Procurement Summary
Country: Romania
Summary: Contract notice: Coastal-defence works
Deadline: 31 Mar 2020
Posting Date: 27 Dec 2019
Other Information
Notice Type: Tender
TOT Ref.No.: 39302276
Document Ref. No.: 617343-2019
Competition: ICB
Financier: Self Financed
Purchaser Ownership: -
Tender Value: Refer Document
CPV Classification
45243000 - Coastal-defence works
71322000 - Engineering design services for the construction of civil engineering works
71328000 - Verification of load-bearing structure design services
71335000 - Engineering studies
71356200 - Technical assistance services
Purchaser's Detail
Name: Login to see tender_details
Address: Login to see tender_details
Email: Login to see tender_details
Login to see detailsTender Details
Object of the contract
Coastal-defence works
Description: Contract notice: Coastal-defence works
Authority Type: Ministry or any other national or federal authority
Contact Nature: Works
Procedure: Open procedure
Document: Contract notice
Regulation: European Union
Award criteria: The most economic tender
CPV code: 45243000, 45243000, 71322000, 71328000, 71335000, 71356200, 45243000, 71322000, 71328000, 71335000, 71356200
CPV Description: Coastal-defense works.
Engineering design services for the construction of civil engineering works.
Verification of load-bearing structure design services.
Engineering studies.
Technical assistance services. coastal erosion and ensuring an adequate degree of pro [...] details on www.elicitatie.ro
Reference Number: PAAPD_1092107
Design and execution of the component works of the coastal protection system in order to reduce the coastal erosion and to ensure an adequate degree of protection for LOT 6- Protection and rehabilitation of the Romanian Black Sea coast in the Costinesti area; LOT 7- Protection and rehabilitation of the Romanian Black Sea coast in the Olimp area; ITOT 8 - Protection and rehabilitation of the Romanian Black Sea coast in the Jupiter-Neptune area; LOT 9 - Protection and rehabilitation of the Romanian Black Sea coast in the Balta Mangalia-Venus-Aurora area; LOT 10 - Protection and rehabilitation of the Romanian Black Sea coast in the Mangalia-Saturn area; LOT 11 - Protection and rehabilitation of the Romanian Black Sea coast in area 2 MAY- within the "REDUCER"EA COASTAL EROSION, PHASE II (2014-2020) "
Main Site: Mangalia Saturn
Design and execution of the component works of the coastal protection system in order to reduce the coastal erosion and to ensure an adequate degree of protection for LOT 10 - Protection and rehabilitation of the Romanian coast. of the Black Sea in the Mangalia-Saturn area from „Reduction of coastal erosion, phase II(2014-2020) ";
The technical documentation of the design for the phases of the technical project and execution details will be elaborated, the technical studies necessary to define the solution, the technical verification, the technical assistance will be executed and the works designed according to the requirements of the Specifications will be executed. for each batch.
Works of artificial sanding of beaches and works of demulation and construction of the coastal structures.
The bidders, the third-party supporters and the subcontractors must not find themselves in the situations provided in art.164, 165, 167 of the Law no. 98 / 2016.
The manner in which the requirement can be demonstrated: the DUAE will be completed by the economic operators participating in the award procedure with the information related to their situation. DocumentelThe justifications proving the fulfillment of those assumed by completing the DUAE will be presented at the request of the contracting authority, only by the tenderer ranked on the first place in the intermediate ranking drawn up at the end of the evaluation of the offers. These documents can be: 1. Certificates confirming the lack of outstanding debts regarding the payment of taxes, taxes or contributionthe overall consolidated budget (local budget, state budget, etc.) at the time of presentation; 2. the criminal record of the economic operator and of the members of the administration, management or supervision body of the respective economic operator, or of those who have the power of representation, decision or control within it, as it results from the certifying certificate issued byONRC / the constitutive act; 3. after the case, documents proving that the economic operator can benefit from the derogations provided in art.166 paragraph (2), art.167 paragraph (2), art.171 of Law 98/2016 regarding public procurement; 4. other edifying documents, as the case may be.
Avoidance of conflict of interest
The bidder / associate bidder / subcontractor / third party supporter must not be in asituation of conflict of interests and / or unfair competition.
Compliance and applicability within the procedure:
- The bidder / associate bidder / subcontractor / third party supporter will present DUAE which confirms that the economic operator is not in any of the situations provided in art. . 59 and art. 60 of the law no. 98/2006 regarding public procurement. People with decision-making functionsie from the contracting authority regarding the organization, development and completion of the award procedure are the following: Hristu Uzun-Director, Adrian Chera-Technical Director ELH, Adela Mihalcea-Economic Director, Nela Ene-Technical Director DI, Titel Gagiu-Director SGA Constanta, Andra Mihaela Negoi, Rodica Tistea-employees ANAR, Stelica Hagi-head of the IPU service, Nicusor Buzgaru, GeorgeDamcaliu, Anca Lungu, Luiza Fratila, Cristian Fugigiu, Gigi Cocione-salaried UIP service, Constantin Sava-head of the Purchasing office, Mirella Oancea-salaried office of the Acquisitions, Gabriela Constantinescu-chief of the Legal office, Anamaria Balan, Georgiana Simona Grigoresid Juriciu, salaried Badoiu-head of the MIZC office, Dobrica Gabriel, Cerneaga Constantin-exploitation office employees.
Where the offeris submitted by an association, each associate will present the above mentioned documents. Also, these
Documents must be presented by each subcontractor / third party supporter declared by the offer.
In case the economic operator (bidder / associate bidder / subcontractor / third party supporter) is in one of the situations provided by art. 60 of Law no. 98/2016 regarding the acquisitionspublic, this will be excluded from the award procedure, the offer being rejected.
The economic operators who submit the offer must prove a form of registration in the conditions of the law of the country of residence, from which it can be seen that the economic operator is legally constituted, that it is not it is in none of the situations of cancellation of the constitution and the fact that it has the professional capacity to performIt confirms the activities that are the subject of the contract.
Confirmation documents:
- The DUAE will be completed by the economic operators participating in the award procedure with the information related to their situation. ONRC from which it can be seen that the tenderer has in the field of activityate, active ... details on www.e-licitatie.ro
Lots: 10, 11, 6, 7, 8, 9 Annual average turnover Average Annual turnover of the last three years (2016, 2017, 2018 ) must be greater than or equal to: LOT 6 580, 000, 000 RON; LOT 7 600, 000, 000 RON; LOT 8 440, 000, 000 RON; LOT 9 840, 000, 000 RON; LOT 10 500, 000, 000 RON; LOT 11 280, 000, 000 RON;
For the present procedure of atrbids can be submitted for 1 or more lots.
The duration of the mentioned contract is determined by reference to the longest execution time within the lots. The duration of the mentioned contract also includes the guarantee period.
In case two or more offers ranked on the first place have equal scores, the bidders will be asked for a new financial proposal in a sealed envelope, In case the contract will be awarded to the bidder whose new financial proposal has the lowest price. / questions / communications ") re-offering, by presenting a new financial proposal only for the biddersyou are in this situation, in order to split the offers and the one with the lowest bid will be declared the winner. The new financial proposal will be submitted only and only following the request of the Contracting Authority.
The bidders have the obligation to carefully analyze the Attribution Documentation and to prepare the offer according to all the instructions, forms, contractual and specific provisionsthe technical information contained in this Documentation. Starting with 08.04.2019, the Single European Procurement Document (DUAE) is integrated into the Electronic Public Procurement System (SICAP). The completion of the DUAE by the economic operators participating in the procedure will be done in SICAP directly, after authentication, by each participant.
The correspondence and all the documents submitted bythe economic operators will be in Romanian, or accompanied by an authorized translation in Romanian.
Requests for clarification of potential bidders will be addressed exclusively in SICAP to the section "requests for clarification / questions / communications" diwithin the award procedure carried out by electronic means.
The answers to the requests for clarifications will be posted in legal term under the "list of clarifications notifications and decisions" of the participation announcement published on the site http: //sicap-prod.e- licitatie.ro/pub.
The evaluation commission will send the requests for clarification regarding the submitted offers, in the SICAP section "requestarea of clarification / questions / communications ". The economic operators will send the answers to clarifications and any documents requested during the evaluation of offers through SICAP (Section" requests for clarification / questions / communications "), in full in the section corresponding to the respective request, in the form of one. or several separate documents / files, signed by the signatoryextended electronic hate valid, based on an unsuspected or revoked qualified certificate at the time of signing the offer in accordance with the legal provisions regarding the electronic signature. the data needed to prepare the offer.
Visit the Sitethe contract is made with the Contracting Authority, but not later than the 60th day from the date of publication of the participation notice. Potential bidders who intend to participate in site visits will announce in writing the contracting authority on the intention to do so at least 48 hours before the proposed / established date.
Internet address (URL): www.rowater.ro
Documents
Tender Notice