Expired Tender Poland ICB TOT Ref. 14918611

Contract notice: Construction works for power Tender - 14918611

Tender notice from Poland, published on 17 Jul 2017.

Executive Summary

The GMINA DASZYNA has issued a Tender notice for the procurement of a Contract notice: Construction works for power plants and heating plants in the Poland. This Tender notice was published on 17 Jul 2017 and is scheduled to close on 22 Aug 2017, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 14918611, while the tender notice number is 275241-2017 and Register on the platform.

Key facts

Summary
Contract notice: Construction works for power plants and heating plants
TOT Ref. No.
14918611
Document Ref. No.
275241-2017
Country
Poland
Notice type
Tender
Competition
ICB
Publication date
17 Jul 2017
Bid deadline
22 Aug 2017
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Construction works for power plants and heating plants
Description: Contract notice: Construction works for power plants and heating plants
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45251000, 71320000, 45210000, 45251000, 45330000, 45331000, 45331110, 45310000, 45231400, 09323000, 45231100, 45251000, 71320000, 45210000, 45330000, 45331000, 45331110, 45310000, 45231400, 09323000, 45231100
CPV Description: Construction works for power plants and heating plants.
Engineering design services.
Building construction work.
Plumbing and sanitary works.
Heating, ventilation and air-conditioning installation work.
Boiler installation work.
Electrical installation work.
Construction work for electricity power lines.
District heating.
General construction work for pipelines.
Wykonanie w formule „zaprojektuj iBuild: design documentation and construction work on: "Daszyn straw fired thermal power station". Reference Number: PPI.271.4.2017
The subject of the order is execution of design and build documentation for: "Thermoelectric power station fired with straw Daszyn "execution of technical documentation and construction robot based on constructionA triple-generation complex with accompanying infrastructure;
Main Site: Daszyn.
The subject of the order is execution of the design and construction formula: construction documentation and construction work on " CHP power plantIn accordance with the Functional Programs, hereinafter referred to as the PFU, and the project documentation, which is annexed to the Terms of Reference, by the Purchaser, including: a) CHP plant
Electric power of steam turbine min.-1.1 MW.
B) Passive biomass laboratory building
Building area 544.8 m
Usable area 767 m including light
Cubic capacity 2346.8 m
including: architectural and construction works, building installation with measuring the building ; Land development and development; Building equipment. C) heating system of networks and nodesEe
d) piping heating medium
1. Contractors may apply for the award of the contract, which: 1) Are not excluded from the public procurement procedure 2) They meet the conditions for participation in the proceedings. Description of the way of assessing the fulfillment of conditions for participation in the proceedings.
1) Possessing the competences or powers to pursue a specific occupational activity, if-This is due to separate regulations.
The ordering party did not specify the requirements. List of statements submitted by the contractor for the purpose of preliminary confirmation that he is not subject to exclusion and meets the conditions for participation in the procedure:
Each bidder must enclose a current statement in the scope confirming fulfillment of the conditions of participation in the proceedings specified in Chapter 10 of this SETC, -The Contractor shall submit the above statements in the form of a Single Document drawn up in accordance with the specimen form set out in the European Commission Implementing Regulation issued pursuant to Art. 59 sec. 2 of Directive 2014/24 / EU and Art. 80 sec. 3 of Directive 2014/25 / EU, ie Single EuropeanAn Ordering Document (JEDZ) constituting an attachment to the SETCPP
The contractor, who relies on the resources of other entities, in order to demonstrate the absence of the grounds for exclusion and fulfillment, to the extent it refers to their resources, the conditions of participation in the proceedings. HEADING about those entities. It also submits the original commitment of those entities to the original offerProvide the necessary resources for the execution of the order.
The contractor, who intends to subcontract parts to subcontractors, in order to indicate the absence of a basis for exclusion from participation in the proceedings, also includes HOW ABOUT SUBCONTRACTORS.
In the case of joint application by contractors for an order. Single European DocumentOrders, submitted by each of the Contractors jointly applying for the contract award.
It documents confirm the fulfillment of conditions for participation in proceedings and no grounds for exclusion from the proceedings to the extent in which each of the performers shows the fulfillment of conditions for participation in proceedings and the lack of grounds for exclusion from the proceedings.
To meet the condition required jIt is a demonstration of:
having financial assets or credit standing of at least 20, 000, 000, - PLN (in words: twenty million pln)
annual turnover of not less than PLN 20, 000, 000 in each of the last 3 financial years; Business activity is shorter for this period.
Paid Contractor's insurance against civil liability in the scope of conductedThe activity related to the subject of the order for a guarantee sum of not less than 20 000 000 PLN (in words: twenty million pln)
Assessment of fulfillment of the aforementioned conditions will be made on the basis of the information contained in the documents and statements specified in Chapter 11 of this SIWZ. The contents of the enclosed documents must clearly show that the above conditions of the Contractor fulfilled. In the seasonThe Contractor shall not be required to submit all the required documents in the SIWZ, unless the Contractor completes the offer despite the completion of the order. Contractor exclusion from participation in progressiveYou should submit:
1) information from the National Criminal Register within the scope specified in art. 24 sec. 1 pt. Ac 14 (not applicable to the person referred to in this provision if convicted for the offense listed in Article 24 (1) (13) (d) of the Public Procurement Law) and 21 of the Act and, in relation to conviction for Prison sentence, to the extent specified by the contracting authorityO based on art. 24 sec. 5, 5 and 6 of the Act, issued not earlier than 6 months prior to the deadline for submitting bids or requests to participate in the proceedings; 2) the certificate of the appropriate head of the tax office confirming that the contractor is not in arrears with the payment of taxes issued not earlier than 3 Months before the deadline for submitting bids or applications for-Admission to participate in proceedings or other document confirming that the contractor has entered into an agreement with the competent tax authority on the repayment of these duties together with possible interest or fines, in particular obtained the legal exemption, postponement or spreading into installments of outstanding payments or suspension of the whole performance Decision of the competent authority;The provision of the appropriate local organizational unit of the Social Insurance Institution or Agricultural Social Insurance Fund or other document confirming that the contractor is not in arrears with the payment of social security or health insurance contributions, issued not earlier than 3 months before the deadline for submission of tenders or requests to participate in the proceedings, orAnother document confirming that the contractor has entered into an agreement with the competent authority on the repayment of these receivables with possible interest or fines, in particular obtained the exemption, postponement or spreading into installments of outstanding payments or suspension of the performance of the competent authority in its entirety; From the relevant register or from central records iiInformation on business activities, if separate regulations require entry in the register or records, to confirm the lack of grounds for exclusion under Art. 24 sec. 5) declaration by the contractor about the non-payment of local taxes and charges referred to in the Act of 12 January 1991 on local taxes and charges (Journal of Laws of 2016, item 716);
6) statements made by youConclusions of affiliation or lack of affiliation to the same capital group; In the case of belonging to the same capital group, the contractor may provide evidence that links to another contractor do not lead to distortion of competition in the proceedings. According to Art. 24 sec. 11 of the Public Procurement Act, the contractor shall provide the contracting authority with a declaration of affiliation or non-membership-To the same capital group referred to in para. 1 pt. 23 of the Public Procurement Law within 3 days of the date of the information referred to in art. 51 sec. 1a, art. 57 sec. 1 or art. 60 d sec. 1 or the posting on the website of the information referred to in art. 86 sec. 5.
7) statement of the contractor not to issue a final sentence convicting the offender for a penalty offenseFreedoms or fines to the extent specified by the contracting authority pursuant to Art. 24 sec.
8) the contractor's declaration of lack of judgment against him as a preventive measure against the prohibition of applying for a public contract; 9) statement of the contractor not to issue to him a final administrative decision on violation of obligations under labor law, -Environmental protection or social security regulations to the extent specified by the contracting authority pursuant to art. 24 sec. Evaluation of the fulfillment of the aforementioned conditions will be made on the basis of the information contained in the documents and statements detailed in Chapter 11 of the SETCPP.
Internet address (URL): http://daszyna.bip.cc
Directive: Classical Directive (2014/25/EU)

Documents

Tender Notice
Login to view

Similar tenders

Poland Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Construction works for power plants and heating plants was 22 Aug 2017. Bidding is closed.

This tender has been issued by GMINA DASZYNA in Poland.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 45251000 - Construction works for power plants and heating plants, 71320000 - Engineering design services, 45210000 - Building construction work, 45330000 - Plumbing and sanitary works, 45331000 - Heating, ventilation and air-conditioning installation work, 45331110 - Boiler installation work, 45310000 - Electrical installation work, 45231400 - Construction work for electricity power lines, 09323000 - District heating, 45231100 - General construction work for pipelines.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 14918611. The purchaser document reference is 275241-2017.

See the Similar Tenders section on this page or browse other tenders from Poland.

This tender falls under Construction and Real Estate, Power and Energy in Poland. Suppliers in these sectors can track similar Poland tenders using CPV-based alerts.