Object of the contractConstruction work
Description: Contract notice: Construction work
Authority Type: Utilities entity
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: Agreement between the European Union and the Swiss Confederation
Award criteria: The most economic tender
CPV code: 45000000, 45000000
CPV Description: Construction work.
ZEB, Olten Aarau, Integrale 4-lane (Eppenbergtunnel): railway technology.
The project perimeter Olten Aarau is currently the only double-lane section of the Bernbach Bernviertel quadripartite system and therefore a crucial bottleneck on this axis. The section Dulliken Daeniken forms a further bottleneck as a 3-track route, whichThe project perimeter Olten Aarau is currently the only two-lane section of the four-track system Bern in the section Daeniken Woeschnau Olten Zuerich and therefore a crucial bottleneck on this axis. The section Dulliken Daeniken imageAs well as a 3-lane track, a further bottleneck, which will be extended to a 4-lane system in the course of the Eppenberg tunnel.
The ZEB train program, Olten Aarau, Integrale 4-Spur (Eppenberg Tunnel) includes the equipment of the Two-lane railway tunnel Eppenberg with essentially construction work from the specialist areas of roadway (track construction), cable construction, -- Main quantities are shown in Part B1, item 143. - Proof to EK1.1:
1 Supplier's reference as GU / TU. As a reference, an essentially concluded, resp. In reference object via the bearbeOf a project comparable to the intended task with a comparable complexity (commissioning of the objects not earlier than year 2000)
Evidence of EK1.2:
1 reference of the supplier for the following track construction works (installation in operation, commissioning of the objects not earlier than Year 2000): - solid road in the tunnel (tunnel length greater than 1 000 m), normal or mete(Total length of the track), track, track, track, track, track, track, track, track, track or track track By division: 1 Supplier's reference. As a reference, a substantially completed, in-service reference object is defined by the processing of a reference object, (Commissioning of the objects not earlier than year 2000).
Several divisions can also be detected within the same reference object. If the requested reference is obtained from a subcontractor, the supplier must submit a confirmation from the subcontractor that he is performing the work in the order
The performance of subcontractors may not exceed a volume of 50% of the total contract.
Proof of EC 2:
Declaration of the turnover of the contractor Last three years. The contract value per year may not exceed 30% of the average JOf the last 3 years. The supplier shall designate the guarantor for the guarantee provided for, and certify that he can provide it within one month of the award decision in accordance with the draft contract.
Proof of EC 4:
copy of the contract Certificate of the quality system according to ISO 9001 or in the case of a non-certified company quality system Description of the system. In the case of consortia, such proof must be provided by the lead Member only.
Partial offers are not permitted.
Conditions for non-WTO countries: NoneThe contracting authority awards public contracts for services in Switzerland only to suppliers who ensure compliance with the provisions on labor protection and the working conditions for employees and the equal pay for men and women.
Other information: Entry of the offer for pre-filled persons: 25.8 .2017 As pre-approved companies, En: ARGE Marti Eppenberg consisting of the companies Marti Tunnelbau AG Mosseedorf; Marti AG Solothurn as well as Marti AG Zuerich.
Right of appeal: This appeal may be lodged in writing with the Bundesverwaltungsgericht, Postfach, 9023 St. Gallen, in accordance with Article 30 BoeB within 20 days of publication. The complaint must be submitted in duplicate and has the requestsN statement of the evidence and the signature of the complainant or his representative. A copy of the present publication and existing evidence are to be enclosed.
Final date / comments: The postmark (company stamps are not valid as postmark) or barcode receipt of a Swiss post office or at AuslaendiOf the receipt of a Swiss diplomatic or consular post. In the case of the transfer of the offer to a diplomatic or consular representation of Switzerland abroad, the supplier is obligated to send the confirmation of receipt of the corresponding representation by e-mail (
[email protected]) by SBB AG at the latest by the deadline of the offerReport to. Offers can not be handed over personally, respectively are not accepted on the spot. The technical details and the price offer are indicated by the corresponding description and the keyword in two separate, sealed envelopes e. Please note the following information: "Please do not open / offer: ZEB, Olten Aarau, Integrale 4-Spur (Eppenbergtunnel)inzureichen.
National reference publication: Simap dated 30.5.2017, Doc. 967155.
Desired deadline for written questions until: 23.6.2017.
Invitation documents are available from 30.5.2017.
Internet address (URL): https://www.simap.ch
Directive: Classical Directive (2014/25/EU)