Country : Germany
Summary : Contract notice: Engineering services
Deadline : 21 Jun 2018
Other Information
Notice Type : Tender
TOT Ref.No.: 23465821
Document Ref. No. : 216408-2018
Financier : Self Financed
Purchaser Ownership : -
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Object of the contract
Engineering services
Description: Contract notice: Engineering services
Authority Type: Regional or local authority
Contact Nature: Services
Procedure: Competitive procedure with negotiation
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 71300000, 71300000
CPV Description: Engineering services.
Specialist planning services of the HLS technology in the course of the renovation of the class tract "Neubau 1974" at the Johann-Heinrich-Alsted-Schule, Mittenaar
Reference Number: 2268/2018/2
Specialist planning for HLS technique according to Part 4, Section 2, HOAI in the course of the renovation of the class tract "Neubau 1974" at the Johann Heinrich Alsted School, Mittenaar.
Main Site: Schulstrasse 13
The Johann-Heinrich-Alsted-Schule in 35756 Mittenaar is a primary, junior and junior high school with a foerder level, which is currently attended by approx. 565 students. The school was founded in 1965 at its current location. The building to be renovated bears the name "Neubau 1974" and was expanded twice in the following years after 1974. The following rooms are currently in the buildingde: work rooms, computer rooms, recreation hall, toilets, natural sciences (physics, chemistry, biology), music, art, general classrooms SEK I as well as the complete elementary school, including mentoring.
The gross floor area is approximately 3 685 m and divides up in basement, ground floor and 1st floor up. It is a reinforced concrete skeleton construction with partial useof finished parts. The cubic structure originally had a flat roof, which was raised by a sloping saddle roof made of fiber cement corrugated sheets about 20 years ago.
In parts of the building, the existing partition walls are not led to the raw ceiling, they end at the height of the ceiling panels. The escape and rescue route situation is mangelhaft. It lacks partially the 2nd structural escape and rescue route. A fire protection concept should be created in the course of the action planning and the implementation should be based on. The existing building technology, especially the ventilation system is over-aged and needs renovation. The windows and Au-enwaende do not meet today's energy standard, the renovation is gem. valid EnEV umzIn the course of the pending fundamental restructuring, a conversion should also take place. The elementary school is to be moved from the 1st floor to the ground floor, the natural sciences to be renovated are planned for the future on the first floor. It is planned to install a stairwell including a lift to ensure accessibility.
During the refurbishment workThe building must be completely or partially cleared. Therefore, substitute classrooms, z. B. in the form of containers required. The actual planning services of object planning are issued as a step order. It is intended to commission first the performance phase 1 to 4 (until completion of the approval planning)the follow-up building sections is provided. Following the granting of the building permit, the continuation of the project in construction and service sections is intended; the continuation is subject to the regulations of the funding authorities of the KIP-II program of the state of Hesse.
The required explanations and proofs are under obligatory use of the application form (see also VI .3).The declarations are, where required, legally binding to sign. All evidence and explanations are to be written in German. The supporting documents and their respective documents must be clearly identified and submitted in the order indicated in the instructions for processing the application form. Submitted application documents will not be acceptedrueckgesandt. The following proofs must be submitted under mandatory application of the enclosed forms:
a) Details of the company with proof of the authorization of the engineer responsible for the project to manage the professional title of engineer (from the provider of the technical design HLS-Technik).
B) Declaration on - 73 Paragraph 3 VgV (Independence of Execution and LAnnex 1
c) Declaration on - 6 (2) VgV (Economic Associations) Appendix 2a
d) Declaration on 43 Paragraph 3 VgV (Authorization of a representative of the grouping and joint and several liability in case of order) Annex 2b
e) Declaration to Section 123 (1) GWB (declaration that the company has no exclusion criteria pursuant to points 1, 2, 3, 4, 5, 6, 7, -8, 9 and 10 of - 123 Abs. 1 GWB) Appendix 3
f) Declaration, to - 124 Abs. 1 GWB (Declaration that for the company no exclusion criteria according to points 1, 2, 3, 4, 5, 6 7, 8 and 9 of - 124 Abs. 1 GWB) Attachment 4
Documents submitted beyond the required application documents are not taken into consideration. The required information and explanations ared to issue / submit to candidate / working groups of all members of the Community. Applications for participation will only be considered upon presentation of the completed and signed application form. All documents and declarations must be up to date (not older than 6 months from the date of publication). Excluded here are the proofs of entitlementfor the title of architect / engineer. For consortia, the required documents must be provided to all members, with each member having to prove his or her suitability for the part of the service that it is supposed to undertake. The breakdown of the service components within the consortia must be indicated. As far as the applicant intendsSubmit partial services to another company or another freelancer, must provide appropriate evidence and statements for this / these who allow for this part of the aptitude test of the entrepreneur or freelancer.
A) Proof of professional liability insurance pursuant to - 45 para 4 VgV an EU Insurance company Annex 5.
With the participationapplication for proof of existing insurance must be submitted. In the case of lesser sums insured than mentioned in point III.1.2, an additional confirmation from the insurance company is required to show that the sums are raised to at least the required amount in the case of an order;
b) declaration by the applicant in accordance with - 45 (4), Sentence 4 VgV over the totalturnover (fees for specialist planning services for HLS technology) gross in million euros in the last 3 business years (2015, 2016 and 2017);
c) declaration of the applicant according to - 46 (3), sentence 8 VgV on the number of permanent employees Employees for specialist planning services of HLS technology on average for the last 3 business years (2015, 2016 and 2017) Annex 7.
The required AusIn the case of applications / working groups, the names and declarations must be given or given by all members of the community. Applications for participation will only be considered upon presentation of the completed and signed application form. All documents and declarations must be up to date (not older than 6 months from the date of publication). For consortiumThe required documents must be submitted to all members, with each member having to prove his / her suitability for the part of the service that he / she is supposed to accept. The breakdown of the service components within the consortia must be indicated. Insofar as the applicant intends to transfer partial services to another company or another freelancerFor this evaluation the suitability test of the company or self-employed person shall be provided.
For the evaluation of the participation procedure, the application must be submitted in writing to the evaluating body only. The application documents will not be returned. Free subscription to the digiFor further information, see the contact address in Section I: "Sending tender documents and supplemental documents" or directly via www.had.de.A request by e-mail stating the procedure number and the contact information is sufficient The client can make any additional information available to all applicants.
For all sorts of applicantsFormal requests can not be scored and are excluded from participation Unless otherwise stated, copies are sufficient evidence to prove that the information and evidence referred to in III.2.1 to III.2.3 are not included in the application form If required, the form of the evidence and the detailed minimum requirements are theapplication documents and this publication. The application form including the required attachments and proofs must be submitted by each member of an application community as well as by each subcontractor. - 46 para. 3, sentence 10 VgV or - 47 VgV to complete and submit
Internet address (URL): www.lahn-dill-kreis.de
Directive: Classical Directive (2014/24/EU)