Procurement Summary
Country : Canada
Summary : Fit-up guy favreau complex (cgf) (ef950-200489/a)
Deadline : 04 Sep 2019
Other Information
Notice Type : Tender
TOT Ref.No.: 34800828
Document Ref. No. : EF950-200489/A
Competition : ICB
Financier : Self Financed
Purchaser Ownership : -
Tender Value : Refer Document
Purchaser's Detail
Purchaser : PUBLIC WORKS AND GOVERNMENT SERVICES CANADA
Contact name
Ghali, Camille
Contact email
camille.ghali@tpsgc-pwgsc.gc.ca
Contact phone
(514) 607-2190 ( )
Contact fax
(514) 496-3822
Contact address
Place Bonaventure, portail Sud-Oues
800, rue de La Gauchetière Ouest
7e étage, suite 7300
Montréal
Québec
H5A 1L6
Canada
Tender Details
Trade agreement: ceta / cfta
tendering procedures: all interested suppliers may submit a bid
competitive procurement strategy: lowest/lower bid
comprehensive land claim agreement: no
nature of requirements:
fit-up the guy-favreau complex (cgf) (ef950-200489/ a)
project description
the project involves the complete fit-up of levels 2, 3, 4, 5 and 7 and partial fit-up of level 8 of the west tower, as well as level 7?s passageway between the west and east towers of the guy-favreau complex (cgf) to accommodate a federal minister?s offices. Works have to be carried out following green globes?s requirements in order to obtain a minimum of three ?globes?, with certification.
Cgf is an existing building whose structural and architectural systems (columns, window mullions, suspended ceiling grids, etc.) are based on metric dimensions. Specific elements, such as the birck masonry and metallic slat ceilings are part of the heritage character of the building and must be preserved.
Works include, but not limited to, the demolition of the majority of the existing architectural systems (ceilings, floor coverings, partitions, millwork, etc), selective demolition of electromechanical, material security elements and telecom elements and systems, the construction of new partitions, ceilings and floor finishes, the installation of electromechanical, material security systems adapted to the new work area?s layouts and the users? needs, as well as various finishing works.
As part of the projet, requirements from the building manager, brookfield global integrated solutions (bgis), govern access to the building and to specific parties (eg, daily checks before each shift, access approvals), use of loading and delivery docks, health and safety regulations (eg conformity of exits, evacuation, hazardous materials, etc.) as well as permitted work (eg, period, nature, equipment required, waste management, etc.). The contractor and his staff must comply with these requirements. In order to meet these requirements, some works will have to carried out during the evening and weekends.
Works by bgis such as maintenance, rehabilitations, repairs or refurbishments will occur during construction, in close proximity of the work areas. A continuous coordination with bgis is required.
there is a site visit scheduled for this project.
There will be an optional site visit (but highly recommended) on wednesday august 14th, 2019 at 10:00 (local). Bidders must proceed to the security guard station on the ground floor of complexe guy favreau (along boul. René-levesque).
mandatory criteria at closing date
- the bidder shall enclose bid security with its bid.
- security requirements:
this document contains security requirements.
The contractor/offeror must, at all times during the performance of the contract, hold a valid designated organization screening (dos) and a "document safeguarding capability (dsc)". Also, the employees of interested entrepreneurs an
Documents
Tender Notice