Expired Tender Lao PDR ICB TOT Ref. 44687857

Mine Closure Guidelines and Mine Waste Management Tender - 44687857

Tender notice from Lao PDR, published on 01 Aug 2020.

Executive Summary

The THE WORLD BANK GROUP has issued a Tender notice for the procurement of a Mine Closure Guidelines and Mine Waste Management Study in the Lao PDR. This Tender notice was published on 01 Aug 2020 and is scheduled to close on 06 Aug 2020, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 44687857, while the tender notice number is 1269841 and Register on the platform.

Key facts

Summary
Mine Closure Guidelines and Mine Waste Management Study
TOT Ref. No.
44687857
Document Ref. No.
1269841
Country
Lao PDR
Notice type
Tender
Competition
ICB
Publication date
01 Aug 2020
Bid deadline
06 Aug 2020
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
World Bank (WB)

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Expression of Interest are invited for Lao PDR Mine Closure Guidelines and Mine Waste Management Study.
REQUEST FOR EXPRESSION OF INTEREST FOR SELECTION # 1269841
This Request for Expression of Interest is for a Firm Selection. Please log in as a valid Firm User if you wish to express interest in this selection.
Selection Information
Assignment Title
Lao PDR Mine Closure Guidelines and Mine Waste Management Study
Publication Date
30-Jul-2020
Expression of Interest Deadline
06-Aug-2020 at 11:59:59 PM (Eastern Time - Washington D.C.)
Language of Notice
English
Selection Notice
Assignment Country
· LA - Lao People`s Democratic Republic
Funding Sources
The World Bank Group intends to finance the assignment/services under:
· BB - BANK BUDGET
· TF0B1375 - Lao Sustainable Energy & Extractives - Mining
Individual/Firm
The consultant will be a firm.
Assignment Description
The World Bank and BGR have supported the strengthening of inspection capacities of MEM, however capacity to detect problems associated with handling of various mine waste types is weak and an improved legislative framework and tools for inspections are needed. Several studies financed by the German BGR and World Bank projects (Tailing Storage Facilities Guidelines and Tin Mining Study) show that mine waste is a major problem and causes considerable environmental damage.
A study is therefore needed to categorize the most important mine waste issues in Lao PDR and to assess how far the existing planning, reporting and inspection system has been able to identify these issues. Based on this assessment, recommendations on how to further improve the planning, reporting and inspection system should be given and on further studies needed to shed more light on enforcement aspects.
Attachments
· Optional TOR File
Qualification Criteria
· 1. Provide information showing that they are qualified in the field of the assignment.
· 2. Provide information on the technical and managerial capabilities of the firm.
· 3. Provide information on their core business and years in business.
· 4. Provide information on the qualifications of key staff.
Mine Closure Guidelines and Mine Waste Management Study

Lao PDR

August, 2020
Contents

Background: 1

Deliverables 2

Output 1: Identify the main waste types and closure planning associated with mining in Laos 2

Output 2: Compare the Findings (Output 1) with available Inspection Reports 4

Output 3: Compare the Findings (Output 1) with available Reports by Mines 4

Output 4: Identify Strengths and Weaknesses of Inspection Tools 4

Output 5: Identify Strengths and Weaknesses on the Reporting System by Mining Companies 5

Output 6: Give recommendations for further activities to improve Inspections and Reporting 5

Output 7: Mine Closure Planning Template and Mine Closure Guidelines 5
Background:

In spite of the moratorium on granting new exploration licenses in place since 2012, Lao PDR has around 150 operating mines. Except for the 2 largest mines (Phou Bia and Sepon), which follow international standards, mine operations in Lao PDR present considerable risks of poor Mine Waste Management and inadequate measures for Mine Closure. Negative effects have been frequently reported to the National Assembly, People-s Provincial Assemblies and other Government of Laos authorities.
The revised Law on Minerals (2017) introduced new articles on Mine Closure and Mine Closure Security. In the previous law there had been a general obligation to close a mine at the end of operational life but limited indications of owner-s obligations and financial liabilities. This was strengthened in the 2017 law. In line with international practice, the revised law requires mines to produce mine closure plans at the time of feasibility study and revise the plan every third year. It also requires applications for new mining leases to submit an initial mine closure plan with their Feasibility Study. Mine closure obligation applies both to metallic mines licensed under Part VI and non-metallic extractive operations licensed under Part VII of the law.
As a follow-up to the Law, in May 2020 the Lao Government introduced the Prime Ministerial Decree on Mine Closure, the decree was designed to follow international closure practice. The Decree stipulates that all new mineral development agreements will be obliged to prepare and implement closure planning and procedures, it also implies that compliance is retrospective and provides that projects have one year for their closure planning to become effective. While in line with international practice, the Decree will require further guidelines and template documents to provide an adequate regulatory framework for operators, regulators and communities.
The World Bank and BGR have supported the strengthening of inspection capacities of MEM, however capacity to detect problems associated with handling of various mine waste types is weak and an improved legislative framework and tools for inspections are needed. Several studies financed by the German BGR and World Bank projects (Tailing Storage Facilities Guidelines and Tin Mining Study) show that mine waste is a major problem and causes considerable environmental damage.
A study is therefore needed to categorize the most important mine waste issues in Lao PDR and to assess how far the existing planning, reporting and inspection system has been able to identify these issues. Based on this assessment, recommendations on how to further improve the planning, reporting and inspection system should be given and on further studies needed to shed more light on enforcement aspects.
Deliverables
- Inception Report which further details the Outputs and Methodology for the study

- Guidelines for mine closure procedures, including template reporting documents (English)

- Waste Management Study Report (English)

- Lao language translation of Study Report, Guidelines and Template documents
Output 1: Identify the main waste types and closure planning associated with mining in Laos

Output 1.1 Based on the data available from recent studies and international mining practice, a full list of mine waste types found on mines in Laos and the internationally accepted methods used to manage and monitor different waste streams.

Output 1.2 Typology of the most common mine waste issues

Output 1.3 Typology of other issues pertaining to mine closure

Output 1.4 For small and undercapitalized mines in Laos what should be the minimum acceptable practice
The studies to be used as sample are:
- Assessment of Mines in the framework of drafting the Tailing Storage Facility guidelines for the World Bank HMTA project, including:

o 4 mine Sites (2 large mines, 2 medium-sized mines in Luang Pabang, Saysomboun and Khammouane
- ‘Tin Mining Study- for the BGR SDMS project:

o Small and Medium Sized Tin, Copper and Gold Mines in Nam Pathaeng/Khammouane
- Other relevant project assessments
By using this sampling through available studies small, medium-sized and large mines are covered as well as a total of 4 Provinces of Laos and a range of different Minerals.
Identified issues should be described in text form, but also by photographs as much as possible (and with photographs of good practice examples, as much as possible)
For a draft list of potential Mine Waste issues, see Annex 1.

 

Output 2: Compare the Findings (Output 1) with available Inspection Reports

Based on the list of mine closure and waste issues (Output 1.1) the consultant should assess how far the Inspection system by MEM-DMM/PDEMs was able to identify these issues and (if not) why not.
To do so, a list of mining Inspections for the relevant time-frames (12 months previous to the point of time of the above mentioned studies and 12 months after, has to be obtained from MEM, PDEMs and MoNRE) (Output 2.1).

The assessment of these Inspection Reports should respond to the following guide-questions:

- Have inspections been carried out in the mines in the sample in the 12 months previous and 12 months after the time of the studies? (Output 2.2) This can include both, regular and incident inspections.

- Which agency (e.g. MEM-DMM Inspection Department, PDEM, MoNRE) has carried out the Inspections? (Output 2.3)

- Which of the mine waste and mine closure issues identified through the studies (output 1.1) has been identified in the Inspection reports and which not, including a comparison of the qualitative description of the issue (Output 2.4)
Output 3: Compare the Findings (Output 1) with available Reports by Mines

The consultant should assess in as far the reports by the Mining Companies have included the relevant questions:
To do so, a list of reports by Mining Companies for the relevant time-frames (12 months previous to the point of time of the above mentioned studies and 12 months after, has to be obtained from MEM, PDEMs and MoNRE) (Output 3.1).

The assessment of these reports should respond to the following guide-questions:

- Which reports relevant to Mine Waste and Mine Closure planning have actually been submitted to the authorities (Output 3.2)

- Which agency (e.g. MEM Inspection Department, PDEM, MoNRE) have these reports been submitted to and what is the formal type of report? (Output 3.3)

- How far has reporting been complete and followed the relevant legislation? (Output 3.4)

- Which of the Mine Waste and Mine Closure issues identified through the studies (output 1.1) has been identified in the reports and which not, including a comparison of the qualitative description of the issue (Output 2.4)
Output 4: Identify Strengths and Weaknesses of Inspection Tools

Based on the findings of Output 1 and Output 2, the consultant shall give recommendations on how the Inspection System coul

Documents

Tender Notice
Login to view

Similar tenders

Tender Country TOT Ref. No. Bid deadline
Consulting, Land Registration (Land Management) Lao PDR 152710145 08 Jan 2027
Gender; Climate change impacts; Ethnic studies scorecard development and other studies Lao PDR 133353603 31 Dec 2026
Procurement Specialist Lao PDR 127622568 30 Sep 2029
International Procurement Specialist Lao PDR 127622563 30 Sep 2029
Rehabilitation of Samakkhyxay Intake and WTP Lao PDR 127621572 31 Dec 2026

Lao PDR Public Procurement Intelligence

Frequently asked questions

The bid deadline for Mine Closure Guidelines and Mine Waste Management Study was 06 Aug 2020. Bidding is closed.

This tender has been issued by THE WORLD BANK GROUP in Lao PDR.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is financed by World Bank (WB).

The tender is classified under the following CPV code(s): 90533000 - Waste-tip management services.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 44687857. The purchaser document reference is 1269841.

See the Similar Tenders section on this page or browse other tenders from Lao PDR.

This tender falls under Construction and Real Estate in Lao PDR. Suppliers in these sectors can track similar Lao PDR tenders using CPV-based alerts.