Funds are not presently available for this contract. As such this contract action is being advertised pursuant to the far clause 52.232-18 availability of funds (apr 1984). The national institutes of health (nih) through this contract action intends to renovate as necessary to accommodate a consolidated computational research facility (ccrf) in bldg. 31. An integral part of the renovations required includes renovations/modifications to the chiller plant in bldg. 28 at the rocky mountain laboratories (rml) hamilton, montana. The magnitude of this construction project is estimated between $5, 000, 000.00 and $10, 000, 000.00. The project consists of the following:
1. Consolidated computational research facility(ccrf) building #31:
the scope of the work includes but is not limited to repurposing approximately 5, 301 sf of building 31 into a new ccr facility. The first floor demolition comprises of approximately 2, 623 sf of offices and storage space. The basement demolition comprises of approximately 2, 678 sf of storage space. Mechani-cal systems work includes construction of a new bi-directional fault-tolerant chilled water distribution sys-tem teamed with in-row type chilled water cooling units situated on the raised data floor. New heat ex-changers, redundant chilled water pumps, chilled water storage tanks and controls, along with a local low ambient emergency air cooled chiller will be installed to support the data center cooling needs. Electrical work includes new electrical service to building 31 and redundant electrical distribution system for new consolidated computational research facility. Systems to include new interior and exterior distribution gear, automatic transfer switches, un-interruptible power supplies, transformers, power transformers, and remote power supplies. Special systems include fire alarm systems, access control, video surveillance, and paging system.
2. Chiller plant modifications building #28:
the scope of the work includes but is not limited to replacement of a 700 ton capacity water cooled steam absorption chiller with a nominal 800 ton centrifugal chiller, replacement of a 170 ton outdoor air cooled chiller with a nominal 250 ton air cooled chiller with variable speed drive and low ambient operation fea-tures, and the addition of an outdoor dry cooler to provide free cooling capability during winter months. The improvements will allow the building 28 chiller plant to produce chilled water all months of the year to support the continuous cooling loads posed by the ccr in building 31. The additions and improvements will also improve plant redundancy and provide better ride-through during failures of major equipment. Electrical work to include new breakers and feeders to provide power to new equipment.
The complete solicitation will be posted at the federal business opportunities web site on 15 march 2016.
903 s. 4th street
hamilton, montana 59840
united states
primary point of contact.:
james s parr,
contracting officer
[email protected]phone: 406-363-9207
fax: 406-363-9340 general information
z -- maintenance, repair, and alteration of real property
naics code:
236 -- construction of buildings/236220 -- commercial and institutional building construction
236 -- construction of buildings/236220 -- commercial and institutional building construction
for help: federal service deskaccessibility
added: feb 29, 2016 4:47 pm