Expired Tender Mongolia ICB TOT Ref. 43017994

Construction of an Advanced Water Purification Tender - 43017994

Tender notice from Mongolia, published on 30 May 2020.

Executive Summary

The MILLENNIUM CHALLENGE ACCOUNT has issued a Tender notice for the procurement of a Construction of an Advanced Water Purification Plant (AWPP) and SCADA in the Mongolia. This Tender notice was published on 30 May 2020 and is scheduled to close on 20 Aug 2020, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 43017994, while the tender notice number is and Register on the platform.

Key facts

Summary
Construction of an Advanced Water Purification Plant (AWPP) and SCADA
TOT Ref. No.
43017994
Document Ref. No.
Country
Mongolia
Notice type
Tender
Competition
ICB
Publication date
30 May 2020
Bid deadline
20 Aug 2020
EMD
Refer Document
Tender value
Refer Document
Purchaser ownership
-
Financier
Other Funding Agencies

CPV classification

Purchaser details

Purchaser contact is for registered users

Login to see details

Tender details

General Procurement Notice for Construction of an Advanced Water Purification Plant (AWPP) and SCADA.
Pre-Solicitation Notice
General Information
Country:
Mongolia
City/Locality:
Ulaanbaatar
Publication Date:
May 20, 2020
Agency:
Millennium Challenge Account (MCA)
Buyer:
Original Language:
English
Contact Information
Address:
Sarangoo Baatarkhuyag

Millennium Challenge Account-Mongolia

MPM Complex, 6th Floor

UNESCO Street, Bayanzurkh District

Ulaanbaatar 14210

Mongolia
Telephone:
+976-77111710
E-mail:
Click here
Goods, Works and Services
45245000 - Dredging and pumping works for water treatment plant installations

45200000 - Works for complete or part construction and civil engineering work

45240000 - Construction work for water projects

Original Text
MONGOLIA WATER COMPACT
PRE-SOLICITATION NOTICE
The United States of America, acting through the Millennium Challenge Corporation (“MCC”), and the Government of Mongolia (the “Government”) have entered into a Millennium Challenge Compact Agreement for Millennium Challenge Account assistance in the amount of 350 million USD to help facilitate poverty reduction through economic growth in Mongolia (the “Compact”). The Compact will assist the Government in alleviating an imminent water shortage and meeting the projected demand for water in the capital city of Ulaanbaatar for residential consumers and commercial and industrial users through three closely related investment activities:
• A Downstream Wells Activity, to construct new groundwater wells with attendant transmission lines, reservoirs, and an advanced water purification plant;

• A Wastewater Recycling Activity, to construct a new wastewater recycling plant and pipelines to provide high-quality treated wastewater that can substitute groundwater used by water-intensive industries, thereby releasing the amount of fresh water available for household consumption; and

• A Water Sector Sustainability Activity, to support policy reforms, capacity building, and provide technical assistance to improve the long-term sustainability of Ulaanbaatar city-s water supply.

Millennium Challenge Account-Mongolia (“MCA-Mongolia”), an Accountable Entity established to oversee the implementation of the Compact, intends to conduct pre-qualifications which will be followed by competitive biddings for the below contracts for works under the Compact-s Downstream Wells Activity:
• Construction of an Advanced Water Purification Plant (AWPP) and SCADA;

• Construction of Pipelines, Well houses, Pumping Station.
These works will require highly qualified contractors, and the procurements will begin with a rigorous pre-qualification for each of these two contract packages. The pre-qualification phase will incorporate elements from MCC-s Quality and Price Based Selection (QPBS) process. Each pre-qualification process will result in a shortlist of entities qualified to competitively bid on the corresponding works package. For the bidding phase for these two works packages, MCA-Mongolia intends to use invitations for bid based on the MCC Standard Bidding Documents (SBD) for procurement of large works. The form of contract used for each of these works packages will be the International Federation of Consulting Engineers (FIDIC) Redbook Construction Contract (1999). The pre-qualification process will be open to all bidders from eligible source countries, as defined in the MCC Program Procurement Guidelines (“PPG”).
Contracts for works financed under the Compact will be implemented according to the principles, rules, and procedures set out in the MCC PPG, which can be found on MCC-s website at https://www.mcc.gov/resources/doc/program-procurement-guidelines.
A Specific Procurement Notice (“SPN”) for each contract will be announced on MCA-Mongolia-s website at https://www.mca-mongolia.gov.mn/, the United Nations Development Business (UNDB Online) website at http://www.devbusiness.com/, the Development Gateway Market (dgMarket) website at http://mcc.dgmarket.com/, in Mongolian daily newspapers, and in other media outlets, as appropriate.
The purpose of this pre-solicitation notice is to:

A) Inform potential bidders that the complete set of Pre-Qualification Bidding Documents with the “Works Requirements” are expected to be posted on MCA-Mongolia-s web site (www.mca-mongolia.gov.mn) by mid-2020, and will be available for downloading free of charge. The documents that will be provided are from the current draft (typically 60%) designs for the AWPP and the wellfields and pipelines. As the design progresses towards 100% completion in parallel with the pre-qualification process, the “Works Requirements” are and will be subject to change until the final issue of the invitations for bids to shortlisted entities, which is expected in late-2020.
“Works Requirements” of the invitations to apply for pre-qualification, which will be issued in mid-2020 are expected to include, but not be limited to:
For the Construction of AWPP and SCADA:
Ø A written summary of works for the construction package;

Ø An overall site layout plan from the draft design set for the AWPP, showing the overall layout and major components of the AWPP;

Ø Grading plans for the AWPP from the draft design set showing the scale of civil works currently anticipated;

Ø Process flow diagrams from the draft design set showing the treatment process that is currently anticipated;

Ø A draft 3D rendering of the design of the AWPP, showing the vertical scale of the buildings currently envisaged for the AWPP;

Ø A summary of geotechnical conditions at the AWPP site; and

Ø A draft of the Contract Operation and Maintenance of the AWPP Specification Section 01950, outlining the requirements for an anticipated two year operation period for the AWPP by the Contractor.
For the Construction of Pipelines, Well houses, Pumping Station, and Fiber Optic Cable installation for SCADA:
Ø Wellfield layout plans from the draft design set for the wells and conveyance, showing a schematic overview of wellfield piping;

Ø A written summary of works for the construction package;

Ø An overview layout drawing from the draft design set for the wells and conveyance, showing planned construction at a typical well site;

Ø Typical pipeline cross section drawings from current design, showing typical pipeline cross sections which are currently envisaged;

Ø A summary of geotechnical conditions in the wellfields and along the pipeline alignment; and

Ø A summary of the draft Resettlement Action Plan (RAP) which the Contractor will be required to implement.
For Both Packages (in addition to specific items for each Package noted above):
Ø A proposed timeline for the procurement process with definition of expected dates for Award of Contract and Notice to Proceed, upon which proposals may be based;

Ø The vicinity and location map, showing the general location and relative locations of the components and the alignment of the pipelines;

Ø A summary of climate information for the Project area;

Ø A summary list of international codes and standards specified by the Government of Mongolia;

Ø A summary of key permitting and regulatory approvals required for the construction activites identifying generally which aspects will be the responsibility of the Contractor;

Ø A summary of the draft Employer-s Environmental and Social Management Plans (ESMPs) for each contract; and

Ø A summary of the Employer-s schedule constraints for the works and key parts of Specificaion 01310 Project Schedule from the draft design.
B) Provide potential bidders with Preliminary Information Package for Applicants, including the description of works. To download the information package, please register with the following link: https://bit.ly/2AMjIvh.
The Preliminary Information Package for Applicants includes the following documents:

1. Brief description of Compact activities and project;

2. A summary of the main technical elements of the work for the Bulk Water Supply Project including a summary of the status of Environmental and Resettlement Plans for the work, health, safety, and environment related rules and procedures;

3. A general responsibilities matrix that shows the scope envisaged for different stakeholders of the works packages;

4. Information available to support potential bidders, including information regarding construction licenses and regulations related to business establishment in Mongolia;

5. Information on taxation and payment; and

6. List of local construction firms that have expressed interest in teaming up for these works packages.
C) Invite potential bidders to start making preliminary arrangements for the pre-qualification applications preparation.
D) Invite potential bidders to monitor the MCA-Mongolia-s website for additional announcements and information regarding this procurement.
Interested eligible contractors who wish to be included in the mailing list to receive a copy of advertisements, or those requiring additional information, should contact the Procurement Agent for MCA-Mongolia at [email protected] with copy to [email protected].
Millennium Challenge Account-Mongolia

F5, MPM Complex, UNESCO Street, Khoroo #1,

Sukhbaatar District, Ulaanbaatar - 14220, Mongolia

Documents

Tender Notice
Login to view

Similar tenders

Mongolia Public Procurement Intelligence

Frequently asked questions

The bid deadline for Construction of an Advanced Water Purification Plant (AWPP) and SCADA was 20 Aug 2020. Bidding is closed.

This tender has been issued by MILLENNIUM CHALLENGE ACCOUNT in Mongolia.

The tender value is not disclosed; please refer to the tender document. EMD / bid security details are provided in the tender document.

This tender is financed by Other Funding Agencies.

The tender is classified under the following CPV code(s): 45252120 - Water-treatment plant construction work.

The tender notice and related documents are listed in the Documents section above. Select a document to view or download it. Please log in or register to access the documents. If you cannot find additional documents in the Documents section, please log in to your account and Send Document Request from your account section.

The TendersOnTime reference is 43017994. The purchaser document reference is not provided in the notice.

See the Similar Tenders section on this page or browse other tenders from Mongolia.

This tender falls under Construction and Real Estate in Mongolia. Suppliers in these sectors can track similar Mongolia tenders using CPV-based alerts.