Summary : Works Markets Relating to the Design, Detailed Engineering, Manufacture, Delivery, Production and Commissioning on Site of a Total Useful Power Biomass Boiler of 7 Mw Useful Envi ...
Deadline : 16 Jul 2025
Other Information
Notice Type : Tender
TOT Ref.No.: 121839834
Document Ref. No. : 422463-2025
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : EUR 3100000
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Works markets relating to the design, detailed engineering, manufacture, delivery, production and commissioning on site of a total useful power biomass boiler of 7 MW useful envi ...
The procedure concerns the design, supply, implementation, installation and In service of a biomass process set composed of: a biomass boiler of around 7 MW of total useful power, of stamp 10 bar; An area of ladders at the bottom of the pit; A biomass conveyor system; A multi cyclone or equivalent fume filtration system and Big bags recovery; A sleeve filter smoke filtration system and Big Bags fine recovery system; A fan of smoke; A sweeping system; An ash extraction system under homes per conveyor; A SNCR smoke treatment system. All of this equipment will be installed in the building defined following the attached plan in the appendix.
Works markets relating to the design, detailed engineering, manufacture, delivery, production and commissioning on site of a total useful biomass boiler of 7 MW useful approximately for the heat network operated by Dijon Energies
Doc Title: Works markets relating to the design, detailed engineering, manufacturing, delivery, production and commissioning on site of a total biomass boiler of 7 MW useful approximately for the heat network operated by Dijon Energies
Type contract: Works
Type document: Contract instructions
Reference Number: 1104110
Type contract: Works
ESTIMATED VALUE: 3100000 - EUR
Doc Title: works contracts relating to design, detailed engineering, manufacturing, delivery, production and commissioning on site of a Biomass Boiler of total useful power approximately 7 MW useful for the heat network operated by Dijon Energies
Dispatch Date: 2025-06-27
Publish Date: 2025-07-01
Submission Date: 2025-07-16