Executive Summary

The MIEJSKI ZAKŁAD WODOCIĄGÓW I KANALIZACJI SP. Z O.O. has issued a Tender notice for the procurement of a Contract notice: Sewage-treatment plant construction work in the Poland. This Tender notice was published on 10 Apr 2020 and is scheduled to close on 20 May 2020, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 42163418, while the tender notice number is 170217-2020 and Register on the platform.

Key facts

Summary
Contract notice: Sewage-treatment plant construction work
TOT Ref. No.
42163418
Document Ref. No.
170217-2020
Country
Poland
Notice type
Tender
Competition
ICB
Publication date
10 Apr 2020
Bid deadline
20 May 2020
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Sewage-treatment plant construction work
Description: Contract notice: Sewage-treatment plant construction work
Authority Type: Other
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45252100, 71320000, 45110000, 45200000, 45252127, 45252200, 45232421, 45232422, 45252140, 45252130, 45231300, 45231500, 45233120, 45232451, 45252100, 71320000, 45110000, 45200000, 45252127, 45252200, 45232421, 45232422, 45252140, 45252130, 45231300, 45231500, 45233120, 45232451
CPV Description: Sewage-treatment plant construction work.
Engineering design services.
Building demolition and wrecking work and earthmoving work.
Works for complete or part construction and civil engineering work.
Wastewater treatment plant construction work.
Purification plant equipment.
Sewage treatment works.
Sludge-treatment works.
Sludge-dewatering plant construction work.
Sewage plant equipment.
Construction work for water and sewage pipelines.
Compressed-air pipeline work.
Road construction works.
Drainage and surface works.
Reconstruction and modernization of sewage treatment plant for the agglomeration of Koło
Reference Number: DZ3.3411-3 / 20
Subject of this contract is the execution of design works and then, on the basis of these works, construction works under the "design build" order covered by"Reconstruction and modernization of sewage treatment plant for the Koło agglomeration" dish according to the conditions described in the Functional Program, developed by Tomasz Miazga Consulting, Services, Construction Supervision, Puławska St. 228, street 67, 02-670 Warsaw, February 2020, and specific conditions in volume III of this ToR. Contract carried out in connection with the performance by the Employer of the contract with Nationalitieswith the Fund for Environmental Protection and Water Management in Warsaw, No. POIS.02.03.00-00-0189 / 16-00, under measure 2.3 water and wastewater management in agglomerations, the Operational Program Infrastructure and Environment 2014 2020.
Main Site: Koło
The scope of this contract provides for the modernization and reconstruction of an active sewage treatment plant for the Koło agglomeration, and based on the power of attorneygranted by the Employer obtaining a permit for use and handing over to the Employer for operation of a modernized and rebuilt sewage treatment plant for the Agglomeration Koło in Koło at ul. Energetyczna 11, together with the necessary accompanying works.
Detailed description of the new, two-draft, set up of new biological reactors, secondary settling tanks and conauxiliary tanks (primary sludge thickener and excessive sludge storage tank), together with a drainage and chemical stabilization station; can be found in point 5.1 of the functional and utility program. All technological and servicing equipment should be located in facilities or buildings adapted for this purpose. Due to the need to changeanalyzing the impact of the sewage treatment plant on the environment, including adverse climate changes, it is envisaged to cover and insulate the primary sludge thickener and the excess sludge storage tank, and ultimately to utilize the resulting sewage sludge to form a product. The sewage treatment plant should be adapted to current operational requirements. Target designed bandwidth of the eyessewage treatment plant will be:
Qdśr design = 9, 300 m / d. and RLM design = 80, 000 RLM.
A detailed description of the subject of the contract is presented in volume III of this ToR. The contractor is obliged to carry out the contract under the terms and conditions described in the contract template constituting the Annex to the ToR (volume II).
The contracting authority in accordance with art. 30 paragraph 4 PPA allows for indicated solutionsby the authors of the Functional Program described by means of standards, approvals, technical assessments, technical specifications and reference systems, the use of equivalent solutions described. equipment or materials) will bethey had all parameters not worse than those specified in the Functional Program and in Volume III of this ToR. The Contractor, who refers to the equivalent solutions described by the Employer, is obliged to demonstrate that the design solutions or construction works offered by him meet the requirements specified by the Employer. Possible equivalence verificationThe proposed solutions will be carried out by the authors of the Functional and Utility Program.
Note: due to technical limitationscited announcement form the content of the conditions for participation in the proceedings is incomplete. The full content of the condition is available at: https://mzwik-kolo.pl/strony, 28, przetargi
Exclusion of the Contractor
1. Contractors who are not subject to exclusion from participation in the procedure may apply for the order.
2. The Awarding Entity will exclude Contractors from the public procurement procedurefrequencies referred to in art. 24 paragraph 1 point 12 23 of the Public Procurement Law (except for the case referred to in Article 24 paragraph 1 point 13 letter d, of the Public Procurement Law and in the case referred to in Article 24 paragraph 1 point 14 of the Public Procurement Law, if the person referred to in this provision has been convicted of an offense listed in Article 24 (1) (13) (d) of the Public Procurement Law) and Article 24 paragraph 5 of the Public Procurement Law, i.e.
1) a Contractor who has not demonstrated compliance with the conditionsow to participate in the proceedings or have not demonstrated the absence of grounds for exclusion;
2) the Contractor being a natural person who has been validly convicted of an offense:
a) referred to in art. 165a, art. 181 188, art. 189a, art. 218 221, art. 228 230a, art. 250a, art. 258 or art. 270 309 of the Act of June 6, 1997, the Penal Code (Journal of Laws of 2018, item 1600, as amended)) or Art. 46 or art. 48 of the Act of 25June 2010 on sport (Journal of Laws of 2019, item 1486);
b) of a terrorist nature referred to in art. 115 - 20 of the Act of June 6, 1997, the Criminal Code;
c) tax;
3) the Contractor for whom a final court judgment or final administrative decision on late payment of taxes, fees or social or health insurance contributions was issued, unless that the Contractor has madethe ease of taxes, fees or social security or health insurance contributions due, together with interest or fines, or has entered into a binding agreement on the repayment of such receivables;
4) a Contractor who, as a result of intentional act or gross negligence, misled the Employer when providing information that he did not is subject to exclusion, meets the conditions for participation in the proceedings or obieffective and non-discriminatory criteria, hereinafter referred to as "selection criteria", or who has hidden this information or is unable to provide the required documents;
5) a Contractor who, as a result of recklessness or negligence, provided information which mislead the Employer, which may have a significant impact on decisions undertaken by the Employer in the procurement procedure;
6) Performingwho unlawfully influenced or attempted to influence the Employer`s activities or obtain confidential information that could give him an advantage in the contract award procedure;
7) the Contractor who participated in the preparation of the contract award procedure or whose employee as well as the person performing the work based on a mandate contract, work contract, agency contract or other service contract, Brparticipation in the preparation of such proceedings, unless the distortion of competition caused by this can be eliminated in a different way than by excluding the Contractor from participation in the proceedings;
8) the Contractor who has entered into an agreement with other Contractors to distort competition between the Contractors in the award procedure orders, which the Employer is able to demonstrate using a stackmeans of evidence;
9) a Contractor who is a collective entity, against whom the court has ruled out a prohibition to apply for public procurement on the basis of the Act of 28 October 2002 on the liability of collective entities for offenses under penalty of punishment (Journal of Laws of 2019 item 628 and 1214);
10) the Contractor who was ordered to take the contract by way of preventive measurepublic contracts;
11) Contractors who, belonging to the same capital group, within the meaning of the Act of 16 February 2007 on competition and consumer protection (Journal of Laws of 2019 item 3691571, 1667), have submitted separate bids, partial bids or requests to participate, unless they show that existing ...
Internet address (URL): http://www.mzwik-kolo.pl

Documents

Tender Notice
Login to view

Similar tenders

Poland Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Sewage-treatment plant construction work was 20 May 2020. Bidding is closed.

This tender has been issued by MIEJSKI ZAKŁAD WODOCIĄGÓW I KANALIZACJI SP. Z O.O. in Poland.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 45252100 - Sewage-treatment plant construction work, 71320000 - Engineering design services, 45110000 - Building demolition and wrecking work and earthmoving work, 45200000 - Works for complete or part construction and civil engineering work, 45252127 - Wastewater treatment plant construction work, 45252200 - Purification plant equipment, 45232421 - Sewage treatment works, 45232422 - Sludge-treatment works, 45252140 - Sludge-dewatering plant construction work, 45252130 - Sewage plant equipment, 45231300 - Construction work for water and sewage pipelines, 45231500 - Compressed-air pipeline work, 45233120 - Road construction works, 45232451 - Drainage and surface works.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 42163418. The purchaser document reference is 170217-2020.

See the Similar Tenders section on this page or browse other tenders from Poland.

This tender falls under Construction and Real Estate in Poland. Suppliers in these sectors can track similar Poland tenders using CPV-based alerts.