Object of the contractConstruction work
Description: Contract notice: Construction work
Authority Type: Regional or local authority
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45000000, 45314310, 45421100, 45262100, 45332000, 45100000, 45332200, 45315700, 45232130, 45232150, 45315600, 45331100, 45317300, 45310000, 45443000, 45312300, 45231220, 45223100, 45262120, 45261320, 45312310, 45320000, 45262110, 45223500, 45230000, 45333000, 45330000, 45231600, 45200000, 45231300, 45315300, 45211000, 45314000, 45111291, 45112100, 45311200, 45110000, 45324000, 45300000, 45312000, 45410000, 45311100, 45400000, 45331000, 45233000, 45262500, 45421152, 44130000, 45111300, 45232423, 45262522, 45316100, 45314300, 45331210, 45442100, 45351000, 45311000, 45315100, 45111100, 45450000, 45000000, 45314310, 45421100, 45262100, 45332000, 45100000, 45332200, 45315700, 45232130, 45232150, 45315600, 45331100, 45317300, 45310000, 45443000, 45312300, 45231220, 45223100, 45262120, 45261320, 45312310, 45320000, 45262110, 45223500, 45230000, 45333000, 45330000, 45231600, 45200000, 45231300, 45315300, 45211000, 45314000, 45111291, 45112100, 45311200, 45110000, 45324000, 45300000, 45312000, 45410000, 45311100, 45400000, 45331000, 45233000, 45262500, 45421152, 44130000, 45111300, 45232423, 45262522, 45316100, 45314300, 45331210, 45442100, 45351000, 45311000, 45315100, 45111100, 45450000
CPV Description: Construction work.
Installation of cable laying.
Installation of doors and windows and related components.
Scaffolding work.
Plumbing and drain-laying work.
Site preparation work.
Water plumbing work.
Switching station installation work.
Storm-water piping construction work.
Works related to water-distribution pipelines.
Low-voltage installation work.
Central-heating installation work.
Electricalinstallation work of electrical distribution apparatus.
Electrical installation work.
Facade work.
Antenna installation work.
Construction work for gas pipelines.
Assembly of metal structures.
Scaffolding erection work.
Guttering work.
Lightning-protection works.
Insulation work.
Scaffolding dismantling work.
Reinforced-concrete structures.
Construction work for pipelines, communication and powerlines, for highways, roads, airfields and railways; flatwork.
Gas-fitting installation work.
Plumbing and sanitary works.
Construction work for communication lines.
Works for complete or part construction and civil engineering work.
Construction work for water and sewage pipelines.
Electricity supply installations.
Construction work for multi-dwelling buildings and individual houses.
Installationof telecommunications equipment.
Site-development work.
Trench-digging work.
Electrical fitting work.
Building demolition and wrecking work and earthmoving work.
Plasterboard works.
Building installation work.
Alarm system and antenna installation work.
Plastering work.
Electrical wiring work.
Building completion work.
Heating, ventilation and air-conditioning installation work.
Construction, foundation and surface works for highways, roads.
Masonry and bricklaying work.
Installation of partition walls.
Sewer mains.
Dismantling works.
Sewage pumping stations construction work.
Masonry work.
Installation of outdoor illumination equipment.
Installation of cable infrastructure.
Ventilation installation work.
Painting work.
Mechanical engineering installation works.
Electrical wiring and fitting work.
Electrical engineering installation works.
Demolition work.
Other building completion work.
Construction works rely on. on building modernization, with the liquidation of low-emission sources of a residential building at ul. Mickiewicza 6 in Knur-w as part of the task invest .: Thermomodernization ...
Reference Number: ZP.271.2.59.2019
Subject of the contract includes construction workstaking advantage of the building's thermomodernization, with the liquidation of low emission residential building at ul. Mickiewicza 6 in Knur-w as part of the investment task: Thermomodernization of historic buildings of Old Knur-w with the elimination of low-emission sources.
Main Site: KNUROW
1. The subject of the contract includes the execution of construction works consisting in thermomodernization of the building, with the liquidation of low building emissionsresidential building at ul. Mickiewicza 6 in Knur-w as part of the investment task: Thermomodernization of historic buildings of Old Knur-w with the elimination of low-emission sources.
2. With a view to the proper operation of the building in the future, the following are envisaged:
1) demolition works related to the building's thermal modernization;
2) construction works related to the building's thermal modernization,
3) robot bconnected with the elimination of coal heating and gas installation, central heating, domestic hot water and mechanical ventilation;
4) other construction works.
3. The scope of works:
1) demolition works related to building thermomodernization,
2) construction works related to building thermomodernization,
3) construction works related to gas installation, central heating, hot water installation and valvemechanical construction,
4) other construction works.
4. The detailed scope of the subject of the contract is specified in the design documentation and technical specification of execution and acceptance of the robot, bill of quantities and the arrangements resulting from the contract template.
5. In the event of a discrepancy between the bill of quantities and the design documentation, the Contractor is obliged to accept the data from the design documentation.
6. Youthe contractor is obliged to read the Terms of Reference and its attachments and to execute the order on the terms and conditions described in them.
7. Equipment and equivalent materials may be used wherever the subject of the order is described in the design documentation by means of trademarks, patents or origin, source or specific process that characterizes products or servicessupplied by the specific contractor.
8. All parameters, including technical and operational parameters as well as functional parameters of devices and materials used by the contractor during the performance of the contract must meet the requirements specified in the project documentation. Providing device types and manufacturers' names should be treated as examples.
Contractors are excluded from the contract award procedurein relation to which any of the circumstances referred to in art. 24. paragraph 1 point 12-23 of the Public Procurement Law, in addition, when the circumstances referred to in art. 24. paragraph 5 point 1 Public Procurement Law, art. 24. paragraph 5 point 8 Public Procurement Law
1. The contractor submits in confirmation the above. circumstances:
a) information from the National Criminal Record in the scope specified in art. 24 paragraph 1 item 13, 14 and 21 of the Act of PPL
b) lights upvice by the competent head of the tax office confirming that the Contractor is not in arrears with tax payments, issued not earlier than 3 months before the deadline for submission of bids, or other document confirming that the Contractor has entered into an agreement with the competent tax authority regarding the repayment of these debts together with any interest or fines, in particular he obtained prlegal release, deferral or installment of overdue payments or suspension of the entire execution of the decision of the competent authority
c) certificate of the competent organizational unit of the Social Insurance Institution or Agricultural Social Insurance Fund or other document confirming that the Contractor is not in arrears with payment of social security contributions lub health insurance, issued not earlier than 3 months before the deadline for submission of bids, or other document confirming that the Contractor has entered into an agreement with the competent authority regarding the repayment of these receivables together with any interest or fines, in particular, he obtained the exemption, postponement or distribution provided for by law installments of late payments or withholding in full incarrying out the decision of the competent authority
d) an excerpt from the relevant register or from the central register and information on economic activity, if separate provisions require an entry in the register or the register, in order to confirm the absence of grounds for exclusion pursuant to art. 24 paragraph 5 item 1 of the Public Procurement Law
e) the contractor's statement that he has not issued a final court judgment or final admiadministrative settlement of arrears with the payment of taxes, fees or social security or health insurance contributions, or - in the event of such a judgment or decision - documents confirming the payment of such receivables together with any interest or fines or the conclusion of a binding agreement on the repayment of these receivables
f) a statement the contractor about the lack of a judgment against himby preventive measure prohibition of applying for public procurement
g) declaration of the contractor about not being in default of payment of local taxes and fees, referred to in the Act of 12.1.1991 on local taxes and fees (Journal of Laws of 2018 item .1445 with later changes)
h) statement on belonging or not belonging to the same capital group as referred to in Article 24 para. 1 point 23 of the PPL, within 3 days from the date of posting on the website information from the opening of offers
2. Contractor, which relies on the ability or situation of other entities on the principles set out in art. 22a of the Public Procurement Law, is obliged to submit in relation to these entities the documents listed above in point a) to g)
3. If the Contractor has its registered office / place of residence outside the territory of the Republic of Polandj Polish, instead of the documents listed in point a) to d) submits other equivalent documents detailed in chapter 5 paragraph 2 point 2 of the ToR
4. If in the country where the contractor has its registered office / place of residence / place of residence there is a person to whom the document relates, no documents referred to above in point a) to d), are replaced by a document containing appropriate statementse contractor, indicating the person or persons authorized to represent him / statement of the person to whom the document was to be submitted, submitted before a notary public / before the judicial, administrative or professional / economic self-government body competent for the seat / place of residence of the contractor / place of residence of that person .
Contractor to confirm the following circumstances, about whichreferred to in art. 25 paragraph 1 point 1 of the Public Procurement Law, submits:
a) documents confirming that the Contractor is insured against civil liability in the scope of conducted activity related to the subject of the contract for the sum insured specified by the Employer in Chapter 4 paragraph 1 point 2) lit. a) ToR, i.e. at least PLN 300, 000.00. In the case of Contractors jointly applying for the order of documentsthese documents are submitted by at least one of the Contractors or they may submit one joint document confirming that all Contractors are insured against civil liability in the scope of conducted activity related to the subject of the contract with a value not less than specified in Chapter 4 paragraph 1 point 2) lit. a) ToR. If, for a justified reason, the contractor cannot submit those required by the contractof the documents referred to above, the contracting authority allows the contractor to submit other documents referred to in art. 26 section 2c of the Public Procurement Law,
b) information from the bank or cooperative savings and credit union confirming the amount of financial resources possessed or the creditworthiness of the Contractor specified by the Employer in Chapter 4 para. 1 point 2) lit. b) SIWZ, i.e. at leastPLN 500, 000.00, not earlier than 1 month before the submission deadline. In the case of Contractors jointly applying for the contract, the Employer requires that a document confirming the amount of financial resources or creditworthiness submitted by at least one of the Contractors. If, for a justified reason, the contractor cannot submit the requirements required byfrom the contracting authority the documents referred to above, the contracting authority allows the contractor to submit other documents referred to in art. 26 section 2c of the Public Procurement Law
If the documents referred to above in point a), b) will indicate values in a currency other than PLN, the Contractor should make a conversion into PLN according to the average exchange rate of the National Bank of Poland on the day on which the contract notice was publishedin the Official Journal of the European Union (OJ EU). In the case where in the documents referred to above in point a), b) values in a currency other than PLN will be indicated by the Contractor, these values will be converted into PLN according to the average exchange rate of the National Bank of Poland on the day on which the contract notice was published in the Journal of Laws The EU. If on the day of publication of the contract notice in the OJ The EU will not publisha mated NBP exchange rate table will be adopted for conversion into PLN the exchange rate from the last published NBP exchange rate table before the date of publication of the contract notice in the Official Journal The EU.
1. The Contractor submits the offer via the Form to submit, change, withdraw the offer or application available on ePUAP. The public key necessary for the Contractor to encrypt the offer is available to the contractorsow on the miniPortal or in Annex 9 to the ToR.
2. The method of submitting an offer, including encrypting the offer, is described in the Instructions for use of the miniPortal and ePUAP systems (Annex 11 to the ToR). The offer should be submitted in the original.
3. Contractors who jointly apply for the contract (e.g. consortium, civil partnership) submit documents specified in detail in chapter 5 SIWZ.
4. Youthe contractor may rely on the technical or professional capacity or financial or economic situation of other entities to confirm compliance with the conditions for participation in the procedure, where appropriate and in relation to a specific contract, or part thereof, irrespective of the legal nature of the legal relations with it. In such a situation, the contractor must prove the Purchaserthat, by carrying out the contract, it will have the necessary resources of these entities, in particular, presenting the undertaking of those entities to make available to it the necessary resources for the purposes of the contract. An example of a third party liability template is Annex 8 to the ToR.
5. Contractor entered in the official list of approved contractors or certification contractorcertified by certification bodies meeting the requirements of European certification standards may submit a certificate of entry into the official list issued by the competent authority or certificate issued by the competent certification body of the country in which the contractor has its registered office or place of residence, indicating the documents constituting the basis for entry or obtaining certification, in place of the right onesdocuments listed in Chapter 5 para. 1 and 2 of the ToR.
6. The Contractor entering the tender should submit a bid security of PLN 40, 000.00 (say: forty thousand zlotys) in accordance with the conditions set out in Chapter 11 of the SETC.
7. The awarding entity does not provide:
1) Award of contracts referred to in art. 67, paragraph 1, items 6 and 7 of the Public Procurement Law,
2) Submission of partial and variant offers,
3) Zawarcand a framework agreement,
4) Establishment of a dynamic purchasing system,
5) Selection of the most advantageous offer using electronic auction,
6) Settlements in a currency other than the Polish zloty.
8. The specification of the Essential Terms of the Order together with attachments is available on the website: http://www.knurow.pl//miasto/zamycji_publiczne.html.
9. Employer: Municipal Housing Management Teamand Administration, ul. Floriana 4, 44-190 Knurow, POLAND. The Awarding Entity's website: http: //www.mzglia.pl.
10. The procedure for granting this order is conducted by the Employer's Representative - the Commune of Knurow, ul. dr. Floriana Ogana 5, 44-190 Knurow, POLAND (e-mail:
[email protected], URL: www.knurow.pl), acting on the basis of a power of attorney to perform specific activitiesand in the procedure for awarding the contract on behalf of and for the benefit of the Employer, granted on the basis of art. 15 paragraph 2 of the Public Procurement Law
11. The procedure for the award of this contract is part of a contract with an estimated value above the equivalent of EUR 5, 548, 000. Thermomodernization of historic buildings of Old Knur-w with elimination of low emission sources.
Internet address (URL): www.knurow.pl