Expired Tender Poland ICB TOT Ref. 32659409

Contract notice: Construction work for water Tender - 32659409

Tender notice from Poland, published on 02 May 2019.

Executive Summary

The SEWIK TATRZA?SKA KOMUNALNA GRUPA KAPITA?OWA SP. Z O.O. has issued a Tender notice for the procurement of a Contract notice: Construction work for water and sewage pipelines in the Poland. This Tender notice was published on 02 May 2019 and is scheduled to close on 16 May 2019, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 32659409, while the tender notice number is 202258-2019 and Register on the platform.

Key facts

Summary
Contract notice: Construction work for water and sewage pipelines
TOT Ref. No.
32659409
Document Ref. No.
202258-2019
Country
Poland
Notice type
Tender
Competition
ICB
Publication date
02 May 2019
Bid deadline
16 May 2019
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Self Financed

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

Object of the contract
Construction work for water and sewage pipelines
Description: Contract notice: Construction work for water and sewage pipelines
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: Lowest price
CPV code: 45231300, 45000000, 45111200, 45111240, 45112000, 45112210, 45200000, 45231100, 45231111, 45231112, 45231113, 45232000, 45231300, 42131160, 45231300, 45000000, 45111200, 45111240, 45112000, 45112210, 45200000, 45231100, 45231111, 45231112, 45231113, 45232000, 42131160
CPV Description: Construction work for water and sewage pipelines.
Construction work.
Site preparation and clearance work.
Ground-drainage work.
Excavating and earthmoving work.
Topsoil-stripping work.
Works for complete or part construction and civil engineering work.
General construction work for pipelines.
Pipeline lifting and relaying.
Installation of pipe system.
Pipeline relaying works.
Ancillary works for pipelines and cables.
Hydrants.
Reconstruction of the water supply network along with connections to buildings at ul. Pocztowcow and ul. Żeromskiego w Zakopanem
Reference Number: 3S / Pocztowcow - waterworks / 2019
1. The subject of the order is the reconstruction of the water supply network along with the connections at ul. Pocztowcow and Żeromskiego in Zakopane.
Main Site: Wojewodztwo Małopolskie, Powiat Tatrzański, Gmina Miasis Zakopane, Pocztowcow Street and Żeromskiego Street, POLAND
1. The subject of the order is the reconstruction of the water supply network along with the connections at ul. Pocztowcow and Żeromskiego in Zakopane.
2. The scope of the order includes the reconstruction of the water supply network of the following lengths:
- 0 90 mm PE 191.14 mb,
- 0 63 mm PE 1.45 m,
- 0 32 mm PE 120.13 mb.
The contracting authority informs that pThe above-mentioned lengths of the water supply network result from the project documentation, determine the estimated needs of the Employer during the contract period, not constituting a commitment for the Employer to its full implementation, or the basis for seeking compensation by the Contractor due to failure to complete the subject of the contract. Final settlement of the Contractor's remuneration for the lecturethe subject of the contract will be based on the actual length of the water supply network, determined on the basis of an as-built geodetic survey carried out by an authorized surveyor, confirmed by the inspector of investment supervision and lump-sum prices of 1 m of the aqueduct as their quotient. 3. The scope and description of the order contains :
- Renovation construction project sWater supply system Annex I to SIWZ,
- Technical Specification of Construction Work and Acceptance (hereinafter: "STWiORB") Annex II to the ToR.
Documentation mentioned in point 3.4 of the ToR, hereinafter referred to as "project documentation" or "technical documentation" is an integral part of the ToR and the contract template.
Important provisions related to the implementation of the order:
a) Contractor guarantortakes delivery of the subject of the order in accordance with the conditions set out in this ToR and the project documentation referred to in point. 3.4 of the SIWZ above.
B) The offer submitted by the Contractor must include all investment costs, including fees related to obtaining current permits as well as costs of restoring the area to the original condition.
C) The order should be made of materials purchased and forThe construction materials are to comply with the SEWiK connection conditions, design documentation and the Technical Specification for Construction Work and Acceptance. e) The materials purchased must have appropriate certificates and approvals allowing the use of external water supply . f) The Contractor under his own responsibility and reinsyko will get all the information that may be necessary to prepare the offer.
g) Contractors should read due diligence with the content of the tender documentation and obtain reliable information about the terms and commitments that in any way may affect the value, nature of the offer or implementation of the order . In the situation when the Contractor wins the tender, complaints relate toce changes in the value of the offer in the light of the Contractor's obligations set out above shall not be considered. h) The Contractor shall bear all costs related to the preparation and submission of its offer and all related documents. i) For the construction works provided for in the subject Ordering Party has notification of the reconstruction of the network not requiring a building permit.
j) Providing obgeodesy servicemen and execution of geodetic survey as-is belonging to the Contractor robot. k) Contractor is obliged to provide a guarantee:
- for material and construction works for 3 years
l) After the works performed Contractor will be required to obtain written declarations of all owners of plots that they do not raise any reservations about the order leftand restoration of the area to the original condition.
The detailed scope and description of the subject of the order is contained in the ToR and the project documentation mentioned in point. 3.4 of the ToR.
Proceedings for granting a public order are carried out in the form of an unlimited tender based on the provisions of the SEWiK Sector Contract Provisions. • Contractors may apply for the award of a public contract.the surveyors meet the conditions regarding: - Having the right to perform a specific activity or activity, if the law imposes an obligation to have such rights:
The ordering party waives the requirement for this condition to be satisfied. The assessment of compliance with this condition will be made on the basis of a submitted declaration on meeting the conditions of participation in the proceedings in accordance with art. 15 Regulaminu.
1. The proceeding to which this document applies is marked with the sign: 3S / Pocztowcow-wodociąg / 2019. Contractors should refer to the above-mentioned indication in all contacts with the Purchaser.
2. Proceedings for granting a public order are carried out under an open tender procedure with an estimated value not exceeding the amounts specified in the regulations issued onbased on art. 11 para. 8 of the PZP Act based on the provisions of SEWiK Sectoral Contracts Orders.
3. Before submitting the offer, the Contractor should read the Sectoral Contracts Regulations applicable to SEWiK.
4. The content of the Regulations is available on the Employer's website: http://www.sewik.com.pl/images/pdf/regulamin_zamowien_2014_04.pdf
5. In unregulated mattersthis ToR shall be governed by the relevant provisions of the SEWiK Sector Inquiry Regulations and the provisions of the Act of 23.4.1964. Civil Code.
6. The Contracting Authority informs that the length of the water supply network results from the project documentation, determine the estimated needs of the Employer during the contract period, not constituting a commitment for the Employer to its fullimplementation, or the basis for the Contractor's claim for damages for non-execution of the entire subject of the order. The final settlement of the Contractor's remuneration for the execution of the subject of the contract will be based on the actual length of the water supply network, determined on the basis of an as-built geodetic survey carried out by an authorized surveyor, confirmedby the investor's supervision inspector and lump-sum prices for the execution of 1 m of the aqueduct as their quotient
7. The Employer informs that whenever the subject of the order specified in the SIWZ, design documentation and STWiORB is described by indication of the trademark, patent or origin, the Employer allows for equivalent solutions, i.e. having features, technical and operational parameters, applicationsnot worse than described in the SIWZ, project documentation and STWiORB. Demonstration of the equivalence of the offered object rests with the Contractor. In the situation when the Contractor intends to use equivalent materials or equipment, he is obliged to attach to the offer a list of offered equivalents along with the characteristics and documents confirming the same or better quality, e.g. specificationsquality, quality control certificates, certificates, etc., which will confirm in a manner that raises no doubts the equivalence of the proposed materials or devices. The Employer requires employment throughout the duration of the contract by the Contractor or Subcontractor based on a contract of employment within the meaning of the provisions of the Act of 26.6.1974. The Labor Code of persons performing the activities of equipment operators cconstruction site or people performing installation work and related to the construction of the water supply network.
9. The Contractor will be bound by the offer for a period of 45 days. The period of being bound by the offer starts as soon as the deadline for submission of tenders expires. (Rule 48 of the Rules of Procedure)
Internet address (URL): http://www.sewik.com.pl

Documents

Tender Notice
Login to view

Similar tenders

Poland Public Procurement Intelligence

Frequently asked questions

The bid deadline for Contract notice: Construction work for water and sewage pipelines was 16 May 2019. Bidding is closed.

This tender has been issued by SEWIK TATRZA?SKA KOMUNALNA GRUPA KAPITA?OWA SP. Z O.O. in Poland.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is Self Financed

The tender is classified under the following CPV code(s): 45231300 - Construction work for water and sewage pipelines, 45000000 - Construction work, 45111200 - Site preparation and clearance work, 45111240 - Ground-drainage work, 45112000 - Excavating and earthmoving work, 45112210 - Topsoil-stripping work, 45200000 - Works for complete or part construction and civil engineering work, 45231100 - General construction work for pipelines, 45231111 - Pipeline lifting and relaying, 45231112 - Installation of pipe system, 45231113 - Pipeline relaying works, 45232000 - Ancillary works for pipelines and cables, 42131160 - Hydrants.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 32659409. The purchaser document reference is 202258-2019.

See the Similar Tenders section on this page or browse other tenders from Poland.

This tender falls under Construction and Real Estate, Technology and Equipment in Poland. Suppliers in these sectors can track similar Poland tenders using CPV-based alerts.