AGUAS DO ALGARVE, S.A. has floated a tender for Contract to Reinforce the Barlavento/Sotavento Interconnection 1St Phase. The project location is Portugal and the tender is closing on 22 Mar 2024. The tender notice number is 153119-2024, while the TOT Ref Number is 98690774. Bidders can have further information about the Tender and can request the complete Tender document by Registering on the site.

Expired Tender

Procurement Summary

Country : Portugal

Summary : Contract to Reinforce the Barlavento/Sotavento Interconnection 1St Phase

Deadline : 22 Mar 2024

Other Information

Notice Type : Tender

TOT Ref.No.: 98690774

Document Ref. No. : 153119-2024

Competition : ICB

Financier : Self Financed

Purchaser Ownership : Public

Tender Value : Refer Document

Purchaser's Detail

Purchaser : AGUAS DO ALGARVE, S.A.
Address: n. 10
Town: Faro
NUTS-Code: PT150
Postal Code: 8000-302
Phone: 351 289899070
Portugal
Email :geral.ada@adp.pt
URL :www.aguasdoalgarve.pt

Tender Details

The purpose of this contract is the execution of the Reinforcement of the Barlavento/Sotavento Algarvio Interconnection, generally with the reinforcement of water transfer to the 2nd Treatment Phase of the Tavira WTP, the construction of two pumping stations (EE do Cascalho and EE da Torre ), in the Poente Aductor, the19981d172c851bd4e8a1788d5726c2d3construction of two reservoirs (Torre do Cascalho and Torre de Vale do Lobo) in the Poente Aductor, reinforcement of the Oriental-Final Aductor (1st Phase) with 5.29 km of water adduction pipelines through trench opening, in FFD piping with a diameter of 600mm and the reinforcement of the lifting capacity of the Lifting Station19981d172c851bd4e8a1788d5726c2d3of the Oriental Aductor with replacement of the impellers of the existing groups.

Contract to Reinforce the Barlavento/Sotavento Interconnection 1st Phase

The purpose of this contract is to carry out the Reinforcement of the Barlavento/Sotavento Algarve Interconnection, generally with the reinforcement of water transferua for the 2nd Treatment Phase of the Tavira ETA, the construction of two pumping stations (EE do Cascalho and EE da Torre), in the Poente Aductor, the construction of two reservoirs (Torre do Cascalho and Torre de Vale do Lobo) in the Aductor West, the reinforcement of the Eastern-Final Pipeline (1st Phase) with 5.29 km of c19981d172c851bd4e8a1788d5726c2d3water supply pipelines through trench opening, in FFD pipes with a diameter of 600mm and the reinforcement of the lifting capacity of the Eastern Aductor Pumping Station with replacement of the impellers of the existing groups,

Doc Title: Contract for Reinforcement of the Barlavento/Sotavento interconnection 1st Fa...19981d172c851bd4e8a1788d5726c2d3
Document Type: Contract Notice
Reference Number: DGA-EO.CP-EO-05/2024
Contract Type: works
Authority Type: pub-undert
Doc Title: Contract to Reinforce the Barlavento/Sotavento interconnection 1st Phase
Dispatch Date : 2024-03-11
Publish Date: 2024-03-13
Submission Date: 2024-03-2219981d172c851bd4e8a1788d5726c2d3

Documents

 Tender Notice