Expired Tender Bulgaria ICB TOT Ref. 42003045

Contract notice: Construction work for water Tender - 42003045

Tender notice from Bulgaria, published on 01 Apr 2020.

Executive Summary

The ВОДОСНАБДЯВАНЕ И КАНАЛИЗАЦИЯ ЕООД — СТАРА ЗАГОРА has issued a Tender notice for the procurement of a Contract notice: Construction work for water and sewage pipelines in the Bulgaria. This Tender notice was published on 01 Apr 2020 and is scheduled to close on 11 May 2020, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 42003045, while the tender notice number is 156055-2020 and Register on the platform.

Key facts

Summary
Contract notice: Construction work for water and sewage pipelines
TOT Ref. No.
42003045
Document Ref. No.
156055-2020
Country
Bulgaria
Notice type
Tender
Competition
ICB
Publication date
01 Apr 2020
Bid deadline
11 May 2020
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Construction work for water and sewage pipelines
Description: Contract notice: Construction work for water and sewage pipelines
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45231300, 45231300, 45231300
CPV Description:
Engineering (Design, supervision and construction) - Reconstruction of the water supply and sewerage network of Stara Zagora with two separate positions
The subject of the contract is related to preparation of investment project in the "working" phase project, construction works and supervision during the construction of sites (separated by): site 1: reconstruction of the water supply and sewerage network of Stara Zagora south with two sub-projects and facility 2: reconstruction of the water supply and sewerage network of Stara Zagora north with two sub-projects.
Main Site: The territory of Stara Zagora District, Republic of Bulgaria. Some of the activities may be performed at the office and / or other location of the Contractor and / or third parties.The scope of the contract for Lot 1: Reconstruction of the water supply and sewerage network of Stara Zagora, southern part, consists of the following:
Activity 1: Development of a working investment project for the project "Reconstruction of the water supply and sewerage network of Stara Zagora, southern part" The following tasks are included in the activities:
1. A comprehensive overview of the existing idean investment project as well as other initial design data;
2. Development of an investment project in the phase of "work" project on all parts contained in the conceptual design, as well as in other design parts necessary for the approval of the work project and the lawful start of construction;
3. Perform all necessary actions resulting from the law on behalf of the Employer, related to the assessment of conformity and approval of the investment project.
Activity 2: Execution of construction and installation works for the site in accordance with the scope and content of the investment project approved under the current legislation. Within the framework of the activity, the contractor performs all construction and related works in accordance with the scope and content of the investment pa project that has been agreed and approved in the appropriate order. Also, within the contract, the contractor should prepare executive documentation in DWG format, which should include graphic objects, each with a unique identifier (id). An accompanying xlsx (Excel) file is prepared for each file in DWG format, which contains descriptive information / characteristics for DWG objects.aila with their unique identifiers entered. Linear objects (water mains and sewers) must be separated and described from axis to axis (from node to node). The data in DWG is packaged (eg zip) together with descriptive information in xlsx format and provided to the contracting authority on disk. All this in accordance with the general conditions for carrying out construction works in the Company.
Izoutside of the above, the contractor performs cadastral recording of the whole construction and submitting to the respective geodesy, cartography and cadastre data service according to Art. 54a, para. 2 of the Cadastre and Property Register Act. In addition, within the framework of the contract, the contractor performs all necessary samples and tests during the execution of the construction works until the completion of the site and its submission to the Contracting Authority, as well as post-completion samples.
Activity 3: Performing authoring during the execution of the construction works. When executing the contract, the contractor performs the functions of copyright supervision during the execution of the construction works within the meaning of the applicable legislation in force, including:
• changes in the approved investment project, in accordance with Art. 154 of the Spatial Planning Act (if necessary);
• explanations of the projectdecisions / if necessary;
• participation in drafting acts and protocols during construction;
• participation in regular meetings organized by the Building Supervision with participants in the construction process;
• drawing up orders in the Order Book;
• participating in
This first item includes two sub-projects, as follows:
Sub-unit 1: Reconstruction of internaland the water supply network of Stara Zagora DMA zones 1, 2, 3, 4, 5, 6 - south and the low water pipelines accompanying the reconstructed sewage system include:
Reconstruction of an internal water supply network of 10 619 m and other facilities and
Subproject 2: Reconstruction of an internal sewerage network of Stara Zagora - catchment area of a collector along Slavyanska Street and collectors included in Main Collector I, incl.nail:
Reconstruction of an internal sewerage network of 6 620 m and other facilities.
The participants must be entered in the Central Professional Register of the builder for the completion of construction of the fourth group, the second category, regardless of whether they participate for one and / or both lots, and for foreign persons in similar registers under the law of the Member State in which they are establishedram. In case the participant participates as an association / consortium, such registration must be held by each member of the association / consortium who will perform construction activities according to Art. 3, para. 3 and para. 4 of the LCS
When the tenderer envisages the participation of subcontractors, the requirement shall be proved for those subcontractors who, in accordance with the type and share of the contract they have been awarded, will execute the contractor.
When submitting a tender, the participants declare compliance with this selection criterion only by filling in the relevant section in the Single European Procurement Document (OEDOP) - Opportunity section of OEDOP.
Proof of the stated requirement
The document proving the requirement is a Certificate for registration in the CPSU with the Construction Chamber for execution of construction works of the construction category, which falls within the subject of the contract: works from the fourth group, the second category. If the participant is a non-resident, he may submit a valid equivalent document or declaration or certificate issued by a competent authority of a Member State of the European Union or of another State party to the Agreement on the European Economic Area
The documents proving compliance with the requirement set shall be submitted by the participant designated as a contractor or upon request during the procedure in the cases of Art. 67, para. 5 and Art. 112 PPL. Documents shall also be submitted to subcontractors and third parties, if any.
1. Documents to prove the requirement under Art. 62, para. 1, item 1 and /or 3 and / or 4 of the PPA - one or more of the following documents in connection with the requirement:
1. bank certificates;
2. the annual financial statements or their constituent parts, when published in accordance with the law of the country in which the participant is established;
3. a reference to the total turnover and / or turnover in the area covered by the contract.reason that the tenderer is unable to present the documents requested by the contracting authority, he may prove his economic and financial status by any other document that the contracting authority considers appropriate. contractor or upon request during the procedure in the cases of Art. 67, para. 5 and Art. 112 PPL. Documents shall also be submitted to subcontractors and third parties, if any.
2. Documents to prove the requirement under Art. 62, para. 1, item 1 and / or 3 and / or 4 of the Public Procurement Act - one or more of the following documents in connection with the requirement:
1. bank certificates;
2. the annual financial statements or their constituent parts, when required to be published in accordance with hthe legislation of the country where the participant is established;
3. a reference to the total turnover and / or turnover in the area covered by the contract.
When the tenderer is not able to present the documents requested by the contracting authority for good reason, he / she can prove his / her economic and financial status by any other document which the contracting authority deems appropriate.
DocThose for proving compliance with the stated requirement shall be submitted by the participant designated as a contractor or upon request during the procedure in the cases of Art. 67, para. 5 and Art. 112 PPL. Documents shall also be submitted to subcontractors and third parties, if any.
1.Tech. and Prof. Opportunities: requirements for experts from 5 to 10 incl .: Expert to have special experience1 design for the part of invest. project for which is proposed in this contract. 1 expert can combine more than 1 position (from 5 to 10 incl.) In case he / she corresponds to the ones indicated for the corresponding. position requirements, but this is only valid for participation in only 1 position, if both parties are participating simultaneously. positions The participants should have separate teams for each positionand for each item this item is applicable individually. For foreign persons, Eq. documents to be followed according to the law of the country where they are established. In the case of a non-legal entity, the requirement under item 3 applies to the entity as a whole. When using a subcontractor, the requirement under item 3 also applies to each 1 of the subcontractors, according to the type, etc.come from the order they will fulfill. When submitting the offer, the Student shall provide the information required in Part IV, "Selection Criteria", "B.Technical and Proficiency." of EDES for the professional competence of the management staff, as required by the contracting authority in the docu- ment regarding the manner of providing information. In the case of an association that is not a legal entity, the relevant information. is inserted in Part IV, "Creeselection theories ", " C. Tech. and prof. "EDED of the members of the association, through which the student proves the requirements and the documents are submitted by those members. With the participation of subcontractors, EDES and the documents are also presented for each of the subcontractors indicated.
2. Award criterion : optimum price / price ratio, which is evaluated on the basis of price as well as costfirs, including quiche, eco. and social aspects. KO has a poppy. value is 100 t. The formula is: KO = P1 P2. The following sub-indicators and their constituent components (mandatory and upgrading) are included in indicator P1: 1. Design and construction works; 1.1.A.Prime for design and construction, guaranteeing the fulfillment of the order; 1.1.B.Organization of staff in relation to mutual relations. m / in the countries during delivery of the order;1.2.A. Linear mud. schedule and pr-e for their tech. last, continued and distribution over time of work; 1.2.B. 2. Design and construction proposal guaranteeing timely implementation within the available budget and Environmental protection measures, 2.2.A. General social aspects and 2.2.B. Specific socialaspects. Max. the points of these sub-indicators from the first evaluation indicator are 60 points. The second indicator is P2 Bid.
P2 = Bid Minimum Price in BGN (excluding VAT) * 40
Bidder`s suggested price in BGN (excluding VAT)
3. Authorities providing the information. for taxes, environment, employment protection and working conditions are: NRA, MOEW, EA and EA "GIT". 4. SPEC. NAT. GROUNDS FOR EXCLUSION: Oucht, shall declare the absence or presence of a sentence for a crime under Art. 108a, Art. 159a-159d, Art. 172, Art. 192a, Art. 194-217, Art. 219-252, Art. 253-260, Art. 301-307, Art. 321, 321a and Art. 352 - 353f of the Criminal Code; The student (and only he) shall not be a related party to other participants in this procedure, in accordance with Art. 101, para. 11 PPA; The participant should not be identified by Vla bad luck force. decree, or judgment, violation of Art. 61, para. 1, Art. 62, para. 1 or 3, Art. 63, para. 1 or 2, Art. 118, Art. 128, Art. 228, para. 3, Art. 245 and Art. 301-305 of the Labor Code or Art. 13, para. 1 of ZTMTM or similar obligations established by an act of com. an authority under the law of the State in which the study is established or similar obligations established by an act of com. authority according tothe horse of the country where the participant is established; The circumstances under Art. 69 of the Law on Public Offering of Public Offices and the Code should meet the requirements of Art. 3, item 8 and art. 4 by ZIFODRUPDRKTLTDS.
Internet address (URL): http://www.wik-stz.com

Documents

Tender Notice
Login to view

Similar tenders

Bulgaria Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Construction work for water and sewage pipelines was 11 May 2020. Bidding is closed.

This tender has been issued by ВОДОСНАБДЯВАНЕ И КАНАЛИЗАЦИЯ ЕООД — СТАРА ЗАГОРА in Bulgaria.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 45231300 - Construction work for water and sewage pipelines.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 42003045. The purchaser document reference is 156055-2020.

See the Similar Tenders section on this page or browse other tenders from Bulgaria.

This tender falls under Construction and Real Estate in Bulgaria. Suppliers in these sectors can track similar Bulgaria tenders using CPV-based alerts.