Procurement Summary
Country : Canada
Summary : 2019 gravel production - kennard pit (sw 30-1-26-w4) - contract no. 191-01913-00
Deadline : 04 Mar 2019
Other Information
Notice Type : Tender
TOT Ref.No.: 30878174
Document Ref. No. : AB-2019-01183
Financier : Self Financed
Purchaser Ownership : -
Tender Value : Refer Document
Purchaser's Detail
Name :Login to see tender_details
Address : Login to see tender_details
Email : Login to see tender_details
Login to see detailsTender Details
Tender are invited for 2019 gravel production - kennard pit (sw 30-1-26-w4) - contract no. 191-01913-00
Details
Category:
Research and Development (RD)
GSINS:
5131C: HIGHWAYS, (ExCEPT ELEVATED HIGHWAYS) STREETS, ROADS, RAILWAYS AND AIRFIELD RUNWAYSA: Research and Development
Region of Delivery:
Alberta
Region of Opportunity:
Canada
Agreement Type:
Tender Type:
Invitation to Tender (ITT)
Estimated Value:
Solicitation Method:
Open
Date
Published:
2019-02-20
Revised:
Closing:
2019-03-0402:00 PMAlberta Time
2019 gravel production - kennard pit (sw 30-1-26-w4) - contract no. 191-01913-00
scope of work
the work under the terms of this contract involves the crushing and stockpiling of aggregates at the kennard pit which is located in cardston county. the contractor shall work within phase 1 of the limits shown on the pit plans or as directed by the consultant.
kennard pit (sw 30-1-26-w4)
the contractor shall note that all aggregates shall be utilized, including all aggregates below the existing water table. any dewatering methods shall meet all applicable environmental regulations. extraction of the aggregate below the water table shall be required. the contractor shall pump any water encountered to a location approved by the consultant.
no separate or additional payment will be made for utilizing aggregates below the water table or for dewatering operations. payment for this work will be considered incidental to the unit price bid for the class of material produced.
the contractor shall begin crushing operations so as to deplete the designated area working to the south and then to the west. the contractor shall conduct his operations in such a manner that no material is spilled over the sides of the stockpile.
silty clay lenses may be present in the pit run aggregate within the designated area. any clay removal or adjustment of crushing methodology to deal with the clay shall be the responsibility of the contractor. no separate or additional payment will be made for the mobilization/demobilization of equipment, excavation, hauling or stockpiling of the clay in a location identified by the consultant. payment for this work will be considered incidental to the unit price bid for the class of aggregate material produced and shall not be considered as an extra work item.
the contractor shall note and be prepared to comply with section 3.2.3.1 of the standard specifications for highway construction: "all material up to and including 300 mm diameter in designated sources and department sources identified in the contract shall be crushed." any oversized rock shall be stockpiled at the stockpile site as shown on the plans or to be determined by the consultant.
kennard pit restrictions
gravel pit activities are restricted from monday to friday from 6:00am to 9:00pm.
no gravel pit activities are permitted on weekends or statutory holidays unless approved by the county.