Object of the contractConstruction work
Description: Contract notice: Construction work
Authority Type: Other
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45000000, 45233140, 45233120, 45100000, 45231300, 45310000, 45112710, 45200000, 45231400, 45316110, 45232310, 45213311, 34922100, 45221111, 45000000, 45233140, 45233120, 45100000, 45231300, 45310000, 45112710, 45200000, 45231400, 45316110, 45232310, 45213311, 34922100, 45221111
CPV Description: Construction work.
Roadworks.
Road construction works.
Site preparation work.
Construction work for water and sewage pipelines.
Electrical installation work.
Landscaping work for green areas.
Works for complete or part construction and civil engineering work.
Construction work for electricity power lines.
Installation of road lighting equipment.
Construction work for telephone lines.
Bus station construction work.
Road markings.
Road bridge construction work.
Construction of the connection ul. I. Paderewski with ul. Wyzwolenia in Konin, in connection with the modernization of the E-20 railway line
Reference Number: ZDM.IV.ZP.221.17.2019
The subject of the order is the construction of a connection street ul. I. Paderewski with ul. Wyzwolenia in Konin, in connection with the modernization of the E-20 railway line, excluding the road viaduct at km 202, 860 E 20 railway line (implemented according to a separate task by PKP PLK SA).
Main Site: The City of Konin
The scope of the contract includes, among others: Construction of a new section of the street from the intersection of ul. Paderewskiego and Przemysłowa to the intersection of ul. Listopada i Zakole,
- expansion of ul. Paderewskiego, Wyzwolenia, Przemysłowa, 11 Listopada, Zakole,
- extension and construction of the crossroadsń,
- construction of additional roads,
- construction of sidewalks, bicycle paths, bus bays, exits, parking lanes,
- reconstruction and construction of drainage elements,
- reconstruction and construction of road lighting,
- construction of engineering facilities (flyover),
- construction of storm water drainage,
- construction of road lighting,
- construction of retaining walls,
- construction of stairs and ramps for pedestrians,
- will strengthensoil subgrade,
- reconstruction or protection of all collisions with foreign devices,
- construction of acoustic screens,
- construction of road safety devices,
- demolition of existing elements of road lane development: roadways, pavements, bus bays, road ditches,
- demolition of existing building structures: residential buildings, garages,
- felling and equipmentgreenery,
- reconstruction of the points of the geodetic matrix.
Details about the individual scope of the works are in the design documentation including:
- Construction design Annex 5
, Executive design Annex 6
- Bill of quantities Annex 7
- STWiORB Annex 8
The detailed terms and conditions for the implementation of the order are set out in the Model Contract constituting Annex 4 to the ToR.
The warranty for the subject of the contract should be at least 6 years from the date of signing the final acceptance protocol, excluding:
a) greenery (grass) - for which 12 months warranty from the date of signing the final acceptance protocol. After this period, the greenery will be picked up from the contractor and handed over to the user, and the robot will be released from further herb careni,
b) thin layer marking for which a 12-month warranty is set from the date of signing the final acceptance protocol.
c) thick layer marking for which a 36-month warranty is set from the day of signing the final acceptance protocol.
Before the abovementioned periods are completed warranty acceptance in accordance with the provisions of the model contract. Requiredthe warranty period for defects in the subject of the contract may not be shorter than the period of warranty granted.
Local vision: Due to the close connection of the subject of the contract with the emerging road viaduct over the E20 railway line at km 202.860 (implemented according to a separate study by PKP PLK SA), it is recommended the contractor made a site visit in the area where the work is to be carried out and obtained for his fatherresponsibility and risk, all relevant information necessary to prepare the offer.
COMMUNICATION BETWEEN THE CONTRACTING PARTY AND THE CONTRACTOR, in particular submitting statements, applications (other than submitting the offer, changing or withdrawing it), notifications and information is provided electronically via a dedicated form available on ePUAP (mailbox address: / ZDMKonin / SkrytkaESP) and made available by the miniPortal (Form for communication). In all correspondence related to this procedure, the Employer and Contractors use the advertisement number (advertisement number in TED). The Employer may also communicate with Contractors by e-mail - the email address
[email protected]. The Employer does not specify a detailed condition in this respecte.
LIST OF DOCUMENTS: 1. In order to initially confirm that the conditions for participation in the proceedings have been met and there are no grounds for exclusion specified by the Employer in Sections III and IV of the ToR, the Employer requests submission, together with the offer, of the current declarations referred to in the offer in art. 25a section 1 point 1 of the PZP Act, on the form of the Single European Order Document (EAT)in electronic version (Annex 2 to the ToR, the Awarding Entity also allows for the completion of EAT via the ESPD tool) ..
2. In order to confirm compliance with the conditions for participation specified by the Employer in Chapter III of the ToR, the contractor whose bid will be rated the highest at the request of the Employer referred to in Article 26 (1) of the PZP Act, shall submit validday of submitting the statement or documents, i.e.: list of construction works - referred to in Chapter III para. 1 point 1.3.1 of the ToR made not earlier than in the last seven years before the deadline for submission of tenders, and if the period of business activity is shorter - in this period together with the type, value, date, place of performance and entities for whom these robots withwere made, with evidence from paragraph 2.2 below (specifying whether these construction works have been carried out properly, in particular information on whether the works have been carried out in accordance with construction law and correctly completed). 2.2. Evidence confirming that the construction works listed in paragraph 2.1 have been duly completed, i.e. references or other documents issuedthat by the entity for whose works the works were carried out and if for a justified reason of an objective nature the contractor is not able to obtain these documents - other documents 2.3 list of persons - referred to in Chapter. III item 1 point 1.3.2 of the Terms of Reference directed by the Contractor to carry out the contract, responsible for managing construction works together with information about theirprofessional qualifications, authorizations, experience and education necessary to perform the public contract, as well as the scope of their activities, and information on the basis of their disposal. 2.4 Information from a bank or cooperative savings and credit union regarding the condition of participation in the procedure specified in Chapter III item 1.2 ToR confirming the heightof financial resources or creditworthiness of the Contractor for an amount of at least PLN 9, 000, 000.00 within a period not earlier than 1 month before the deadline for submission of tenders. referred to in art. 86 section 5 of the PZP Act, will provide the Employer with a declaration of belonging orlack of belonging to the same capital group - according to the template constituting Annex 3 to the ToR. for this amount.
LIST OF STATEMENTS AND CD DOCUMENTS: 3. To confirm the absence of grounds for exclusion specified by the Employero in Chapter IV of the Terms of Reference, the contractor whose bid will be rated the highest on the call of the Employer, referred to in Article 26 para. 1 of the Public Procurement Law Act within 10 days, submits valid as at the day of submitting the statement or documents, ie: 3.1 information from the National Criminal Register in the scope specified in art. 24 paragraph 1 item 13, 14 and 21 of the PZP Act issued not earlier than 6 months beforethe deadline for submitting bids; 3.2. An excerpt from the relevant register or from the central register and information on economic activity, if separate provisions require an entry in the register or the register, in order to confirm the absence of grounds for exclusion pursuant to art. 24 paragraph 5 point 1 of the PPL Act; 3.3 the contractor's statement that he has not issued a final judgment or final administrative decision to himon arrears with payment of taxes, fees or social security or health insurance contributions or in the event of such a judgment or decision - documents confirming the payment of such receivables together with any interest or fines or the conclusion of a binding agreement on the repayment of these receivables; 3.4 the contractor's statement that the title has not been awarded to himpreventive measure prohibiting from applying for a public contract.
4. In the case of a joint bid, documents and statements referred to in Chapter V in the paragraph 3 points 3.1.- 3.4 and par. 9 SIWZ must be submitted (separately) by all contractors jointly applying for the award of the order 5. If the Contractor demonstrating compliance with the conditions referred to in Chapter III item 1 SETC, consists of resourcesh other entities on the principles set out in art. 22a of the PZP Act, the Employer requests the Contractor to present in relation to these entities the documents listed in Chapter V paragraph 3 pts. 3.1.a-3.4. SIWZ.
6.If the Contractor has its registered office or place of residence outside the territory of the Republic of Poland, instead of the documents referred to in: 6.1 Chapter. V paragraph 3 points 3.1 SIWZ submits information with responsesthe relevant register or, in the absence of such a register, another equivalent document issued by the competent judicial or administrative authority of the country in which the contractor has its registered office or place of residence or place of residence, has the person to whom the information or document relates, to the extent specified in art. 24 paragraph 1 item 13, 14 and 21 of the Act - issued not earlier than 6 months before the expiry ofthe time for submitting bids; 6.2 Chap. V paragraph 3 point 3.2 of the Terms of Reference submits a document or documents issued in the country in which the contractor has its registered office or place of residence, confirming accordingly that: its liquidation has not been opened or bankruptcy has been declared - issued not earlier than 6 months before the deadline for submission of tenders. 7.If in the country in which the contractor has its registered office or place of residenceand the place of residence is the person to whom the document relates, the documents referred to in Chapter V paragraph 6, shall be replaced by a document containing a statement of the contractor, indicating the person or persons authorized to represent him, or a statement of the person to whom the document was to relate, submitted before a notary public or before a judicial, administrative or administrative bodyprofessional or economic self-government competent for the registered office or place of residence of the contractor or place of residence of that person. The document should be issued not earlier than 6 months before the deadline for submission of tenders. (...) cont. section III.2.2
1) cd. Technical capacity and professional qualifications: applicable provisions - to the extent sufficient to manage works inas above and having at least 5 years of experience in managing construction works of the abovementioned specialties;
e) Telecommunications industry robot manager - at least 1 person with building qualifications to manage works in the installation specialty in the field of telecommunications networks, installations and equipment, or the corresponding valid building qualifications that have been issuedon the basis of previously binding provisions - to the extent sufficient to manage works in the area mentioned above. and having at least 5 years of experience in managing construction works of the abovementioned specialties;
f) Construction works manager - at least 1 person with building qualifications to manage works in the construction and building specialization orthey have valid construction licenses issued to them on the basis of previously binding provisions - to the extent sufficient to manage works in the area mentioned above. and having at least 5 years of experience in managing construction works of the abovementioned specialties.
The Employer requires a separate person for each specialty also if one person has the qualificationsenia in two or more specialties.
2) The procedure is conducted in an open tender.
2.4. Contractors may jointly apply for the contract, on the terms set out in art. 23 of the PZP Act. In the case of Contractors jointly applying for the award of this contract to confirm compliance with the conditions described in paragraph 1 of the IES, the Employer will assess the linknot their economic or financial capacity, and technical or professional capacity in the field of persons.
3) Contractor pursuant to art. 22a of the Public Procurement Law may, in order to confirm compliance with the conditions for participation in the proceedings, in appropriate situations and in relation to a specific contract, or part thereof, rely on technical or professional capabilities or the financial or economic situation of otherh entities, regardless of the legal nature of the legal relations with it. For this purpose, the contractor, together with the offer, presents to the Ordering Party the original commitment of these entities to provide him with the necessary resources at the disposal of the contract (in the form of an electronic document signed by another entity by a qualified electronic signature or in an electronic copyand a statement certified as true to the original by another entity by a qualified electronic signature.)
4) The Awarding Entity will exclude from participation in the proceedings a contractor who is subject to at least one of the conditions specified in art. 24 paragraph 1 point 12-23 of the PPL Act. The contracting authority will also exclude a contractor who is subject to the exclusion conditions specified in art. 24 paragraph 5 points 1 and 4of the Public Procurement Law - LIST OF STATEMENTS AND DOCUMENTS TO CONFIRM THE LACK OF GROUNDS FOR EXCLUSION - SECTION III.1.2
Processing of personal data: Chapter I para. 19 of the SETC.
Employer pursuant to art. 29 paragraph 3a of the PZP Act, requires employment by a contractor or subcontractor on the basis of an employment contract, persons performing activities in the field of the contract, the performance of which consists of performingwork in the manner specified in art. 22 - 1 of the Act of June 26, 1974 - Labor Code (j. Journal of Laws of 2019, item 1040, as amended) - in accordance with Chapter I para. 11 of SIWZ.
Internet address (URL): www.zdm-konin.pl