Object of the contractConstruction work for electricity power lines
Description: Contract notice: Construction work for electricity power lines
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45231400, 44212222, 44212224, 45232200, 71323100, 45231400, 44212222, 44212224, 45232200, 71323100
CPV Description: Construction work for electricity power lines.
Electricity transmission pylons.
Poles for carrying overhead lines.
Ancillary works for electricity power lines.
Electrical power systems design services.
Increased transport capacity. : 13328043/2019/21992
The acquisition is designed for a complex work project that includes both executionie works, delivery of equipment, as well as services: design, tests, tests and verifications including PIF, etc.
Main Site: Stejaru Gheorgheni - Fantanele
Quantities of equipment, construction-assembly works and services, necessary to achieve the investment objective "Increasing the transport capacity LEA 220 kV Stejaru-Gheorgheni-Fantanele", are provided in the Technical Project SpecificationTasks.
Requirement 1
The bidders, the third-party supporters and the subcontractors must not be found in the situations provided in art.177, 178, 180 of Law no. 99/2016. Method of fulfillment: The DUAE will be completed in accordance with art. 202 para. (1) of Law 99/2016. The supporting documents proving the fulfillment of those assumed by completing the DUAE will be presented, upon requestthe contracting entity only to the bidder ranked first in the intermediate ranking drawn up at the end of the evaluation of the tenders are: - certificates confirming the lack of outstanding debts, regarding the payment of taxes, taxes or contributions to the general consolidated budget (local budget, state budget, etc.) at the time of presentation; - the criminal record of the economic operator andand of the members of the administrative, management or supervisory body of the respective economic operator, or of those who have power of representation, decision or control within it, as it results from the certifying certificate issued by the ONRC / the constitutive document; - as appropriate, documents proving that the economic operator can benefit from the derogations provided for in art. 179 para. (2), art. 180 paragraph (2), art. 184 of Law 99/2016 on public procurement; - other edifying documents, as the case may be. If in the country of origin or the country in which the bidder / supporting third party / subcontractor is established, documents of the nature provided for above are not issued or those documents do not cover all the situations provided for in articles 177, 178 and 180, the entitythe contracting party has the obligation to accept a declaration on its own responsibility or, if there is no legal provision in the respective country regarding the declaration on its own responsibility, an authentic statement given before a notary, an administrative or judicial authority or a professional association that has competence in this regard
Requirement 2.
Persons with decision-making function within the frameworkl the contracting authority / entity regarding the organization, development and completion of the award procedure are: CARAȘOL Marius Danuț - Managed President, FLOREA Andreea - Georgiana - Managed Member, TEODORU Alina Elena - Managed Member, ANASTASE Claudia Gina - Managed Member, SAVU Adrian - Managed member, HATEGAN Ioan Dorin - DTEETN Director, DINU Ana Iulia - UEFA Director, STANCIU Florin - DSFTM manager, ZIRNOVAN Cristiana - DBRM manager, PIRVU Beatrice -Specialist- CFP manager, RADUCANU Florentina - Investment management director, DAVID Adina Georgiana - DJC director, STRATON Cristiadis Alina - DAJAR manager, NICOLAE Sorinela, legal counselor Aurelia - legal advisor, LANGER Georgiana - legal advisor, , POPESCU Adriana - legal advisor, SANDU Eugen Petru - Head of Serv. SSMASMI, SMEEIANU Ion - DMIPCEIE Director, SIMION Adrian Mihai - UMICA Director, HARHOIU Marius Serban - Commercial Director, RADESCU Cerasela Aritina - DAMMMVBSA Manager, IFRIM Ionut Irinel- DAIMMSP Manager, POPOVICI Nicoleta Raluca - SEI SAI, OPRIS expert public, VORONCA Simona Louise - Manager DICr, DINA Alexandru - manager of proiect, GOGUTA Marius Florinel- Head of CE Suceava, TUDORACHE Lavinia - Main specialist engineer - ST Bacau, MAZILU Adriana - Project manager - ST Bacau, GHERLA Codrin - Main engineer - ST Bacau, STEF Ion Ovidiu - Project manager - ST Sibiu, SIMBOTIN Marius - Engineer LEA - ST Sibiu, MORARU Aurora - Expert electrical networks - ST Sibiu, MIRESCU Octavian Florin - Head of investment services ST Sibiu, FERECATU Monica Iuliana - Industrial strategy specialist, VASIU Viorel - DEM-RIGHT specialist engineer.
Fulfillment mode:
The economic operators (individual bidder, member of an association, subcontractor, third party supporter) must not find themselves in the situation provided for in art. 73 according to L99 / 2016. The way in which it can be fully demonstrated ... details on www.e-licitatie.ro
Scertify the average annual turnover The Bidder (Individual Economic Operator or members of the association together) must prove an average of the turnover for the last 3 financial years ended, respectively 2016, 2017, 2018 of at least RON 26, 000, 000. The equivalent in another currency is calculated at the annual average exchange rate / LEI established by the NBR for the respective years, publicat the site www.bnr.ro.
Other economic or financial requirements If the tenderer demonstrates his economic and financial situation by invoking the support granted, by another person, then he has the obligation to prove the support he benefits from., by presenting a firm commitment of the respective person, confirming that he will make available to the operator the savingsc of the financial resources invoked. Information about the third party supporter will be presented. The supporting third party will present a declaration of non-compliance within the art.73 Law no. 99/2016 and in the situations provided by art.177 of Law no. 99/2016; art 178 of Lg 99/2016 and art. 180 of Law no. 99/2016 and related information art.188 / Law no.99 / 2016.
For additional instructions necessary biddersplease, please access the annex to this announcement, named: ANNEX INSTRUCTIONS FOR OFFERS.
Visit to the site- Op.ec.c expressing its intention to visit the site. may participate in the visit organized by EC on the 21st day, the 22nd day and the 23rd day from the public date. AP, between 9 am 15. Pt. to participate in the site op.ec. tb. to send EC a written ground in this regard. ground. must be received by the AC at least 6 days before the visit date. The request consists of sending to the email address:
[email protected] a Formul.pt. access from Sect II-Form. (completed, stamped and signed by the company representative). In the annex to the access form the full name of the persons who will participate in the visit will be mentioned. It will also be submitted with Form.deaccess and a copy of the identity document (ID or passport) of the pers. listed in the annex. Only nominal persons will be able to attend the visit to Amplas. in the request mentioned above. The costs incurred by the site (transport, accommodation, etc.) for the pers. who will participate. from the op. ec. will be borne by them
Internet address (URL): www.transelectrica.ro