DNR-OMM-CO#1 (Notice of Change Order) -Rosiclare Pull & Hillside Mine#1802 Tender

DNR - NATURAL RESOURCES has floated a tender for DNR-OMM-CO#1 (Notice of Change Order) -Rosiclare Pull & Hillside Mine#1802. The project location is USA and the tender is closing on 23 Apr 2019. The tender notice number is 19-422DNR-MINES-B-6964, while the TOT Ref Number is 32121222. Bidders can have further information about the Tender and can request the complete Tender document by Registering on the site.

Expired Tender

Procurement Summary

Country: USA

Summary: DNR-OMM-CO#1 (Notice of Change Order) -Rosiclare Pull & Hillside Mine#1802

Deadline: 23 Apr 2019

Other Information

Notice Type: Tender

TOT Ref.No.: 32121222

Document Ref. No.: 19-422DNR-MINES-B-6964

Financier: Self Financed

Purchaser Ownership: -

Tender Value: Refer Document

Purchaser's Detail

Name: Login to see tender_details

Address: Login to see tender_details

Email: Login to see tender_details

Login to see details

Tender Details

Project Title : DNR-OMM-CO#1 (Notice of Change Order) -Rosiclare Pull & Hillside Mine#1802

Tendor No : 19-422DNR-MINES-B-6964

Bid Opening Date : 04/23/2019 10:00:00 AM

Buyer : Zivile Scott

Location : AD001 - Abandoned Mined Lands Reclamation Division

Bid Type : OPEN Informal Bid FlagYes

Info Contact : Contact Kristi Crisman at (217)557-1236

Bulletin Desc : CHANGE ORDER NOTICE CO#1. This change order is needed to adjust the items quantities. Contract change order is required to increase the contract in the amount of $83, 580.00 for a new contract total of $762, 854.78 This change order is a 12.3% increase to the current contract amount. These circumstances were unforeseeable at the time and germane to the original contract. Change order is in accordance with 720 ILCS 5/33E-9. (ref. original contract - P-4692)

Documents

 Tender Notice


Procurement Documents for USA

Access a comprehensive library of standard procurement documents specific to USA. Here, you'll find all the essential forms, guidelines, and templates required for tender applications and submissions in USA

Explore Procurement Documents for USA


Want To Bid in This Tender?

Get Local Agent Support in USA and 60 More Countries.

View All The Services


View Tenders By


Publish Tenders


Have Any Dispute With The Purchaser?