The TATABÁNYAI TANKERÜLETI KÖZPONT has issued a Tender notice for the procurement of a Contract notice: Refurbishment work in the Hungary. This Tender notice was published on 20 Nov 2019 and is scheduled to close on 18 Dec 2019, with an estimated Tender value of Refer Document. Interested bidders can access detailed Tender information, eligibility criteria, and complete bidding documents by referencing TOT Ref No. 38144229, while the tender notice number is 545989-2019 and Registering on the platform.

Expired Tender

Procurement Summary

Country: Hungary

Summary: Contract notice: Refurbishment work

Deadline: 18 Dec 2019

Posting Date: 20 Nov 2019

Other Information

Notice Type: Tender

TOT Ref.No.: 38144229

Document Ref. No.: 545989-2019

Competition: ICB

Financier: Self Financed

Purchaser Ownership: -

Tender Value: Refer Document

CPV Classification

45453100 - Refurbishment work
45000000 - Construction work
45110000 - Building demolition and wrecking work and earthmoving work
45210000 - Building construction work
45262700 - Building alteration work
45310000 - Electrical installation work
45350000 - Mechanical installations
45443000 - Facade work
45410000 - Plastering work
45261400 - Sheeting work

Purchaser's Detail

Name: Login to see tender_details

Address: Login to see tender_details

Email: Login to see tender_details

Login to see details

Tender Details

Object of the contract
Refurbishment work
Description: Contract notice: Refurbishment work
Authority Type: Regional or local Agency/Office
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45453100, 45000000, 45110000, 45210000, 45262700, 45310000, 45350000, 45443000, 45453100, 45410000, 45261400, 45453100, 45000000, 45110000, 45210000, 45262700, 45310000, 45350000, 45443000, 45410000, 45261400
CPV Description: Refurbishment work.
Construction work.
Building demolition and wrecking work and earthmoving work.
Building construction work.
Building alteration work.
Electrical installation work.
Mechanical installations.
Facade work.
Plastering work.
Sheeting work.
Oroszlany J.A.Alt.Iskola inf.fejlesztese
Reference Number : EKR001383562019
„Koeznevelesi intezmenyek infrastrukturalis fejlesztese a hatranykompepromoting education and quality education; Infrastructure developer of Oroszlanyi Jozsef Attila Elementary School-EFOP-4.1.2-17-2017-00085 "
Main Site: 2840 Oroszlany, Tancsics Mihaly Street 42., no. - Built-in wardrobe openings: 4 pitches
- Substrate level: 361.82 m
- Ceramic flooring: 79.31 m
- Tile flooring:102.68 m
- Laying down grooved parquet: 282.52 m
- Plastered and repaired plastered walls and ceilings: 595.40 m
- Dispersion painted walls: 2279.84 m
- Plasterboard walls: 56.34 m
Episode working section:
- Heating pipe disassembly: 18 m
- Heating pipe installation: 10 m
- Installation of compact sheet metal radiator plate, mounting of thermostatic valve head: 2 pieces
- IvoviPlumbing (Polyethylene pipe): 10 m
- Installation of PE polyethylene: 12 m
- Installation and installation of wash basin or wash basin: 2
- Installation and installation of shower tray or shower stall:
2
- Installation and installation of toilet bowl, flush tank, corner valve, toilet flush: 2 pieces
- Fitting of canal cross sections and fittings: 9 pieces
- Kueloenboizer typeentilator placement: 4 pieces
Epueletville work area:
- Extension devices: 4 pieces
- Ceiling mounted LED luminaires: 109 pieces
New construction
Construction work: 57.57 m
- Tuekoer construction: 233.08 m
- Superstructure of sandy gravel under the pavement: 139.85 m
- Superstructure of lime stone under the pavement: 46.62 m
- Structure of paving: 79.61 m
position: 43.08 m
- Reinforced concrete panel: 15.75 m
- Reinforced concrete walls and columns: 46.47 m
- Reinforced concrete extruded, beams: 13.96 m
- Shuttering reinforcement wall: 29.14 m
- Reinforced concrete : 10.8 t
- Installation of prefabricated dogwood runners: 300 m
- Athidals: 21 pieces
- Seedlings reinforced underfloor: 200.77 m
- Insulation against soil moisture: 260.60 m
- Teherhordo front wall 30 cm: 498, 45 m
- Loadbarrel masonry 30 cm: 40.33 m
- Plastering: 1032.13 m
- Insulation on baseboards and facades: 2139.14 m
- Insulation of new plastic arrow corners: 37 pcs
- Acel corner hinges acel door: 5 pieces
- Acel plasterboard door: 12 pieces
- Padlo insulated: 197.23 m
- Floored insulated: 408.78 m
- Floored subfloor: 594.01 m
- Subfloor coverings: 555.05 m
- Disperse paint for wall painton ceilings, white: 1357, 76 m
- Gypsum plasterboard walls: 162, 82 m
- Cassette ceiling, batten: 575, 92 m
Episode working space:
- Heating pipes: 484 m
- Compact sheet metal plate radiator, with brackets, fitting: 25 pieces
- PP, PE, KPE fitting, in foam grooves, with welded studs, fittings: 25 m
- Ivoviz pipes, Terhalated polyethylenepipe (PE-Xa) with pipe fitting, with threaded sleeves and threaded studs, pipe placement with pipe fittings, pipe-insulated, sectional press probe, free pipe clamps: 455 m
- PE polyethylene drain pipe with pipe holders, sectional PVC pipe, freely or bench-mounted, sleeve, rubber ring studs, pipe placement with pipe fittings, intermittent toemopower probe, free: 44 m
- Wash basin or wash basin, Shower tray or shower stall, WC cabinet placement and installation: 13 pcs
- Installation of sewerage system: 79.90 m
- Installation of heat recovery ventilation unit: 1 pcs
- Gas pipes mounting, with press studs, pipe placement with pipe fittings, intermittent press probe, freely, supporting structure nelkuel: 36 m
- Single-sided case workmaterial pipe fitting into foam grooves, rubber ring fitting, pipe fittings nelkuel: 34 m
- Concrete elements placement, groove groove, grout fitting, fitting fittings fitting: 24 pcs
- PP, PE, KPE fitting pipe fitting, welded fittings, welded m
Episode of electrical work:
- Extension of distribution units: 4 pcs
- Installation of new distribution units: 2 db
- LED Lamps: 90 pieces
- Cable Layouts: 3259 m
- Lightning Layout: 1 pieces
The detailed technical description and other specifications are included in the technical appendix to the documentation annex. AT) (koezoes AT), sub-contractor and may not be an economic operator against whom Kbt. Section 62 (1) es (Any of the grounds for exclusion listed in paragraph (2) above shall apply. Section 62 (1) - (2) specific exclusion reasons are introduced in the course of the procedure.economic buyer of the year (X.30.) Of the Government of the Republic of Hungary (hereinafter KR), by submitting the single European Co-Procurement Document (hereinafter referred to as EEKD), it is necessary to pre-certify the Kbt. Disqualification of the grounds for exclusion mentioned in - 62.
The proposing economic operator has made an attempt to disclose the statement contained in the EEKD with respect to the disqualification of the grounds for exclusionni. Master gives you garden information. The statement must include a statement that the Kbt. Article 69 (4) of the Act on the certification of the certificate to be submitted, which body is entitled, and the Kbt. 69. Paragraph (11) of the database requires the use of data and a statement to that effect. (Section 67 (1) Kbt., Section 1 and Section 3 of the KR),
If it precedesrt is suited to suit the needs of the person or body providing the offer, the form shall be provided by the person offering it in the representation of such organizations or persons. In the dogs of the organizations or persons providing their capacities, the terms of eligibility shall be limited to those which the tenderer agreesbe removed for eligibility,
In the case of a Koezoes suggestion or reelection, the economic operator who submits the offer or rejoinder shall make a statement in the representations of the co-author or reelection candidate. Article 62 (1) to (2)(c) of Article 67 (4) Kbt. Article 69 para. and - 16.
For reasons of exclusion, certificates issued prior to the commencement of co-procurement may be retrieved (used) as long ashow long the content of the breed or data contained in the certificates is correct. Unless proven otherwise, the correctness of the data will be claimed by the tenderer in the relevant statement of kueloen for this subject.and a certificate of its authenticity, as certified by the Cegbirosag, in simple masculine form, in accordance with Article 13 of the CM. The bid must include a statement by the bidder as to whether or not there is a listing process in progress.
The bidding power calls attention to Kbt. 64 of the Kbt. Article 74 (1).
Appropriate proof of suitability requirements P1) and P2) shall be obtained by submitting a statement in the EEKD, subject to the provisions of Kbt. Article 67. It is recommended that all economic operators in question comply with the requirements of Section IV of the EEKD. Thorough proof of compliance with the suitability test specified in this paragraph shall be provided with details. Capacity of other organizationsIn the event of a claim, we call the attention of Kbt. 65. Paragraphs (7) - (8) of Section 65.
In the case of P1) and P2) described below, submission of corroborated certificates shall be in the sole discretion of the Kbt. In the event of a request under Article 69 (4), the following shall apply.
Further attention is drawn to - 1 (1) and - 3 of the CR.attorney (s) shall certify the suitability of the suitably qualified person as follows:
P1) The sponsor (koezoes proposer) shall include in his account all penc solo statement depending on when AT came down and started tIf this information is available, please see the following information: Have you received a payment queuing for more than 30 days in a 12-month period from the start of the call back to your service. TV. -2 (25) favors the concept as amended.(sc), the statement contained in the EEKD is a statement of the number of business supplies (counting new or upgrading and / or upgrading existing epaulet) of three commercially completed counterparts completed at the merchant turn, depending on when the reviewer (koezoes reviewer) drankor when you started the activity, provided that these data are available.
Section 19 (3) of the KR may apply in the event of appropriate suitability of P2). . See also - 65.
All documents serving as proof of suitability must be submitted in plain language.enye:
A Kbt. Section 65 para. (1) c) of the Act: In the case of economic contractors (contractors, sub-contractors) carrying out construction work, the Contracting Authority shall require that the organizations performing the construction work referred to in the proposal shall must be included in the list of contractors who carry out construction work in the building industry or in Hungaryin the case of an established economic operator, it must be registered in the State of establishment (provided that the law of the State of establishment requires it). (X. 30.) on the basis of Article 26 (2). In accordance with paragraph 1 (a), it is a matter of reasonable considerationn In the case of an economic operator established in Hungary, the registered property is checked by the bidding authority free of charge, electronically available registration data from the ceginformation service, registration of sole proprietorships, and data of the non-registered employees of the European Union 24european parliament and doctrine iranian XI. certificate (extract) or other certificate or statement according to the registrations listed in Attachment 1
1.) Relevant aspect: Section 76 (2) para. (c) best values based on gold criteria. The maximum score for each score is also 0 to 10 points.as well as raising awareness about the opportunity to enter the Kbt. Article 71 (1) to (10) provides for cross-border cross-border referral. Rev. 1: Reverse Gold Certification, Rev. 2 and Rev. 3 straight goldsmithing, 4th dot: dot distribution, file. Methodologies. in the doc.
2.) AK on the basis of - 30 (4) of the KR, the conditions and certificates of economic and technical and professional competence of the qualified adviserk for official notes has been tightened up.
3.) Kbt. According to - 35 (8) AK does not make it possible to establish a host organization (project partnership) for the sake of the performance of the author.
4.) AK makes a mistake and makes it known. (1) - (10) Kbt.71 Sec.
5.) Proposals are subject to the submission of .jpeg or .pdf files for electronic documents in the form attached to the ECR.I must be terrible. Documents may be attached in one or more files.
6.) A statement that serves as the basis for a coexistence test (eg a disclaimer of warranties or a disclaimer of warranties) must be electronically documented in accordance with the strong private
7.) AT must attach Kbt. 66. (6) and the arrows according to - 67 (4).
8.) The offer must contain the express statement of the offeror in the Kbt. - 66. (2)
10.) The offer must be in accordance with the Kbt. 66 (2), in the original subscript regarding the terms of the contract, the test and performance of the author, and the garden counterpart.1.) Certificate of Alairas: The proposal must be accompanied by the Alairas Cimpeldanyat, an authorized representative of the AT, the sub-contractor, the holder of the certificate of aptitude (providing the capacity), alairas / dated 9/6/2006. (1). If the quotation is entitled to the quotation by the authorized representative (s), the representative must consider
12.) AT must have a policy of insurance of at least 10 million HUF / arm and 80 million HUF / year at the time of the contract test. Yes. In accordance with Section 134 (4), the AT shall release the order in accordance with Section 1334 (5) of the Civil Code.
14.For the purpose of this procedure, use Kb as an inexperienced ok. - 75 (2) para.
15.) Formal information in KB Doc. utmutatojaban.
16.) Kbt. On the basis of Section 66 para. 68. (17) In the present case, the provisions of Act 424/2017 (XII.19.) Kr. Quotations are exclusively cross-referenced in the ECRcan be entered. Documents / declarations for the submission of tenders, if not all in electronic format, must be submitted in pdf format. in the ECR half-life. AK draws attention to the following orders of the ECR: - 11 (2) - (3)), (7)
18.) Reason for excluding the quotation: The collector's item is subject to the approval of a technical unit, where the realization of the property on the basis of an epithelial permit is required, including for technical and legal reasons. possible. It should be further emphasized that the tasks related to the contract subject matter form a professionally unified whole, unequivocal liability can only be assured by continuous offer and performance.
Internet address (URL): https://kk.gov.hu/tatabanya

Documents

 Tender Notice


Similar Tenders

Request Demo
GiZ Tenders India

Procurement Documents for Hungary

Access a comprehensive library of standard procurement documents specific to Hungary. Here, you'll find all the essential forms, guidelines, and templates required for tender applications and submissions in Hungary

Explore Procurement Documents for Hungary


Want To Bid in This Tender?

Get Local Agent Support in Hungary and 60 More Countries.

View All The Services


View Tenders By


Publish Tenders


Have Any Dispute With The Purchaser?