Procurement Summary
Country: Philippines
Summary: Design, Supply and Installation of a Minimum 12.78 Kw 3-Phase Grid-Tied Solar Power System at Mlwd Warehouse and Motorpool Compound, Brgy. Balintawak, Lipa City, Batangas
Deadline: 12 May 2026
Posting Date: 06 May 2026
Other Information
Notice Type: Tender
TOT Ref.No.: 140759938
Document Ref. No.: 001-05-05-2026
Competition: ICB
Financier: Self Financed
Purchaser Ownership: Public
Tender Value: PHP 500000.00
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_detailsLogin to see details
Tender Details
Tender are invited for Design, Supply and Installation of a Minimum 12.78 kW 3-Phase Grid-Tied Solar Power System at MLWD Warehouse and Motorpool Compound, Brgy. Balintawak, Lipa City, Batangas
Procurement Mode : Negotiated Procurement - Small Value Procurement (Sec. 53.9)
Classification : Goods
Category : Power Generation and Distribution Machinery
Contract Duration : 45 Day/s
Budget for the Contract : PHP 500, 000.00
Area of Delivery : Batangas
Description : Design, Supply and Installation of a Minimum 12.78 kW 3-Phase Grid-Tied Solar Power System, MLWD Warehouse and Motorpool Compound, Brgy. Balintawak, Lipa City, Batangas
ABC : Php 500, 000.00
Project Duration : 45 Calendar Days
TERMS OF REFERENCE (TOR)
Project : Design, Supply, and Installation of a Minimum 12.78 kW 3-Phase Grid-Tied Solar Power System
Location : MLWD Warehouse and Motorpool Compound, Brgy. Balintawak, Lipa City, Batangas
Approved Budget for the Contract (ABC) : ₱ 500, 000.00)
Project Duration : 45 Calendar Days
1. Scope of Work
The Contractor shall provide end-to-end services, including but not limited to:
1.1 System Design
• Site inspection and assessment
• Load analysis and system sizing (minimum 12.78 kWp)
• Preparation of detailed engineering design and drawings
• Submission of design for approval
1.2 Supply of Materials
• Solar PV modules
• Grid-tied inverter
• D...
Documents
Tender Notice