9/11/2026: Question - At the walk thru it was stated that we are replacing the shower stall same as existing. That is a shower base and fiberglass fabricated walls. Patch in tile around shower as required. The scope of work I interpret as installing new base pan and installing subway ceramic tile on the shower walls from floor to ceiling. Please clarify what is to be provided.
Answer: We want the entire shower replaced including pan and wall. We understand some of the tiles will need to be replaced, so we ask to either replace with direct copy of what is already there or recommend an accent border.
Question - So, the walls and base will be fiberglass to match existing and patch ceramic around the stall. The base and walls are a prefabricated unit that comes in 3 or 4 pieces as a kit. Is that correct? Answer - Yes
8/28/2026: Updates have been made to attachment documents for this solicitation to answer questions posed regarding bid bonds, evaluation criteria and other items. Please review ALL documents as the answers are incorporated into the SOW, Construction RFQ Clauses, and the SF-1442. Further questions should be posed via email to SKCS Sergio Cosby, the listed Contracting Officer's Representative.
The contractor shall provide all personnel, equipment, tools, transportation, supervision and
other items and services necessary to replace 15 showers in their entirety. All details are included in the SOW.
Contact InformationPrimary Point of ContactSERGIO COSBYEmail
[email protected] Phone Number2068152774Alternative Point of ContactRaymond CrowleyEmail
[email protected] Phone Number2157785808Contracting Office Address1 MUNRO AVENUE (No Street Address 2) CAPE MAY, NJ 08204 USA Attachments/LinksLinksNo links have been added to this opportunity.AttachmentsDocumentFile SizeAccessUpdated Date SF-1442_SDB_Shower Replacement.pdf 230.77 KB
Public Aug 28, 2026 SDB SOW Shower renovaton_revised.pdf 742.52 KB
Public Aug 28, 2026 Const...