Object of the contractHostel construction work
Description: Contract notice: Hostel construction work
Authority Type: Body governed by public law
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union, with participation by GPA countries
Award criteria: Lowest price
CPV code: 45212412, 45300000, 45261410, 45331100, 45330000, 45400000, 45110000, 45212412, 45300000, 45261410, 45331100, 45330000, 45400000, 45110000
CPV Description: Hostel construction work.
Building installation work.
Roof insulation work.
Central-heating installation work.
Plumbing and sanitary works.
Building completion work.
Building demolition and wrecking work and earthmoving work.
„Modernizacia Študentskeho domova UKF Brezovy haj 1. etapa"
Reference Number : NZ 1/2018
Predmetom zakazky je realizacia stavebnych prac v rozsahu podľa projektovej dokumenof the respective proportions, which form Annex no. 1 and 2 of the tender documents for this request.
Main Site: The object of the existing Brezova Haj Student House building, Mlad- Boleslav 1, Nitra v k. u. Chrenova, district Nitra, - Superse 1565.
The subject of the contract is determined by the project documentation, the report as well as other documents, which are part of the tender documents for this ordere. In the modernization of the control and regulation system of the existing boiler technology, the existing boiler is removed and replaced by a new condensing boiler. The boiler assembly is completed with a new distributor (flood dismounting) and new measurement and regulation. The floods of TUV trains are being demolished and 7 new hot water traps are installed. An explosive wall of the boiler room will be installed. English courtyard, which is provided by pristup to the boiler from the outside, the situation is removed for the bad and the new one is being implemented. The movement of the inlet / outlet to / from the existing heat channel is realized. I'll excavate the floor and plaster of the walls and the ceiling. Building new floor, wall and ceiling designs. The sewerage system is abolished and the new one is implemented. The subject of the work in the 1st phase of the modernization of ŠD UKF Brezovy haj in the economicof the block (A), - dismantling the roof roof, - thermal insulation of the roof and realization of the new roof waterproofing, - dismantling of the thermal channel, dismantling the floods, laying of the UK, SV and PV distribution systems, covering of the thermal channel,
- assembly of UK distribution and heating facilities,
- gas pipeline translating for secondary school in Nitra,
of the neck between the farmhouse and the accommodation pavilion and 2 garages.
The subject of the work in the 1st stage of the modernization of ŠD UKF Brezovy haj in accommodation block (B) su:
- Excavation of the heat plaza, dismantle of flood divorces, deposition of lay-ups UK, SV, CV and sewerage, thermal cover of the heating channel, - installation of UK pipelines and heating bodies, - flooring and static construction work- In the courtyard between blocks A and B, the following are dismantled and dismantled: there is an existing sewerage system, including guides and shafts, - a new row of ducts and shafts is installed, - it will be covered with no application flooded surface treatment. The Applicant must comply with the conditions of participation in accordance with - 32 par. 1 ca. no. 343/2015 Coll. in later versions(hereinafter referred to as the "Public Procurement Act"). This fact is evidenced by the Act on Public Procurement.
The applicant entered in the list of economic entities, which is kept by the Public Procurement Office, does not submit any documents proving the fulfillment of the conditions under Article 32 par. 1 of the Act on Public Procurement.
If the applicant group is awarded a public contractrequires the proving of compliance with the terms and conditions for the personal status of each member of the group separately. The fulfillment of the condition of part-time according to - 32 par. 1 letter. e) the public procurement law is proved by the member of the group of suppliers only in relation to the part of the object of the procurement which is to be ensured. According to - 39 of the Public Procurement Act, the entity may provisionally replace- documents proving the fulfillment of the terms and conditions specified by the Contracting Authority by the Single European Document. Documents proving the fulfillment of the conditions of the partially replaced by the Single European Document shall be submitted to the contracting authority by the applicant pursuant to - 39 par. 6 of the Act on Public Procurement in Time and on behalf of the Public Procurer. The contracting authority requires that the European Union be uniteda document signed by a person entitled to act on behalf of a business entity or a duly authorized person.
Deduction of the use of the terms and conditions:
The conditions for participation in the applicant's personal status derive from a public procurement law. the procurement will be publicly advertised in the profileto the procurer: http://www.uvo.gov.sk/profily/-/profil/pdetail/269, to which the contracting authority will allow unrestricted access to the subcontracts. From this proof it is not necessary to send a request to the public procurer for the supporting documents. The public contracting authority recommends to the interested parties the explanation of the tender documents and the conditions in this notice of the award of public procurement to be sent in(2). In case of need to clarify the information given in this notice or in the tender documents, any interested party may ask for an explanation in writing for any interested person. The Public Procurer recommends an explanation sufficiently in advance, not later than 12.6.2018. In case of personal delivery, nothis explanation can only be delivered during the working hours from 8.30 am. until 15.00. at UKF in Nitra Department of Procurement, Trieda Andreja Hlinku 1, 949 74 Nitra directly at the contact person Ing. Zita Tomanova, 421 37 6408 060,
[email protected].
3.) The contracting authority will provide an explanation of the details by publishing this explanation on its profile within the scope of this procurement: http: //www.uvo.gov.sk/profily/-/profil/pdetail/269.
4.) In assessing the fulfillment of the terms and conditions, the contracting authority will apply - 40 par. 6, letter. (5) In the event that the value of the lowest total VAT value will be the same in many offers, the Commission will determine from these tenders the successful bidder who will lower the price in the statement for the part of the Heating ModernizationAddition and regulatory system of boiler technology ŠD Brezovy haj
6.) For the preparation of the tender, the public contracting authority can publish on its web page (https://www.ukf.sk/uradnatabula/Public_bestavanie) Attachment no.2 Reports in Excel format and Appendices 4 and 5 in Word format at the latest 3 working days after the date of publication of this notice in the Official Journal of the EU.
7.) The contracting authority shallthe evaluation of the fulfillment of the conditions of part-time procedure pursuant to Section 66, par. 7 and the offers will be submitted in single-item mode according to - 49 par. 6 sheets. a) the public procurement law.8) In order to ensure the proper conduct of the public procurement in question, the contracting authority considers that the tenderer, by submitting the tender, is in charge of processing the personal data of the physical persons listed in his tender and is responsible forensuring the summoning of all persons concerned with the processing of personal data in accordance with the Personal Data Protection Act in force at the time of submission of the tender.
9.) The public procurement is not green public procurement, it is not the provision of innovation, nor is the procurement focused on social aspects.
Internet address (URL): http://www.ukf.sk
Directive: Classical Directive (2014/24/EU)