Object of the contractLow-pressure pipeline
Description: Contract notice: Low-pressure pipeline
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: GPA
Award criteria: The most economic tender
CPV code: 44161600, 44161600
CPV Description: Low-pressure pipeline.
KW Schaechen: Lot 2.1 - pressure line (section - GFK)
The new KW Schaechen, is a single-stage run-of-river power plant. The water collection site is located at about 536.80 m above sea level at the underwater canal of the KW Buerglen. From the water intake, the water flows in a pressure line (2 500 m length) to the KW headquarters, which is south of the Sch-chens to about 456 m ue M. M. Main Site: Canton: Uri.
The new CH Schaechen is a single-stage run-of-river power plant. The water collection site is located at about 536.80 m above sea level at the underwater canal of the KW Buerglen. From the water intake, the water flows in a pressure line (2 500 m length) to the KW center, which is south of the Sch-chens to about 456 m ue M. The following main components include the pressure line delivery:
-Pressure pipes DN 1'600 with PN 16, PN 10 and PN 6: 2'500 m,
- inlet pipes DN 2'200 and cone DN 2'200-1'600 PN 6: 4 m,
- sheets up to 30 approx. 10 pcs,
- Boards up to 60 appr. 10 pcs,
- Manholes 4 pcs,
- Trouser pipes and distribution pipes PN 16 in front of central DN 1600/900/800,
- Ultrasonic flow measurements integrated in GFK DN 1'600: 2 pcs.
The offer documents are completely executed by the offerers
All documents requested are to be enclosed with the offer.
Partial offers are not permitted.
Business conditions: According to the tender documents.
Negotiations: No negotiations are held. See tender documents.
Principles of procedure: The award procedure is based on the submission of the Uri canton of 15.-February 2006 (SubV). For the rest, Swiss law is applicable both to the procedure and to the contract to be concluded; Jurisdiction is Altdorf, Uri.
Other information: The compulsory inspection will take place on 5.4.2018 at 09.00 clock. Meeting point: car park KW Buerglen, Klausenstrasse 123, CH-6463 Buerglen Participation of an expert representative on the ascent-The construction site is a prerequisite for the submission of an offer.
Remedies: Within 10 days of publication at the Paritaetic Commission in Public Procurement, c / o Mario Bachmann, President, Rathausplatz 7, 6460 Altdorf, an application for initiation of a
Final date / comments: The UnContractor must submit a tender that fully complies with the specifications and the legal / commercial conditions of this tender. The offer, with all required documents, must be submitted in German, 1x in writing, 1x digitally (eg on CD) in the closed envelope with the inscription KW Schaechen, lot 2.1 - pressure pipe (section - GFK) "Nicht Oeffnen".Address for personal delivery at the reception EWA or at a Swiss post office see pos. 1.2. The risk that the offer will arrive on time lies with the entrepreneur. The date of the postmark is not decisive. Offers submitted or received late are excluded from the procedure and returned to the provider unopenedask questions)
Questions concerning the call for tenders should be sent by e-mail to the following person, stating the chapter concerning the question.
[email protected] Answers to essential questions will be answered in writing to all bidders who requested the tender documents by 13 April 2018.
National Reference Publication: Simap dated 16.3.2018, doc. 1009889
Date requestedfor written questions until: 5.4.2018
Tender documents are available from 19.3.2018 to 27.3.2018
Conditions for obtaining the tender documents: The tender documents can be obtained on CD.
Internet address (URL): https://www.simap.ch
Directive: Classical Directive (2014/25/EU)