REQUEST FOR QUOTATION (RFQ)
DATE: Janaury 29, 2016
R.I.S. #: 16-83-002
Gentlemen:
Please submit your lowest price quotation (including taxes and government discounts) on charged account basis, on the following supplies/
materials/equipment or labor for the account and official use of the Authority. This Request for Price Quotation or your Formal Bid Proposal maybe
submitted through Fax # 877-1756 / through E-mail at procmiaa/@gmail.com/
[email protected] or personally submitted to Ms. Leticia Felix/
John Patrick P. Lazaro at the Office of the Procurement Division on Feb. 11, 2016@2:00P.M.on which date shall be opened in your presence or your
duly authorized representative.
Thank you.
ELSIE P. NITOLLANO
Manager, Procurement Division
NOTE:
1.QUOTATION SHALL BE SUBMITTED TYPEWRITTEN.
2. ALTERNATIVE BIDS / A BID WITH OPTIONS SHALL BE REJECTED.
3. Request for Quotation shall be obtained from the office of Procurement Division on February 4 to 11, 2016
4.Warranty shall be for a period of one (1) year, which shall commence after the final acceptance of the end-user
5. Price validity shall be for a period of 120 calendar days.
6. The lowest bidder shall be advised to submit sample/s and brochure/s, if applicable, showing specifications of product being
offered and likewise shall State the Brand in the RFQ or bid proposal.
7. If awarded, the bidder shall submit a Sworn Affidavit of Compliance with the Disclosure Provision of No Relationship and required
registration documents
(FAILURE TO DO SO WILL MEAN DISQUALIFICATION OF YOUR PROPOSAL)
QTY. UNIT DESCRIPTION OF ARTICLES ABC UNIT PRICE TOTAL PRICE
Supply of labor and materials for the chemical treatment of MIAA 95, 000.00
Administration Building Air conditioning System and MIAA Power
Plant Cooling System
1 lot - 6 months Chemical Treatment of chilled water and cooling system
- Service report and water analysis
- Manpower and Labor
Scope of Work:
1. Supply of chemicals, labor and technical services for the treatment of
chilled water of air conditioning system MIAA Admin Bldg., and cooling
water of MIAA Power Plant.
2. Weekly analysis and checking of chilled water, make up and
re-circulating and should be submitted and discussed to end user.
3. Cooling tower should be operational when applying anti-scalant, anti-
algae and anti-corrosion for complete chemical mixing which must be
coordinated with the engineer-in-charge.
4. Cleaning of cooling tower upon request of the end user.
5. Shall submit free consultation of water treatment and related program
during the duration of the program.
6. Shall submit a monthly status report to up date the engineer in charge
about the progress in the water treatment . The report shall include the
result for the control parameters.
7. Submit treatment progress report through graphical presentation at the
end of the contract.
NOTE:
1. To be delivered the chemical/start of treatment within five (5) days
upon receipt of the approved Work Order.
2. Should submit the following during the bidding for technical evaluation:
Treatment schedule/program for six (6) months; quantity of chemicals
to be used; technical data and MSDS; and manpower list including contracts.
3. ALL additional materials/scope of work not included in the above list
but needed to complete the project should be for the account of the
contractor.
Basis of proposal:
1. MIAA Administration Building Air conditioning Chilled Water Circuit:
No. of chiller: Three (3) units air cooled liquid chiller
Tonnage rating : 180TR per unit
Re-circulating water rate: 432 gal/min per unit
Mode of operation: two (2) units operating simultaneously during office hours
2. Power plant cooling system
No. of cooling tower: Two (2) units bottle type
Mode of operation: Standby power source & test run of the unit once a week
Air flow rate: 2, 200 cu.m/sec
Nominal water flow rate: 3, 900 li/m
Treatment Objectives:
1. To ensure the quality of re-circulating water of the cooling system.
2. To maintain and prolong chiller, condenser and cooling tower life
and parts at the most economical means.
3. To strengthen the technical knowledge of chiller operators on cooling
water treatment program and related technology.
4. To achieve high cleanliness condition to promote equipment efficiency
and reliability while minimizing control level corrosion rate.
5. To achieve higher level of program success by proper monitoring
and highly responsive technical services.
Control Parameters
To obtain optimum result from the program and to economize chemical
and water usage, the following recommended control limits should be
maintained
Cooling Tower/Open Loop System
pH : 8.3 - 8.6
Total Alkalinity : 500 ppm max
Cycle of Concentration : 1.5 -2.0 cycles
Chemical Residual : 6.0 - 10.0 ppm
Silica : 150 ppm
LSI : 1.1 -2.2
Phosphonate 6 -10 ppm
pH : 9.0 -10.0
Nitrite Residual : 800 ppm minimum
Denitrifying Bacteria : No presence
Prepared & Canvassed By :
J. B. SULIT
Procurement Officer
Tel No. 877-1109 loc. 3605
Procurement Division
Sir:
In connection to the above request, we hereby submit our quotation as indicated above and that we agree to deliver the
items /complete the project as per specifications within ___________ calendar / working days upon receipt of corresponding
Purchase/Work Orders.
Authorized Representative (Printed Name/Signature)
Tel. No./Cell No.
Date