Procurement Summary
Country: Aland Islands
Summary: Construction of steel frame roof structure at the treatment plant for the dennery north water supply project (phase 1) in dennery, saint lucia - copy
Deadline: 29 Jan 2018
Posting Date: 20 Feb 2018
Other Information
Notice Type: Tender
TOT Ref.No.: 20069682
Document Ref. No.: RFQ/2018/2985
Competition: ICB
Financier: United Nations Secretariat
Purchaser Ownership: -
Tender Value: Refer Document
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_details
Login to see detailsTender Details
Construction of Steel Frame Roof Structure at the Treatment Plant for the Dennery North Water Supply Project (Phase 1) in Dennery, Saint Lucia - copy
Deadline: 29-Jan-2018 16:00
Time zone: (GMT 0.00) Western Europe Time, London, Lisbon, Casablanca
Description:
The Government of Saint Lucia through the United Nations Office for Project Services (UNOPS) received a USD 5 million grant from the Government of Mexico to undertake a water supply project in Dennery.
UNOPS, functioning as the project management entity in accordance with the signed agreement with the Government of Saint Lucia, is managing the implementation of the project, while the Water and Sewerage Company (WASCO) will facilitate the work of the representatives of UNOPS through follow-up, review and monitoring of project activities.
The beneficiary of the project is the Ministry of Agriculture, Fisheries, Physical Planning, Natural Resources and Co-operatives, and the Government of Saint Lucia and subsequently and most importantly the citizens of Dennery.
The sustainable operation of the system is key to ensure an enhanced level of service to the populations. Experience has proven that benefits are only achieved when hardware installation is fully integrated with properly planned and implemented arrangements for the long-term operation, maintenance and financing of an improved service.
The community of Dennery North deserves a system that is not only fully functional but is also resilient to the unique climatic conditions of the Caribbean region. For this reason, UNOPS wishes to incorporate sustainability by implementing structures that improve the efficiency of the water treatment process as well as creating a safe and comfortable working environment for the end-users.
-----
IMPORTANT NOTE: Interested vendors must respond to this tender using the UNOPS eSourcing system, via the UNGM portal. In order to access the full UNOPS tender details, request clarifications on the tender, and submit a vendor response to a tender using the system, vendors need to be registered as a UNOPS vendor at the UNGM portal and be logged into UNGM. For guidance on how to register on UNGM and submit responses to UNOPS tenders in the UNOPS eSourcing system, please refer to the user guide and other resources available at: https://esourcing.unops.org/#/Help/Guides
UNSPSC:
D - Construction, Transportation & Facility Equipment & Supplies
22000000 - Building and Construction Machinery and Accessories
There have been no revisions to this notice.
26-Jan-2018 22:52 : [email protected] - New amendment added #1: This amendment is the incl...
Change/edit date
26-Jan-2018 22:52
Change/edit email
[email protected]
Change/edit details
New amendment added #1: This amendment is the inclusion of Annex 1 in the list of documents in support of CLARIFICATION NOTE No. 3 as follows:Description of Site Condition and Site Plans
26-Jan-2018 22:40 : [email protected] - New clarification added: Question No. 2“Please cla...
Change/edit date
26-Jan-2018 22:40
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 2“Please clarify if you require the anchors to be chemical with stainless steel threaded rod or new mild steel anchor bolts cast with rework to the concrete footings.Answer No. 2:Anchor bolts and nuts are provided by the Client and will have already been installed at the six (6) anchor point on the existing reinforced concrete raft. The bidder is to include for the specified baseplate and associated works to erect the structural frame. Refer to ANNEX 1, Images 4-5 for anchoring components.
26-Jan-2018 22:39 : [email protected] - New clarification added: The following clarificati...
Change/edit date
26-Jan-2018 22:39
Change/edit email
[email protected]
Change/edit details
New clarification added: The following clarifications are relevant to the process mentioned in reference and should be considered in the preparation of your proposals:Question No. 1:“Can you provide or upload a site layout or pictures of what exist? Our concern is access to and from the site as well as man lift/craneage requirements.”Answer No. 1:The site is located along the Castries Vieux Fort Highway and can be accessed via a concrete residential collector which connect to the aforementioned highway.See Clarification 3 - ANNEX 1 – Site Conditions and Site Plans
25-Jan-2018 21:54 : [email protected] - New clarification added: Question No. 8 “Please co...
Change/edit date
25-Jan-2018 21:54
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 8 “Please confirm the building code and wind-speed to be used for the project”Answer No. 8:For information, the wind-speed and building code used for the design of the structure were:· IBC- 2009, ASCE 7-05· Basic wind speed 130mph· Region – Hurricane Prone· Exposure Cat- C
25-Jan-2018 21:53 : [email protected] - New clarification added: Question No. 7“Are we all...
Change/edit date
25-Jan-2018 21:53
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 7“Are we allowed to submit an alternative building to the one shown - or do we have to fabricate what is shown on the plan? “Answer No. 7:No alternative bids are allowed.
25-Jan-2018 21:53 : [email protected] - New clarification added: Question No. 6“When is th...
Change/edit date
25-Jan-2018 21:53
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 6“When is the due date?”Answer No. 6:All offers must be submitted by 5:00 p.m. Saint Lucia Time on 24th January 2018. The works should be completed 21 days after contract award.
25-Jan-2018 21:50 : [email protected] - New clarification added: Question No. 5“Is the str...
Change/edit date
25-Jan-2018 21:50
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 5“Is the structure constructed already or in progress? “Answer No. 5:Only the reinforced concrete floor slab for the structure is completed. Note that a fully operating water treatment plant is atop this slab.
25-Jan-2018 21:50 : [email protected] - New clarification added: Question No. 4“Is the Cl...
Change/edit date
25-Jan-2018 21:50
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 4“Is the Client providing scaffold/ access?”Answer No. 4:No. Bidder to include scaffold in their quotation.
25-Jan-2018 21:49 : [email protected] - New clarification added: Question No. 2“What type ...
Change/edit date
25-Jan-2018 21:49
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 2“What type of roof sheets? Gauge and color?”Answer No. 2:To be specified by supplier
25-Jan-2018 21:47 : [email protected] - New clarification added: Question No. 1:Is the quo...
Change/edit date
25-Jan-2018 21:47
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 1:Is the quote only for the roof covering?Answer No. 1:The quotation should be for the superstructure- the slab currently exists so all components above slab should be included, inclusive of the roof covering and steel frame.
25-Jan-2018 21:03 : [email protected] - New clarification added: Question No. 2“Will the U...
Change/edit date
25-Jan-2018 21:03
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 2“Will the UNOPS allow for sub contract installation service from our sub-contractor in St. Lucia?"Answer No. 2:Yes. UNOPS allows for sub-contracting. However, be reminded that Clause 3.4 of UNOPS’ Minor Works Contract applies:“In the event the Contractor requires the services of subcontractors, the Contractor must obtain the prior written approval of the Employer’s Representative for all such subcontractors. The approval of the Employer’s Representative does not relieve the Contractor of any of its obligations under this Contract, and the terms of any sub-contract must be subject to and in conformity with the provisions of this Contract.”
25-Jan-2018 21:03 : [email protected] - New clarification added: Question No. 1:“[…] the t...
Change/edit date
25-Jan-2018 21:03
Change/edit email
[email protected]
Change/edit details
New clarification added: Question No. 1:“[…] the tender contains a statement under section III, Deliverables: "The activities shall be carried out in Saint Lucia". Can you please clarify if this means that fabrication must be carried out in St. Lucia? Or does the tender allow for external fabrication?”Answer No. 1:The structure only needs to be erected in St. Lucia. At the sole discretion of the bidder, the structure can be pre-fabricated externally and then erected at the final location.
NOTE: Multiple Countries (Total: 23)
Type of notice :Request for quotation
More Details :D - Construction, Transportation & Facility Equipment & Supplies
22000000 - Building and Construction Machinery and Accessories
Documents
Tender Notice