Procurement Summary
Country: USA
Summary: Sources Sought Notice for Project Labor Aggreements Plas to Coastal Storm Risk Management Csrm for Bethany Beach and South Bethany Beach, De Csrm Beachfill, Fenwick Island, De Csrm Beachfill, Rehobo...
Deadline: 02 Nov 2026
Posting Date: 19 Oct 2026
Other Information
Notice Type: Tender
TOT Ref.No.: 151141167
Document Ref. No.: W912PM27BA005
Competition: ICB
Financier: Self Financed
Purchaser Ownership: Public
Tender Value: Refer Document
CPV Classification
45243000 - Coastal-defence works
45243300 - Sea wall construction work
45243510 - Embankment works
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_detailsLogin to see details
Tender Details
Sources Sought Notice for Project Labor Aggreements Plas to Coastal Storm Risk Management Csrm for Bethany Beach and South Bethany Beach, De Csrm Beachfill, Fenwick Island, De Csrm Beachfill, Rehoboth Beach Dewey Beach, De Csrm Beachfill
The US Army Corps of Engineers, Enterprise Dredge Delivery Center (EDDC), is soliciting comments from the construction community addressing the potential use of Project Labor Agreements (PLA) for a large-scale construction project (exceeding $35 million) within the Bethany Beach and South Bethany Beach, DE (CSRM - Beachfill), Fenwick Island, DE (CSRM - Beachfill), and Rehoboth Beach & Dewey Beach, DE (CSRM - Beachfill): areas. This procurement is for Coastal Storm Risk Management (CSRM).
Bethany Beach and South Bethany Beach, DE (CSRM - Beachfill): The work for the Bethany Beach and South Bethany Beach, CRSM projects will include periodic renourishment of the beach berm and dune to the original design template. It is estimated that approximately 532, 000 cubic yards of sand would be required to restore Bethany Beach and South Bethany Beach to the original design template and approximately 165, 000 CY of optional sand could be provided for advanced nourishment for the project. The base bid work would also include repair/replacement of dune grass, fencing and crossovers. Borrow Area E will be the source used for sand to restore this beach area and will require the use of a hopper or hydraulic cutterhead since Borrow Area E is located approximately two to three miles offshore of the Town of South Bethany.
Fenwick Island, DE (CSRM - Beachfill): The work for the Fenwick Island, CRSM project will include periodic renourishment of the beach berm and dune to the original design template. It is estimated that approximately 207, 000 cubic yards of sand would be required to restore Fenwick Island to the original design template and approximately 60, 000 CY of optional sand could be provided for advanced nourishment for the project. T...
Documents
Tender Notice