1 |
SCS F NW S 700 C DCS MAIN SUPPLY complete with all accessories including E andC Spares for 2X660 MW DVC RAGHUNATHPUR TPP PH II STG |
SCS F-NW S-700 C-DCS - MAIN SUPPLY complete with all accessories including EandC Spares- Refer Technical Specification and detailed BOQ for break up and details |
4 |
NOS |
380 |
|
2 |
MANDATORY SPARES for 2X660 MW DVC RAGHUNATHPUR TPP PH II STG |
MANDATORY SPARES- Refer Technical Specification and detailed BOQ for break up and details |
1 |
LOT |
380 |
|
3 |
Installation checks and Commissioningfor SCS F NW S 700 C DCS Lump sum visit charges for engineer including travel -except daily charges- for 2X660 MW DVC RAGHUNATHPUR TPP PH II STG |
Installation checks and Commissioning for SCS F-NW S-700 C-DCS - Lump sum visit charges for engineer including travel -except daily charges- Refer Technical Specification and detailed BOQ for break up and details |
4 |
VISIT |
975 |
|
4 |
Installation checks and Commissioning for SCS Lump Sum daily charges for engineer including boarding, lodging, local conveyance, medical, insurance etc for 2x660 MW DVC RAGHUNATHPUR TPP PH II STG |
Installation checks Commissioning for SCS F-NW S-700 C-DCS - Lump Sum daily charges for engineer including boarding or lodging, local conveyance, medical, insurance etc -Refer Technical Specification and detailed BOQ for break up and details |
16 |
DAYS |
975 |
|
5 |
SCS FNW S600 CDCS MAIN SUPPLY complete with all accessories including E and C Spares for 2X660 MW DVC RAGHUNATHPUR TPP PH II SG |
SCS F-NW S-600 C-DCS - MAIN SUPPLY complete with all accessories including EandC Spares - Refer Technical Specification and detailed BOQ for break up and details |
2 |
NOS |
380 |
|
6 |
MANDATORY SPARES for 2X660 MW DVC RAGHUNATHPUR TPP PH II SG |
MANDATORY SPARES -Refer Technical Specification and detailed BOQ for break up and details |
1 |
LOT |
380 |
|
7 |
Installation checks and Commissioningfor SCS FNW S 600 C DCS Lump sum visit charges for engineer including travel except daily charges for 2X660 MW DVC RAGHUNATHPUR TPP PH II SG |
Installation checks and Commissioning-for SCS F-NW S-600 C-DCS - Lump sum visit charges for engineer including travel -except daily charges-Refer Technical Specification and detailed BOQ for break up and details |
2 |
VISIT |
975 |
|
8 |
Installation checks and Commissioningfor SCS Lump Sum daily charges for engineer including boarding, lodging, local conveyance, medical, insurance etc for 2x660 MW DVC RAGHUNATHPUR TPP PH II SG |
Installation checks and Commissioning-for SCS F-NW S-600 C-DCS - Lump Sum daily charges for engineer including boarding or lodging, local conveyance, medical, insurance etc- Refer Technical Specification and detailed BOQ for break up and details |
8 |
DAYS |
975 |
|
9 |
SCS FNW S 900 C DCS MAIN SUPPLY complete with all accessories including E and C Spares for 2X660 MW MAHAGENCO KORADI TPP UNIT 11 and 12 |
SCS F-NW S-900 C-DCS - MAIN SUPPLY complete with all accessories including EandC Spares - Refer Technical Specification and detailed BOQ for break up and details |
4 |
NOS |
380 |
|
10 |
MANDATORY SPARES for 2X660 MW MAHAGENCO KORADI TPP UNIT 11, 12 |
MANDATORY SPARES -Refer Technical Specification and detailed BOQ for break up and details |
1 |
LOT |
380 |
|
11 |
Installation checks and Commissioningfor SCS FNW S 900 C DCS Lump sum visit charges for engineer including travel except daily charges for 2X660 MW MAHAGENCO KORADI TPP UNIT 11, 12 |
Installation checks and Commissioning for SCS F-NW S-900 C-DCS - Lump sum visit charges for engineer including travel -except daily charges- Refer Technical Specification and detailed BOQ for break up and details |
4 |
VISIT |
975 |
|
12 |
Installation checks and Commissioning for SCS Lump Sum daily charges for engineer including boarding, lodging, local conveyance, medical, insurance etc for 2x660 MW MAHAGENCO KORADI TPP UNIT 11, 12 |
Installation checks and Commissioning for SCS F-NW S-900 C-DCS - Lump Sum daily charges for engineer including boarding or lodging, local conveyance, medical, insurance etc - Refer Technical Specification and detailed BOQ for break up and details |
16 |
DAYS |
975 |