Expired Tender Denmark ICB TOT Ref. 35918894

Contract notice: Heat pumps Tender in Denmark - 35918894

Tender notice from Denmark, published on 30 Aug 2019.

Executive Summary

The PLANENERGI has issued a Tender notice for the procurement of a Contract notice: Heat pumps in the Denmark. This Tender notice was published on 30 Aug 2019 and is scheduled to close on 25 Sep 2019, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 35918894, while the tender notice number is 409680-2019 and Register on the platform.

Key facts

Summary
Contract notice: Heat pumps
TOT Ref. No.
35918894
Document Ref. No.
409680-2019
Country
Denmark
Notice type
Tender
Competition
ICB
Publication date
30 Aug 2019
Bid deadline
25 Sep 2019
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Heat pumps
Description: Contract notice: Heat pumps
Authority Type: Utilities entity
Contact Nature: Supplies
Procedure: Negotiated procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 42511110, 42511110
CPV Description: Heat pumps.
Pre-qualification for supply of air heat pump for Dronninglund district heating
Dronninglund district heating wants to establish an electric heat pump. The planned heat pump system must primarily utilize outdoor air as a heat source, but could also cool down the steam heat storage when this is advantageous. The heat pump must be used as a heat production unit together with the other units of the plant at the current a
Main Site: North Jutland
The current facility in Lunderbjerg consists of 4 main elements:
Solar heating plant, with a total area of 37, 500 m2 and an annual heat production of 18, 000 MWh (10, 000 MWh in the summer period). of 60, 000 m3 and a heat supply of 7, 000 MWh in the winter half (including solar collectors)
A transmission line of 2.8 km to the city (boiler center at S0ndervahighway) with a maximum capacity of 160 m3 / h, corresponding to approx. 6 MW.
A mixer circuit which can supply water at any temperature between the temperature in respectively. "top" and "center" of the steam heat storage during the summer period, to limit the supply temperature in the transmission line to approx. 75 C.
The heat pump should in principle only be used in the winter months from October to May and be installed in a new buildingng in connection with the current engineering building at the steam heat storage facility. Dronninglund District Heating establishes the new engineering building. The cooling fan with air solder for the new heat pump is placed immediately north of the steam heat storage, approx. 10 m above building level. Condensation water is directed to the seepage pool west of the steam heat storage. All of this is located at Lunderbjerg 6A, 9330 Dronninglund.
The project uis offered as a function offering in the following contracts:
Heat pump contract, including associated machine installations, electricity and control - Total contract
- Construction work - Contractor delivery,
- Electricity supply and management contractor - Contractor supply,
- to coordinate with the developer throughout the heat pump contract.
Br0nderslev Municipality has decided that the project does not require an EIA permit. The complete heat pump installation must be designed for high quality, high efficiency, long service life, low noise levels and many hours of operation during the winter half. -- 135-136 pamt de evt. selected voluntary exclusion grounds in - 137.
Total turnover:
Turnover for the last 3 completed and audited financial statements must be disclosed. Companies that have not yet completed 3 financial statements must provide available information on annual turnover. Companies there thoughnow not
have completed 3 financial years must provide available information on annual turnover and key figures.
The following key figures must be disclosed:
- Income before tax,
- Equity,
- Equity ratio,
- Liquidity ratio.
Internet address (URL): https://permalink.mercell.com/112514837.aspx

Documents

Tender Notice
Login to view

Similar tenders

Denmark Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Heat pumps was 25 Sep 2019. Bidding is closed.

This tender has been issued by PLANENERGI in Denmark.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 42511110 - Heat pumps.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 35918894. The purchaser document reference is 409680-2019.