders section on this page or browse other tenders from Burkina Faso.

This tender falls under Construction and Real Estate in Burkina Faso. Suppliers in these sectors can track similar Burkina Faso tenders using CPV-based alerts.