Procurement Summary
Country : Germany
Summary : Engineering Services Planning and Construction Supervision - Remediation of Contaminated Sites - Power Plant Site East, Section of the Coal Belt Bridge in the Area of The Former Coal Mining Plant -...
Deadline : 16 Apr 2024
Other Information
Notice Type : Tender
TOT Ref.No.: 98548749
Document Ref. No. : 146593-2024
Competition : ICB
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : EUR 360000.00
Purchaser's Detail
Purchaser : AWARDING OFFICE IN THE STATE CAPITAL OF STUTTGART
Address: Construction Contracting Service Center
Town: Stuttgart
NUTS Code: DE111
Postal Code: 70178
Attn: Construction Contracting Service Center
Phone: 000
Germany
Email :65-8dlzbau@stuttgart.de
Tender Details
Engineering Services Planning and Construction Supervision - Remediation of Contaminated Sites - Power Plant Site East, Section of the Coal Belt Bridge in the Area of The Former Coal Mining Plant - Stuttgart-East
As part of the VgV process, a planner for services for the remediation of contaminated sites through soil replacement with hydraulic securing of the old deposit on the east power plant site, the coal belt bridge section in the area of the former coal mining plant in Stuttgart-East is to be identified and commissioned in stagest.
On the site of the EnBW power plant in Stuttgart-East lies the old deposit "power plant site east, partial area of coal belt bridge, area of former coal mining plant" (ISAS no. 523_2).
The existing soil and groundwater contamination was caused by previous filling of gravel pits withcaused by gasworks residues. Due to its location in the core zone of the mineral spring protection area, there is a need for action for renovation.
In recent years, a large part of the contamination has already been removed. Now there is to be a previously inaccessible residual damage with an area of around 600 m2be renovated. The renovation plan provides for preliminary excavation above the groundwater pressure level and deep excavation in saturated ground with shoring elements using the slide rail method. During the measure, around 8, 200 tons of soil material are expected to be collected for disposal.
Declaration informationThe correct parameters are PAH, nuclear power plants and MKW.
During the deep excavation, dewatering must be carried out in the shoring elements.
In addition, the pollutants mobilized in the subsoil must be secured by a hydraulic measure at two groundwater measuring points.
As the entrances and exits...
Document Type: Contract Notice
Reference Number: VgV_Kohlebandbruecke_Altlasten
Contract Type: services
Estimated Value: 360000.00 - EUR
Authority Type: body-pl-la
Doc Title: Engineering services planning and construction supervision - contaminated site remediation - power plant site east, part of the coal band bridge in Berie the former coal mining plant - Stuttgart-Ost
Dispatch Date: 2024-03-07
Publish Date: 2024-03-11
Submission Date: 2024-04-16
Documents
Tender Notice