Procurement Summary
Country : Philippines
Summary : Invitation to Bid for the Construction of 1-Storey, 1 -Classroom School Building at Dagatkidavao Integrated School, Dagatkidavao, Valencia City, Bukidnon
Deadline : 15 Aug 2019
Other Information
Notice Type : Tender
TOT Ref.No.: 34891395
Document Ref. No. : 19-1368
Financier : Self Financed
Purchaser Ownership : -
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Invitation to Bid for the Construction of 1-Storey, 1 -Classroom School Building at Dagatkidavao Integrated School, Dagatkidavao, Valencia City, Bukidnon
Local Government of Valencia
Catarata Street, Poblacion, Valencia City,
Bukidnon, Philippines
Philippine access (088) 828-5430
Contract Reference No. 15-2019
07/22/2019
INVITATION TO BID FOR THE CONSTRUCTION OF 1-STOREY, 1 -CLASSROOM SCHOOL BUILDING AT DAGATKIDAVAO INTEGRATED SCHOOL, DAGATKIDAVAO, VALENCIA CITY, BUKIDNON
1. The City Government of Valencia through its Annual Appropriations intends to apply the sum of One Million Pesos (Php1, 000, 000.00) being the Approved Budget of the Contract (ABC) to payments under the contract for the Construction of 1-Storey, 1-Classroom School Building at Dagatkidavao Integrated School, Dagatkidavao, Valencia City, Bukidnon. Bids received in excess of the ABC shall be automatically rejected at bid opening.
2. The City Government of Valencia now invites bids for Construction of 1-Storey, 1 -Classroom School Building at Dagatkidavao Integrated School, Dagatkidavao, Valencia City, Bukidnon. particularly describes as follows:
UNIT ITEM DESCRIPTION QTY UNIT COST TOTAL COST
1 Construction of 1-Storey, 1-Classroom School Building (8.5 x 9.0m).
SCOPE OF WORKS:
l.s Permits and Clearances 1.00 1, 050.00 1, 050.00
each Project Billboard/Signboard 2.00 4, 039.70 8, 079.39
mo. Occupational Safety and Health Program 2.00 6, 618.15 13, 236.30
l.s Mobilization / Demobilization 1.00 7, 875.00 7, 875.00
cu.m Structure Excavation 17.07 503.23 8, 590.06
cu.m Foundation Fill 9.22 429.68 3, 961.67
cu.m Gravel Fill 8.53 1, 292.65 11, 026.32
sq.m Soil Poisoning 155.26 16.26 2, 525.05
cu.m Structure Concrete, Class A-28 days 21.55 5, 139.08 110, 747.12
kg Reinforcing Steel (Deformed), Grade 33 2, 109.50 72.10 152, 103.63
sq.m Forms and Falsework 98.37 1, 113.67 109, 551.33
sq.m 4" CHB Non- Load Bearing (Machine Made) 70.94 794.16 56, 337.75
set Door Frames(Jambs, Head &Transom ) 2.00 4, 335.36 8, 670.72
sq.m Wooden Panel Doors 3.78 3, 457.56 13, 069.58
sq.m Jalousie Window ( Glass ) 11.10 1, 145.67 12, 716.95
sq.m Grille Window 16.50 1, 103.28 18, 204.11
l.s Carpentry and Joinery Works (Blackboard) 1.00 7, 638.36 7, 638.36
sq.m Plain Cement Finish with Floor Hardener 76.50 325.55 24, 904.91
sq.m Plain Cement Plaster Finish 139.66 224.90 31, 409.25
m G.I. Pipe Railings, 38mm dia. 18.00 501.18 9, 021.20
sq.m Fiber Cement Board Ceiling on Metal Frame 95.54 547.72 52, 328.76
sq.m Pre-painted Metal Sheet, Long Span, Corrugated type, above 0.427mm thk 106.92 668.51 71, 476.83
m Fabricated Metal Roofing Accessory (0.6mm thk. Ridge Roll & End Flashing) 31.70 377.71 11, 973.38
kg Structural Steel, Trusses 230.42 98.97 22, 804.31
kg Structural Steel, Purlins/Fascia 998.66 89.59 89, 473.37
pcs Metal Structure Accessories, Bolts 64.00 44.97 2, 878.03
kg Metal Structure Accessories, Steel Plates 60.59 88.58 5, 367.20
kg Metal Structure Accessories, Sag Rods 21.31 85.92 1, 830.91
kg Metal Structure Accessories, Cross Bracing 85.27 73.04 6, 228.13
pcs Metal Structure Accessories, Turn Buckle 8.00 354.88 2, 839.06
sq.m Ceiling and Masonry/Concrete Painting 235.20 227.67 53, 549.02
sq.m Wood Painting 39.29 185.32 7, 281.26
sq.m Metal Painting 165.93 38.11 6, 323.64
l.s Conduits, Boxes and Fitting 1.00 9, 129.83 9, 129.83
l.s Wires and Wiring Devices 1.00 13, 273.29 13, 273.29
set Panel Board with Main & Branch Breakers Flush Type, NEMA 1 1.00 13, 504.18 13, 504.18
l.s Lighting Fixtures 1.00 13, 882.28 13, 882.28
l.s Fire Alarm System 1.00 5, 137.85 5, 137.85
***Nothing Follows*** ABC for the Contract 1, 000, 000.00
Required number of days for completion is 60 Calendar days. Bidders should have completed a contract similar to the project within 10 years from the date of submission and receipt of the bid hereof. The description of an "eligible bidder" is contained in the bidding documents, particularly in section II. Instructions to bidders.
3. No time extension shall be granted unless on fortuitous event, acts of nature or any natural calamities.
4. Bidding will be conducted through open competitive bidding procedures usin...
Closing Date : 2019-08-15
Documents