Summary : Viaduct Construction Contract at Rotunda da Amizade - 2nd Phase
Deadline : 24 Oct 2023
Other Information
Notice Type : Tender
TOT Ref.No.: 89388021
Document Ref. No. :
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Tenders are invited for Viaduct Construction Contract at Rotunda da Amizade - 2nd Phase.
Copies of the competition process: digital version, upon payment of $1, 000.00 (one thousand patacas).
Maximum deadline for execution of the work: the maximum global execution period is 550 (five hundred and fifty) working days (counting from the date of the first assignment of the work), with 5 (five) mandatory execution targets, being The:
- 1st mandatory target: completion of the pile foundations of the viaduct and stairs and boxes(1) (excluding zones x and Y)(2), with a maximum execution period of 300 (three hundred) days of work, counting from from the date of the first consignment of the work;
- 2nd mandatory target: completion of the structures of the viaduct decks and the overpass for pedestrians (excluding zone Y) and the superstructure of the stairs and boxes (1) (excluding zone Y), with a maximum execution period of 450 ( four hundred and fifty) days of work, counting from the date of the first assignment of the work.
- 3rd mandatory target: completion of the piling foundation structures of the viaduct and the retaining wall in zone of the work (the second assignment will be carried out within a maximum period of 100 working days, counting from the date of the first assignment of the work);
- 4th mandatory target: completion of the solid foundation structures of the viaduct and pillars, the structure of the retaining wall and the pile foundations and superstructure of the stairs and boxes(1) in zone Y, with the maximum execution period 160 (one hundred and sixty) working days, counting from the date of the third assignment of the work (the third assignment will be carried out within a maximum period of 260 working days, counting from the date of the first assignment of the work);
- 5th mandatory target: completion of the structures of the viaduct decks and the overpass for pedestrians and the architectural covering of the stairs and boxes(1) and the pavement under the viaduct in zone Y, with a maximum execution period of 220 ( two hundred and twenty) working days, counting from the date of the third assignment of the work (the third assignment will be carried out within a maximum period of 260 working days, counting from the date of the first assignment of the work).