Object of the contractConstruction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
Description: Contract notice: Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork
Authority Type: Ministry or any other national or federal authority
Contact Nature: Works
Procedure: Restricted procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45230000, 45231300, 45232000, 45232100, 45232140, 45232151, 45232410, 45232424, 45232440, 45232450, 45232452, 45232453, 45232454, 45230000, 45231300, 45232000, 45232100, 45232140, 45232151, 45232410, 45232424, 45232440, 45232450, 45232452, 45232453, 45232454
CPV Description: Construction work for pipelines, communication and power lines, for highways, roads, airfields and railways; flatwork.
Construction work for water and sewage pipelines.
Ancillary works for pipelines and cables.
Ancillary works for water pipelines.
District-heating mains construction work.
Water-main refurbishment construction work.
Sewerage work.
Sewage outfall construction work.
Construction workfor sewage pipes.
Drainage construction works.
Drainage works.
Drains construction work.
Rain-water basin construction work. . sewer exchange and climate protection at establishment 101. The castle. The castle is a protected ancient monument and bThe Main Project: Kastellet
The proposed project includes renewal of the drainage system in Kastellet, establishment of underground delay basin below the church site, renovation of existing pumping station for delay basin and establishment of new underground pumping station north-east of Kommandantgarden with controlled sub-drilling for Copenhagen. Port for 3 pcs.pressure pipes with discharge structures in the seabed for the discharge of rainwater in connection with cloudbursts. In addition, the project contains the setup of the power generator for pumps in the pump station incl. construction of a building around the generator.
The project involves digging, soil and pipeline work as well as redirection of coatings throughout the Kastellet, and there are also partial replacements attagnedl0b. In this connection, it is pointed out that the Kastellet and the surrounding areas are protected ancient monuments with buildings that are protected by buildings. The project also includes extensive sediment, soil and gravel disposal and replacement materials.
In addition to the preventive measures listed above, the project involves the replacement and renewal of water pipes and internal remotermer0r in the terrain. Pipelines for the castle's buildings are renewed towards and through foundations. Internal replacements of plugs are carried out in a number of buildings, including necessary internal excavation and addition work, finishing work and minor masonry and painting work. In connection with the work, minor works on parcels are furthermore pared. Some interior work on. inInstallations, including work on walls and floors, are carried out by another contractor, which is why coordination must be done in connection therewith.
In order to ensure optimal use of synergies by carrying out all kinds of preventive measures such as replacement of water pipes and district heating pipes, the Ministry of Defense's Property Agency has chosen not to divide the 2 works into sub-contracts, but instead choosegt to offer the project as a single main contract due to the complexity of the project as well as for financial reasons. paregnes construction site facilities north of Kastellet near Norwaythe bridge and the castle itself. There will be construction site for the Langelinie Bay, where the construction works for the pressure pipes are placed, and construction site on the Pr-vestenen South for pipework and concrete joints and shipment thereof. Concrete work,
- Dry work,
- Plumbing workjde,
- Plumbing work,
- Plumbing in soil,
- Electricity work,
- Building automation,
- Chairs,
- Planting.
The project's design is divided into 6 zones of different duration and with overlapping execution period. It is part of the main contract to plan the work of the zones, including planning of work in zone subdivisions, ensuring that the castle's buildings can be used throughout.sperioden. Likewise, it is part of the main contract to foresee traffic planning by, among other things. signage and decommissioning as well as redirection of driving and going traffic throughout the execution period combined with own contractors' carriage.Applicants must enclose completed ESPD, Section IV.B, stating the following information, cf. Section 142 and 154 of the Public Procurement Act:
1) Total applicant's turnover in each of the last 3 completed financial years;
2) Applicant's equity in the most recent completed financial statements.
ESPD serves as a preliminary evidence that the applicant meets minimum eligibility requirementsin relation to economic and financial capacity and / or how the applicant meets the selection criterion, cf. clause II.2.9). Before the award decision, the tenderer whose contractor intends to award the contract must provide evidence that the information in the ESPD is correct. When the contracting authority so requires, the following documentation must be submitted for financial and financial reasonsnancial capacity: - - (turnover of the last three completed accounts): - Declaration on the total turnover of the tenderer in each of the last 3 completed financial years. If the information is not available for 3 years, because the tenderer's business is established later than this, the date of establishment of the company and the available information are stated. By an association of companies (eg. a consortium) the information must be provided for each of the participating companies in the association. If the bidder bases itself on the financial and financial assets of other entities (eg, a parent, a subsidiary or a subcontractor), the information must also be provided for those entities. regnskabsar, as soon as the publication of the balance sheet is mandatory in the country where the company is established or other evidence of the size of the equity. For an association of companies (eg a consortium) the information must be provided for each of the participating companies in the association. Bases the bidder on the financial and financial form of other entities (eg a mother-, the sister company or a subcontractor), the information must also be provided for these units. In that case, the requirements must be met by the association's undertakings together. A declaration of solidarity must be made, provided that the consortium is given creditlt the contract. The contracting authority has prepared a template for consortium declaration which the applicant may use. must apply, as soon as the contracting authority so requests, to document that they have the resourcess required to fulfill the contract by submitting a statement of support or other evidence that the application is actually in line with the necessary financial and financial form, cf. 1 and 2. This shall demonstrate that the entity (s) in question is legally obliged to the applicant. Otherwise, the contracting entity will not pay attention to other units' accountsomic and financial assets other than the applicant's own. The contracting authority has prepared a template for support declarations that the applicant can use.
Participation in the tender can only be done electronically via the contracting authority's applied electronic tender system, iBinder, cf. In order to gain access to the tender documents, the applicant must be registered or register as a user.The gene or offer contains several editions (versions) of the same document, the latest uploaded version will be the current one.
All communication in connection with the tender procedure, including questions and answers, must be made via the electronic tender system, iBinder. Any questions to the tender should be sent via the query function on iBinder no later than Tuesday, 26 March 2017. The questions will staye answered no later than 6 days before the application deadline. It is the responsibility of the applicant to keep up-to-date on any publications on iBinder.
As soon as the applicant experiences problems with the system, iBinder's support can be contacted by email at
[email protected] or by phone (45) 89 88 78 30.
Applications must be as their application submit an ESPD as a preliminary evidence of the provisions of section 148 (1) of the Public Procurement Act. 1, no. 1-3, nmentioned conditions. For an association of companies (eg a consortium), a separate ESPD must be submitted for each participating economic operator. If the applicant is based on the other units' form, an ESPD must be submitted for each of the units on which it is based. Reference is made to the client's instructions for ESPD.
The applicant will be excluded from participation in the tender processif the applicant is covered by the mandatory exclusion grounds mentioned in sections 135 and 136 of the Public Procurement Act, and the grounds for exclusion stated in section 137 (1) of the Public Procurement Act. 1, no. 2, unless the applicant has provided sufficient evidence that this is trustworthy in accordance with section 138 of the invitation to tender Act.
Before the award decision, the tenderer whose contractor intends toshare the contract, provide documentation for the information provided in the ESPD pursuant to section 151-152 of the Public Procurement Act, cf. section 153. In so far as references cf. intends to award the contract, provide satisfactory performance and result certificates, cf. Section 155, no. 1 of the Public Procurement Act.l.
Attention is drawn to the fact that for the pre-qualified tenderers it will be possible to participate in the inspection of the Kastellet, 2100 Copenhagen 0, Wednesday 8.5.2019 at. 10:00. Tenderers wishing to participate in the survey, must register no later than 3 days before the inspection, stating the company affiliation and the number of participants with it in section. I.1) contact person specified. Contracting Authoritycan reduce the number of participants per company.
Internet address (URL): http://www.ejendomsstyrelsen.dk