Executive Summary
The THE KWAZULU-NATAL DEPARTMENT OF TRANSPORT has issued a Tender notice for the procurement of a Provision of a Service Provider to Provide the Contractor Development Programme (CDP) Management for Kwazulu-Natal- Department of Transport in the South Africa. This Tender notice was published on 22 Aug 2022 and is scheduled to close on 23 Sep 2022, with an estimated Tender value of Refer Document.
Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 70636830, while the tender notice number is ZNB01088/00000/00/HOD/GEN/21/T and Register on the platform.
Key facts
Summary
Provision of a Service Provider to Provide the Contractor Development Programme (CDP) Management for Kwazulu-Natal- Department of Transport
Tenders are invited for Provision of a Service Provider to Provide the Contractor Development Programme (Cdp) Management for Kwazulu-Natal- Department of Transport Work Stream One: Overall Programme Management Support
Item Unit QTY Rate Rands
2 Work Stream One (1): Overall Programme Management Support
which includes Social facilitation, Access of Plants, Finance,
Reports, and Recruitment of Contractors
2.1 Programme Inception Reports
One inception report for each year of programme implementation
(36nonths /12 months = 3).
This is to indicate how the programme manager is to deals with the
yearly intake, training and mentorship and other deliverable associate
to the yearly intake.
No 3
Recruitment of the Contractors
a. Advertising of the CDP Expression of Interest
b. Number of Contractors final recruited to the programme
c. Induction of the Contractors
No
No
No
3
264
3
2.2 Monthly Progress Reports not limited to the ff:
• CDP Programme Management Reports
• Social and Community Facilitation Reports
• Training and mentorship Monitoring Reports
• Status report on Upgrading, and graduation/contractor exit
• Construction Site visits and monitoring progress monitoring Reports month 36
2.3 Close Out Report
a. Yearly Programme Closeout Report
b. End of Programme closeout Report
No
No
3
1
2.4 Facilitate Access to finance from funding institutions for the CDP
contractors.
The programme manager will be paid to facilitate and ensure that
subcontractors get access to finance
(The programme manager will be paid on proof that a sub-contractor
has access to finance through an Authorised Financial Service Provider
or Government Institution of a minimum of R650 000, 00 with in the first
six months).
The lead contractor will not directly provide loans and stand as
guarantor to the sub-contractors.
Lump
Sum /
Finance
264 R3 000 R792 000
Signature: ___________ Date:____/_____/________
14
Supply Chain Management Quotation Pack
Invitation to Tender Standardized 13 June 2022
Description Price
Item Unit QTY Rate Rands
2.5 Facilitate Access to plants
The programme manager will be paid to facilitate and ensure that
subcontractors get access to plant.
(The programme manager will be paid on proof that a sub-contractor
has access to plant suppliers with in the first six months).
The programme manager will not directly provide access to plant and
stand as guarantor to the sub-contractors.
Lump
Sum /
Finance
264 R3 000 R792 000
Total
2.6 Social Facilitation: This involves the engagement and involvement of
community structures as outline in the Community Participation. This
item allows for:
a) Principal Facilitator (Programme Level),
Role: to design and oversee the process of community participation,
engages with Client, the community and 3rd parties to ensure approval
and endorsement of process and its ongoing and holistic incorporation
into all other aspects of the Programme.
(2 Hours x 21 days x36 Months )
b) Senior (District Level)
Role:
To facilitate the selection of learners.
To attend to community issues and attend PLC meeting to report on
progress and challenges.
(4 Hours x21 Days x 36 Months x12 Districts)
c) Junior. (Project Level)
Role:
To undertake and facilitate skills audits, household demographic and
income surveys.
To attend PLC meetings and provide ongoing oversight of the function
of the PLC and PLO.
To attend to grievances, disputes.
Hours
Hours
Months
1 512
33 264
36
Total
2.7 Programme manager (1)
Programme Manager shall be responsible for all required secretarial
services, administrative support, computer support and office
accommodation and shall not be entitled to claim any additional
amount from the Department for such services, support and office
2. Work Stream Two (2): On-site Mentorship and Business training
support to contractors
Item Unit QTY Rate Amount
3
3.1
3.3
3.4
Rates to include (, review training frames works, conduct
assessments, moderation and provide certification as per CETA
requirements, materials for training, facilitate graduation and
exiting of contractors, issuing of certification, legislative
compliance, business management and compliance and onsite
mentorship) Training MUST be compliant with CETA standards and
all unit standards must be accredited.
Skills Gap analysis.
Will be undertaken with contractors inside the programme,
before any training, project implementation and mentorship.
Per
Contractor
264
Training Plan
Based on the skills analysis individual and generic training plans will be
developed for contractors.
Individual kills gap analysis will be used to develop individual training
plans for contractors. This individual skills gap analysis will be used to
identify the generic areas for the development of generic areas training
and mentorship.
One training plan is required for each year of programme
implementation (36 months /12 months = 3).
This is to indicate how the programme manager is to deal with the
yearly intake, training and mentorship and other deliverable associate
to the yearly intake. Assessments will be undertaken at the completion of every second
project at each grade. These assessments will be conducted in line
with the skills gap analysis. A non-refundable tender deposit of R610.00 is payable in cash or bank card for collection Documents may be collected during working hours from 08H00 to 15H30 between Monday to Friday on the 22nd ofAugust
2022 till 06 September 2022. Alternatively, can be downloaded for free on www.kzntransport.gov.za or www.etenders.gov.za The closing time for receipt of Tenders is 11h00 on 23 September 2022 on KZN Department of Transport 172 Burger Street, Pietermaritzburg, 3201
The bid deadline for Provision of a Service Provider to Provide the Contractor Development Programme (CDP) Management for Kwazulu-Natal- Department of Transport was 23 Sep 2022. Bidding is closed.
This tender has been issued by THE KWAZULU-NATAL DEPARTMENT OF TRANSPORT in South Africa.
The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.
This tender is Self Financed
The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.
The TendersOnTime reference is 70636830. The purchaser document reference is ZNB01088/00000/00/HOD/GEN/21/T.