DIRECTOR OF THE MARITIME OFFICE IN GDYNIA has floated a tender for Preparation of Multi-Discipline Design Documentation for the Task Titled: "Construction of Hydrotechnical Infrastructure for the Needs of the Ej1 Investment in the Lubiatowo-Kopalino Location" Togethe.... The project location is Poland and the tender is closing on 28 Feb 2024. The tender notice number is 42282-2024, while the TOT Ref Number is 95570597. Bidders can have further information about the Tender and can request the complete Tender document by Registering on the site.

Expired Tender

Procurement Summary

Country : Poland

Summary : Preparation of Multi-Discipline Design Documentation for the Task Titled: "Construction of Hydrotechnical Infrastructure for the Needs of the Ej1 Investment in the Lubiatowo-Kopalino Location" Togethe...

Deadline : 28 Feb 2024

Other Information

Notice Type : Tender

TOT Ref.No.: 95570597

Document Ref. No. : 42282-2024

Competition : ICB

Financier : Self Financed

Purchaser Ownership : Public

Tender Value : Refer Document

Purchaser's Detail

Purchaser : DIRECTOR OF THE MARITIME OFFICE IN GDYNIA
Address: ul. Chrzanowskiego 10
Town: Gdynia
NUTS-Code: PL633
Postal Code: 81-338
Attn: Anna Szwedowicz
Phone: 48 583553333
Poland
Email :zam_pub@umgdy.gov.pl
URL :www.umgdy.gov.pl

Tender Details

Preparation of Multi-Discipline Design Documentation for the Task Titled: "Construction of Hydrotechnical Infrastructure for the Needs of the Ej1 Investment in the Lubiatowo-Kopalino Location" Together with the Supervision of the Author...

Preparation of multi-discipline design documentation for the task titled: "Construction of hydrotechnical infrastructure for the needs of the EJ1 investment in the Lubiatowo-Kopalino location" along with author's supervision

1. The subject of this public procurement is the preparation of multi-sectoral documentationji design including the construction of the MOLF (Marine Off-Loading Facility) unloading pier, i.e. a permanent marine structure with an openwork structure, for unloading indivisible oversized loads (AIL) and other large-sized materials and equipment necessary for construction and operationtion of the NPP, together with the approach track and turntable, as well as a section of a technical road with a length of approx. 20 m. As part of the order, the Contractor is obliged to perform author's supervision during the implementation of construction works. A detailed description of the subject of the order (OPZ) is attached as Annex No. 10 to the SWZ.

2.The construction of the MOLF (Marine Off-Loading Facility), i.e. a marine structure intended for unloading elements of the planned nuclear power plant in Pomerania, is of critical importance for the possibility of timely implementation of the construction of the Nuclear Power Plant and the construction of this power plant in general. MOLF constitutes them in practiceThis is a unique way to ensure delivery to the construction site of the most important power plant components, which, due to their size, can only be transported as a whole and only by sea. The Nuclear Power Plant is a strategic investment from the point of view of the interests of the energy security of the Republic of Poland...
Document Type: Contract Notice
Reference Number: ZP.371.2.2024.ASz
Contract Type: services
Authority Type: ra
Doc Title: Development of multi-discipline design documentation for the task titled: "Construction of hydrotechnical infrastructure for the needs of the EJ1 investment in the Lubiatowo-Kopalino location" along with fullcopyright supervision
Dispatch Date: 2024-01-19
Publish Date: 2024-01-22
Submission Date: 2024-02-28

Documents

 Tender Notice