Object of the contractSite preparation and clearance work
Description: Contract notice: Site preparation and clearance work
Authority Type: Other
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union, with participation by GPA countries
Award criteria: The most economic tender
CPV code: 45111200, 45100000, 45231000, 45233000, 45233220, 45233221, 45233290, 45233292, 45233222, 77211600, 71326000, 45221119, 45221111, 45111300, 45233121, 45111200, 45232150, 45231221, 45233130, 45232400, 45231400, 45232300, 45111200, 45100000, 45231000, 45233000, 45233220, 45233221, 45233290, 45233292, 45233222, 77211600, 71326000, 45221119, 45221111, 45111300, 45233121, 45232150, 45231221, 45233130, 45232400, 45231400, 45232300
CPV Description: Site preparation and clearance work.
Site preparation work.
Construction work for pipelines, communication and power lines.
Construction, foundation and surface works for highways, roads.
Surface work for roads.
Road-surface painting work.
Installation of road signs.
Installation of safety equipment.
Paving and asphalting works.
Tree seeding.
Ancillary building services.
Bridge renewal construction work.
Road bridge construction work.
Dismantling works.
Main road construction works.
Works related to water-distribution pipelines.
Gas supply mains construction work.
Construction work for highways.
Sewer construction work.
Construction work for electricity power lines.
Construction and ancillary works for telephone and communication lines.
Rozbudowa drogi wojewodzkiej Nr 835 Lublin - Wysokie- Biłgoraj - Sieniawa - Przeworsk - Kańczuga - Dynow - Strabska Grabownica from km 90 490 to km 115 875 on the section Biłgoraj - Gr. voivodship
Reference Number: DZU.371.141.2019.dk
The subject of the investment is a section of voivodship road No. 835 subject to expansion, located in the Lublin voivodship, in the Biłgoraj poviat, in the commune of the city of Biłgoraj and the communes: Biłgoraj, Księżpol and Tarnogrod. The beginning of the section is located at km 90, 490.00 in the city of Biłgoraj, the end at km 115, 855.00 - at the border of the Lublin and Podkarpackie voivodships. The road was designed on the parameters of a G-class road, along with the construction and extension of engineering structures as well as the protection or extension of foreign devices colliding with the developed road and engineering structures.
Main Site: Road wojewodzka No. 835 Lublin - Wysokie - Biłgoraj - Sieniawa - Przeworsk - Kańczuga - Dynow - Grabownica Starzeniaska from km 90 490 to km 115 875 on the section Biłgoraj - Gr.
And the province. 1. The awarding entity envisages the award of an order pursuant to art. 67 section 1 item 6 of the Public Procurement Law for an amount not exceeding PLN 50, 000, 000 net. The contract will be able to be awarded on the road covered bybasic order essay. The scope of the contract includes: supervision of a specialist ornithologist, entomologist, herpetologist, temporary bridges, access to temporary bridges, reference points, measuring works, elevation and stabilization of PD border points, removal of shrubs and bushes, removal of the layer of humus, dismantling of cubature objects, dismantling of elements (road, fences and culverts), execution ofmounds and embankments, soil replacement, reinforcement of the embankment base, execution of French drains, removal of the fertile soil layer, execution of the trough together with profiling, cleaning and sprinkling of structural layers, performance of an improved foundation, implementation of foundations, implementation of frost-resistant and cut-off layers, execution of binding layers, execution leveling layers, making the navelandings (roadways, roadside exits, parking yards, bays), execution of pavement surfaces and bicycle paths, construction of exits, construction of street elements, strengthening of slopes, ditches and watercourses, surface milling, execution of roadsides, liquidation of bituminous pavement cracks, arrangement of geocomposites, arrangement of sewage, laying culverts under the exits, strengthening inlets and outlets, makinghorizontal and vertical marking and BRD devices, setting curbs and edges, setting concrete palisades, securing trees, constructing retaining walls, moving construction works, works related to reconstruction and protection of the gas network, works related to reconstruction and protection of water and sewage networks, related works with the implementation of storm water drainage, work connectedrelated to lighting, works related to reconstruction and protection of power equipment, works related to reconstruction and protection of teletechnical devices, dismantling and construction of culverts, dismantling and construction of bridges.
2) Conditions on which they will be granted:
a) Negotiations will be conducted, on which the parties will determine the detailed scope of the contract, the date of implementation fromorders and the amount of remuneration,
b) The contractor for the basic contract will perform them in the same standard as for the basic contract.
II. According to art. 30 paragraph 4 of the Public Procurement Law, the Awarding Entity allows for equivalent solutions to those described. The Contractor who refers to the equivalent solutions described by the Employer is obliged to demonstrate that the offered construction worksthey meet the requirements specified by the Employer (Article 30, paragraph 5 of the Public Procurement Law).
III. According to art. 93 item 1a. of the Public Procurement Law, the Awarding Entity may cancel the procurement procedure if the funds which the Awarding Entity intended to spend on financing all or part of the award have not been granted.
IV The Contractor is obliged to promote the Project.
V. Behindit is recommended that the Contractors make a site visit.
VI. Employer pursuant to art. 29 paragraph 3a of the Public Procurement Law, requires employment by a contractor or subcontractor on the basis of an employment contract of persons performing activities within the scope of the contract in accordance with doc. orders.
VII. According to art. 13 section 1 and 2 of Regulation (EU) 2016/679 of the European Parliament and of the Council of 27 April 2016 onknows the protection of natural persons in connection with the processing of personal data and the free movement of such data, and repeals Directive 95/46 / EC (general regulation on data protection) (Official Journal EU L 119 of 04.05.2016, p. 1), hereinafter " GDPR ", I would like to inform you that:
- the administrator of your personal data is the Director of the ZDW in Lublin, 7A Turystyczna St., 20-207Lublin,
- with the personal data inspectorThe Voivodship Road Administration in Lublin can be contacted by e-mail:
[email protected]. Detailed information on RODO can be found in doc.
And orders. 1. Contractors who meet the conditions regarding:
1) Technical or professional capacity;
2 may participate in the tender. Minimum conditions concerning:
1) Expert's experience: Implementation within the last 5 years before the expiry ofthe submission deadline, and if the period of business activity is shorter during this period, at least one construction work covering its scope of construction or reconstruction (within the meaning of the Act of 7 July 1994 "Construction Law", Journal of Laws of 2019, item 186 ) a public road worth at least PLN 65, 000, 000.00. (net) and documenting that the work has been carried out properlyy and in accordance with the principles of the art of construction and properly completed.
2) Professional qualifications of persons referred by the contractor to carry out the contract:
a) Construction manager: This person must have building qualifications in the road specialty, authorizing the construction of the road covered by the contract, whose parameters specified in the project documentation.
b) road works robot manager: Person te must have construction qualifications in the road specialty, authorizing to manage the construction of the road covered by the contract, whose parameters are specified in the design documentation,
c) head of the bridge industry works: This person must have construction qualifications in the bridge engineering specialty, authorizing the construction of bridge structures covered by the contract whose parameters are specified in the documentdesign tation,
d) head of the sanitary industry works: This person must have building qualifications to manage the construction works covered by the contract, whose parameters are specified in the design documentation in the installation specialty in the field of gas, water and sewage networks, installations and equipment,
e) work manager power industry: This person must be authorizedand construction works to manage construction works in the installation specialty in the field of networks, installations and electrical and power equipment covered by the contract, the parameters of which are specified in the design documentation,
f) telecommunications industry works manager: This person must have building qualifications to manage construction works in the telecommunications specialty Ordersaying whose parameters are specified in the project documentation,
g) nature protection specialist - ornithologist,
h) nature protection specialist - entomologist,
i) nature protection specialist - herpetologist,
it is forbidden to combine specific functions in point 2) lit. a) -f)
Under the concept of roads, the Employer understands public roads specified in the Act of March 21, 1985r. public roads (Journal of Laws 2018 item 2068 from later changes) or equivalent roads in the European Union countries, countries that are parties to the World Trade Organization Agreement on government procurement and countries that are parties to international agreements to which the European Union is a party.
II.1. The Awarding Entity will exclude the contractor mentioned above from the contract award procedurereferred to in art. 24 paragraph 1 point 12) -23) of the Public Procurement Law and the contractor in relation to which at least one of the following conditions apply:
1) in relation to which liquidation has been opened, in the arrangement approved by the court in the restructuring proceedings there is provision for satisfaction of creditors by the liquidation of its assets or the court ordered liquidation of his assets pursuant to art. 332 paragraph 1 of the Act ofand May 15, 2015 - Restructuring Law (Journal of Laws of 2017, item 1508 and of 2018, item 149, 398, 1544 and 1629) or whose bankruptcy was announced, except for the contractor who entered into an arrangement after the declaration of bankruptcy approved by a final court decision, if the arrangement does not provide for satisfaction of creditors by the liquidation of the assets of the bankrupt, unless the court ordered the liquidation of its assets in a courte art. 366 section 1 of the Act of February 28, 2003 - Bankruptcy Law (Journal of Laws of 2017, item 2344 and 2491, and of 2018, items 398, 685, 1544 and 1629);
2) which has been seriously violated professional duties, which undermines his integrity, in particular when the contractor as a result of the intended action or gross negligence failed to perform or improperly performed the contract, which the contracting authority is inable to demonstrate by appropriate means of evidence;
3) which, for reasons attributable to it, failed to perform or improperly performed significantly the previous public procurement contract or concession contract concluded with the awarding entity referred to in Art. 3 clause 1 point 1-4 of the Public Procurement Law, which led to the termination of the contract or the award of damages;
2.ę the technical or professional abilities of other entities are required to demonstrate the lack of grounds for exclusion due to the non-compliance by these entities of the conditions referred to in art. 24 paragraph 1 items 13-22 of the Public Procurement Law and the reasons indicated and reasons indicated in points II1.1) -3) of this section.
III. List of statements or documents confirming compliance with the conditions for participation in the procedure and bgrounds for exclusion.
1. The contractor will attach to the offer a current statement as at the date of submitting the offers in the form of a Single European Procurement Document, hereinafter EAT, to the extent indicated by the Employer. The information contained in the statement constitutes preliminary confirmation that the contractor: is not subject to exclusion and meets the conditions for participation in the proceedings.
Note!
The contractor in Part IV EAT "Krqualification criteria 'may be limited to completing section α only, the contracting authority does not require completing any of the other sections of section IV. the extent to which their resources are referred to, the conditions for participation in the proceedings are also submitted by a uniform documentyou (EAT) about these entities
3. In the event of joint application by the contractors, JEDZ shall be submitted by each of the contractors jointly applying for the contract. These documents confirm compliance with the conditions for participation in the conditions for participation in the procedure and the absence of grounds for exclusion.
4. In addition, in addition to the Single European Procurement Document, the Contractor must attach tooffers:
a) proof of payment of the bid security.
b) tender (with net price and VAT).
c) commitment or other documents of entities to provide the contractor with the necessary resources at the disposal of the contract - if the Contractor relies on the abilities of other entities. The undertaking must be submitted in the original in the form of an electronic document (document in electronic form)signed with a qualified electronic signature).
I. A condition of participation in the tender is a bid bond of PLN 1, 500, 000.00; in words: one million five hundred thousand 00 / 100.
II. From the Contractor who will be awarded the contract, the Employer will demand the submission of a security on due performance of the contract in the amount of 10% of the gross offer price.
III. Bid evaluation criteria:
1. Price, 60% criterion;
The offer with the lowest price will be awarded to PC = 10 points
The remaining offers will receive a number of points calculated according to the following formula:
PC = (Price of the cheapest offer / price of the evaluated offer) x10
2. Warranty period - 10% criterion;
Offers with a warranty period of 5 years will receive the number of PR points = 0 points
Offers with a warranty period of 6 years will receive the number of pPR points = 5 points
Offers with a warranty period of 7 years and more will receive the number of PR points = 10 points
3. Experience of the construction manager - significance of the 10% criterion
The experience of the construction manager in performing the function of construction manager or road works robot manager on a road investment consisting in construction or reconstruction (within the meaning of the Act of July 7, 1994, "Lawconstruction "Journal of Laws of 2019, item 1186) of a public road and the value of the works at least PLN 65, 000, 000.00 (net), where the investment should be finally collected by its contracting authority.
Offers with the experience of the construction manager:
- during the execution of one construction work or without indicating the experience specified above, they will receive the number of PD points = 0
- during the implementation of two construction worksthey will receive PD = 4
points - during the implementation of 3 construction works they will receive PD points = 6
- during the implementation of 4 or more construction works they will receive PD = 10
points with FIDIC conditions) or signing the final acceptance report (in case of taskson which the Takeover Certificate is not issued.)
Under the concept of roads, the Employer understands public roads specified in the Act of 21 March 1985 on public roads (Journal of Laws of 2018, item 2068, as amended). ) or equivalent roads in the European Union, countries party to the World Trade Organization Agreement on government procurement and countries that areparties to international agreements to which the European Union is a party.
4. The Contractor's independent performance of the (key) parts of the contract relevant to their correct implementation - the significance of the 20% criterion
4.1. Offers without an indication of the contractor's independent performance of the (key) parts of the contract from the road industry that are relevant to their proper implementationher 0 points (PW = 0).
4.2. Tenders with independent performance by the contractor of important (key) parts of the contract from the road industry will receive 10 points (PW = 10).
The following works in the road industry are key to obtaining the expected road parameters: bituminous layers:
- foundation from asphalt concrete AC22P item cost 154, 155, SST D-04.07.01a,
- AC11W asphalt binder course, cost items 167.
SST D-05.03.05b.
- binding / leveling layer of asphalt concrete AC16W items cost 168, 169, 170, 171 SST D-05.03.05b,
- wearing course with AC5S item cost. 164, SST D-05.03.05a
wearing course with AC11S item cost. 165, 166 SST. D-05.03.05a
- wearing course with SMA11 item cost. 177, SST. D-05.03.13a.
5. For the bestthe most successful will be the offer that obtains the highest total number of points calculated according to the formula:
P = PCx60% PRx10% PDx10% PWx20%
Internet address (URL): www.zdw.bip.lubelskie.pl