Procurement Summary
Country: Canada
Summary: LN- T1R/T2R - T1B/T2B 230kV New Build
Deadline: 05 Jun 2026
Posting Date: 09 May 2026
Other Information
Notice Type: Tender
TOT Ref.No.: 140961055
Document Ref. No.: 1018450
Competition: ICB
Financier: Self Financed
Purchaser Ownership: Public
Tender Value: Refer Document
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_detailsLogin to see details
Tender Details
Scope of Work: SaskPower is seeking new construction of approximately 19km and 18km of 230kV transmission line to sectionalize the current B4R/B5R double circuit line and connect in/out to the new Tableland Switching Station. This new line will consist of direct embed 230kV double circuit galvanized H-frame structures with double-circuit twin-bundled Drake ACSR conductor. To complete the Work, a temporary bypass line will be constructed to allow one circuit of the B4R/B5R line to be energized. The by-pass work includes installation of temporary dead-end structures to facilitate sectionalizing of the B4R/B5R line, and dead-ending of overhead shield wires on B2W and B1K lines, salvage existing lattice tower structures #428 and #429, salvage the conductors and shield wires between structures #428 and #429 and deadending of shield wires on B2W 138kv at structure #16 and at structure #19 and B1K 230kV at structure #8 and at structure #14A (Structure B1K #9 is a deflection). Structure T1B/T2B #430 will be raised, this work is not part of this scope of work and will be done by others. Project Timelines: Successful achievement of Construction Completion in accordance with the requirements of the Contract no later than March 15, 2027.
Scope of Work: SaskPower is seeking new construction of approximately 19km and 18km of 230kV transmission line to sectionalize the current B4R/B5R double circuit line and connect in/out to the new Tableland Switching Station. This new line will consist of direct embed 230kV double circuit galvanized H-frame structures with double-circuit twin-bundled Drake ACSR conductor. To complete the Work, a temporary bypass line will be constructed to allow one circuit of the B4R/B5R line to be energized. The by-pass work includes installation of temporary dead-end structures to facilitate sectionalizing of the B4R/B5R line, and dead-ending of overhead shield wires on B2W and B1K lines, salvage existing lattice tower structures #428 and #429, salvage the conductors and shield wires between structures #428 and #429 and deadending of shield wires on B2W 138kv at structure #16 and at structure #19 and B1K 230kV at structure #8 and at structure #14A (Structure B1K #9 is a deflection). Structure T1B/T2B #430 will be raised, this work is not part of this scope of work and will be done by others. Project Timelines: Successful achievement of Construction Completion in accordance with the requirements of the Contract no later than March 15, 2027.
Additional Information:
This competition is available on MERX (https://www.merx4.merx.com/saskpower), and all amendments, addenda, clarifications, and further instructions will also be posted on MERX.
Competition Type: Request for Propo...
Documents
Tender Notice