Expired Tender Estonia ICB TOT Ref. 17413743

Contract notice: Gas supply mains construction Tender - 17413743

Tender notice from Estonia, published on 17 Oct 2017.

Executive Summary

The ELERING AS has issued a Tender notice for the procurement of a Contract notice: Gas supply mains construction work in the Estonia. This Tender notice was published on 17 Oct 2017 and is scheduled to close on 20 Nov 2017, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 17413743, while the tender notice number is 410176-2017 and Register on the platform.

Key facts

Summary
Contract notice: Gas supply mains construction work
TOT Ref. No.
17413743
Document Ref. No.
410176-2017
Country
Estonia
Notice type
Tender
Competition
ICB
Publication date
17 Oct 2017
Bid deadline
20 Nov 2017
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Gas supply mains construction work
Description: Contract notice: Gas supply mains construction work
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Negotiated procedure
Document: Contract notice
Regulation: European Union, with participation by GPA countries
Award criteria: Lowest price
CPV code: 45231221, 45231221, 45231221
CPV Description:
Reference Number: 191431
The front line of the public procurement is to provide the "EPC engineering, procurement and construction" service for the design, construction and maintenance of the Balticconnector pipeline project for the mainland of Estonia. Approximately 55 km long DN700 MOP 54bar D-categoryThe gas pipeline from Kili liin rack dust to the Paldiski compressor station includes:
The front line of the public procurement is to provide the "EPC engineering, procurement and construction" service for the design, construction and deployment of the Balticconnector pipeline project for the mainland of Estonia. The DN700 MOP 54bar D-category natural gas pipeline Kiili lineFrom the core to the Paldiski compressor station, it contains:
a) Kili liin raisin dust (DN700 MOP 54bar).
b) Kili probe dust.
c) Kili gas gas regulator.
d) Keila linin beam with Keila town branch line connection.
e) Paldiski liinraanisolm with Paldiski town branch line connection
f) LNG terminal branch block dust in Paldiski
g) Paldiski probe dust (DN700 MOP 54 bar)
h) Kiil Katod Protection Station
i)Keila Cathodic Power Station
A more revealing description of the design and construction works will be provided to qualified service providers during the second stage of the procurement procedure.
Each applicant and subcontractor listed in the application must be registered in the Estonian Aerial Register or in the equivalent registry of their country of location. The applicant will provide a written confirmation of this in the procurement box and, if necessary, provide the contracting authority with information on
1) The net profit of the applicant for the previous three financial years (2014-2016) (which has expired and is reported in the annual accounts) must be at least EUR 24 000 000 for each financial year during the period.
If the applicant seeks to promote its compliance with the economic and financial position on the basis of other entrepreneur resources, the applicant and the other company must be held liableThe applicant must provide the requisite information to the contracting authority in the procurement package in order to promote compliance with the qualification requirements and, if necessary or appropriate, provide the relevant documentation at the request of the contracting authority (annual reports, bank statements or other relevant documents that will be compared to applyand the custody of the tenderer has the financial means necessary to ensure the completion of the procurement contract; confirmation of the person whose funds are invoked to be jointly and severally liable for the part of the procurement contract to which his resources are based).
The contracting authority verifies that the shareholders whose funds are invoiced do not have the bases for the redemption and fulfill the qualification requirementswhich is based on their resources.
2) Applicants are entitled to receive, on the basis of bank statements or other relevant documents, the funds necessary to secure the award of the contract in the amount of EUR 7 000 000.
If the applicant seeks to promote his compliance economic and financial situationThe claimant and the other company must be jointly and severally liable for the part of the procurement contract to which the other company's funds have been invoked.
The applicant must provide the contracting authority with the necessary information in the procurement package in order to promote compliance with the qualification requirements and, if necessary or appropriate, to submit, at the request of the contracting authority, relevant-documents (annual reports, bank statements or other relevant documents that duplicate that the applicant or tenderer has the funds necessary to ensure the performance of the procurement contract; a confirmation of the person whose funds are claimed to be jointly and severally liable for the part of the procurement contract to which his resources are based).
The vendor checks that for the companies whosethe resources are based, there are no grounds for recovery and they meet the qualification requirements insofar as they are based on their resources. Employers whose funds are relied upon must provide a procurement batch to the contracting entity.
Interested parties may submit to the contracting authority the bottlenecks in the Public Procurement Register in writing in accordance with the Public Procurement Act. Competitions can be submitted in English, with the contracting authorityAB in English.
At least 16 months after the signing of the contract, the Kiili-Paldiski pipeline has to be able to transport natural gas from Estonia to Finland, and vice versa (this means that the probe has been flooded, the Kiil gas pipeline regulator, the line shafts and other necessary equipment). A deadline for receipt of a decision is made no later than 18 months after the signing of the contract.
Contract-In order to be successful, the provider must ensure communication with the customer in Estonian or in English. If the service provider is not an Estonian or English language speaker, the provider must provide professional backing and bear all the costs involved.
Internet address (URL): http://www.elering.ee
Directive: Classical Directive (2014/25/EU)

Documents

Tender Notice
Login to view

Similar tenders

Estonia Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Gas supply mains construction work was 20 Nov 2017. Bidding is closed.

This tender has been issued by ELERING AS in Estonia.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 45231221 - Gas supply mains construction work.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 17413743. The purchaser document reference is 410176-2017.

See the Similar Tenders section on this page or browse other tenders from Estonia.

This tender falls under Construction and Real Estate in Estonia. Suppliers in these sectors can track similar Estonia tenders using CPV-based alerts.