Summary: Sources Sought Tangier Island Beneficial Use
Deadline: 26 Mar 2026
Posting Date: 12 Mar 2026
Other Information
Notice Type: Tender
TOT Ref.No.: 137599610
Document Ref. No.: W9123626SA002
Competition: ICB
Financier: Self Financed
Purchaser Ownership: Public
Tender Value: Refer Document
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_detailsLogin to see details
Tender Details
THIS IS A SOURCES SOUGHT NOTICE ONLY. THIS IS NOT A REQUEST FOR PROPOSALS. ALL AVAILABLE INFORMATION IS INCLUDED IN THIS NOTICE.
Purpose:
USACE is evaluating the beneficial use of shoaled sediments within the Tangier Island navigation channel. The volume of shoaled material varies depending on dredging frequency; however, the most recent survey indicates that approximately 100, 000 cubic yards are currently present within the channel. Instead of disposing of this material offshore or placing it directly along the shoreline, USACE proposes to use it for shoreline stabilization by placing it within geotextile tubes (i.e. Geotubes®). Additional details regarding sediment characteristics are provided in the Geotechnical Summary, and design information is included in the Coastal Summary sections.
The attached document contains both the Geotechnical Summary and the Coastal Summary. Please answer the survey questions below using the data from this document.
Industry Survey:
Given the details provided in the attached document, is it feasible to construct geotextile tubes given the fine grained nature of the soil and is there enough material available for the proposed design?
Geotechnical Summary Survey
Based on the fine-grained nature of the dredge material, it is feasible to fill geotextile tubes effectively?
What are the anticipated losses during the dredging and infilling process of the geotextile tubes based on our geotechnical data?
What is the expected "shrinkage" factor? Specifically, for every cubic yard of material dredged, what is the anticipated final, consolidated volume of material inside the tube?
What are the anticipated dewatering times for the geotextile tubes, particularly when filled with material having a high percentage of fines?
How long is the anticipated dewatering and consolidation period to achieve the required strength for the design?
Should additional geotechnical data be collected to better inform your an...
Notice ID: w9123626sa002
Department/Ind. Agency: dept of defense
Sub-tier: dept of the army
Office: w2sd endist norfolk
Product Service Code: y1kf - construction of dredging facilities
NAICS Code: 237990 - Other Heavy and Civil Engineering Construction
Inactive Dates: apr 10, 2026
Inactive Policy: 15 days after response date