Summary : Berlin Lake Sewer Treatment Plant Replacement
Deadline : 26 Apr 2024
Other Information
Notice Type : Tender
TOT Ref.No.: 99737097
Document Ref. No. : W911WN24SS8016
Competition : ICB
Financier : Self Financed
Purchaser Ownership : Public
Tender Value : Refer Document
Purchaser's Detail
Purchaser : DEPT OF DEFENSE
Contracting Office Address : PITTSBURGH, PA 15222-4198
Primary Point of Contact : Aaron Barr
aaron.m.barr@usace.army.mil
Phone Number 4123957157
Secondary Point of Contact : CONNIE FERGUSON
connie.l.ferguson@usace.army.mil
Phone Number 4123957551
USA
Email :aaron.m.barr@usace.army.mil
Tender Details
Description
Berlin Lake Mill Creek Recreation Area - Wastewater Treatment Facility Replacement Project
Berlin Lake, Mahoning County, Ohio
The U.S. Army Corps of Engineers (USACE), Pittsburgh District, is carrying out a Project to replace the existing Wastewater Treatment Facility (WWTF) at the location referenced above. Work is to be performed entirely on Government property which consists of a public campground, two USACE field offices, and the existing WWTF. The campground is open annually from mid-May to mid-September, while the two USACE field offices are open year-round. The Government currently operates the existing 30, 000 gallon per day (gpd) WWTF year-round and will need continuous access and utility services to do so during the Project. The new prefabricated WWTP is to be constructed adjacent to the existing WWTP. Final conversation to the new prefabricated WWTP is required prior to demolition of the existing WWTP.
Major features and coordination efforts of the Project generally include, but are not limited to, the following:
Installing a new, prefabricated pump station and force main line. Installing a new, prefabricated WWTF with appurtenances. The prefabricated WWTF (rated at 30, 000 gpd) will utilize the extended aeration process and may have, among other features, a trash trap, flow equalization/aeration/clarifier/sludge holding/dosing tanks, fixed media and surface sand filtration, and UV disinfection. Renovating the existing WWTF control/laboratory building. Limited testing has been conducted and it is assumed that additional lead and asbestos testing/remediation may be required. Upgrading the existing power supply per local utility requirements and installation of a dedicated automatic emergency power generator. Installing gravel driveway for access and parking, lighting, and security fencing/gates. Reconfiguring portions of the existing sanitary sewer piping near the headworks and outfall manhole of the existing WWTF to acc...
Active Contract Opportunity Notice ID W911WN24SS8016 Related Notice Department/Ind. Agency DEPT OF DEFENSE Sub-tier DEPT OF THE ARMY Major Command USACE Sub Command LRD Office W072 ENDIST PITTSBURGH
General Information
Contract Opportunity Type: Sources Sought (Original)
All Dates/Times are: (UTC-04:00) EASTERN STANDARD TIME, NEW YORK, USA
Original Published Date: Apr 05, 2024 07:53 am EDT
Original Response Date: Apr 26, 2024 05:00 pm EDT
Inactive Policy: Manual
Original Inactive Date: Oct 26, 2024
Initiative: None
Classification
Original Set Aside:
Product Service Code: Y1PD - CONSTRUCTION OF WASTE TREATMENT AND STORAGE FACILITIES
NAICS Code: 237110 - Water and Sewer Line and Related Structures Construction